Loading...
HomeMy WebLinkAboutItem 1g: Accept Work by Gentry Brothers for the Rehabilitation of Westbound Huntington as Complete 4O F Ake, C.:• rig17741�emrnor.wa.., Auyur�},IYO3, ., 0., 4'"Wiry°`/� STAFF REPORT Development Services Department DATE: October 18, 2011 TO: Mayor and City Council FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director l- Philip A. Wray, Deputy Director of Development Services/City Engineer Prepared by: Tim Kelleher, Assistant Engineer SUBJECT: ACCEPT ALL WORK PERFORMED BY GENTRY BROTHERS INC. FOR THE REHABILITATION OF WESTBOUND HUNTINGTON DRIVE BETWEEN HOLLY AVENUE AND BALDWIN AVENUE AS COMPLETE AND AUTHORIZE THE FINAL PAYMENT TO BE MADE IN ACCORDANCE WITH THE CONTRACT DOCUMENTS Recommendation: Approve SUMMARY On July 19, 2011 the City Council awarded a contract to Gentry Brothers Inc. in the amount of $462,930 for the Rehabilitation of Westbound Huntington Drive between Holly Avenue and Baldwin Avenue and authorized a 10% contingency. There were three (3) change orders increasing the total contract by $26,564.20. The terms and conditions of this project have been complied with and the required work has been performed to staff's satisfaction for a final cost of $489,494.20. Staff is recommending that the City Council accept the project as complete and authorize the final payment in accordance with the approved contract documents. BACKGROUND The City's Pavement Management Program, which analyzes the existing condition of the street pavement, identified the Huntington Drive westbound lanes between Baldwin Avenue and Holly Avenue as the highest priority street for repair with a Pavement Condition Index (PCI) rating of 37 (100 being best and zero being worst). The City annually appropriates approximately $600,000 in Proposition "C" funding for arterial street pavement projects. Because Huntington Drive is extremely wide, it is difficult to fund a project of a significant length in one fiscal year, so the street was divided into two projects over two separate years. The eastbound segment of Huntington Drive was rehabilitated in the summer of 2006 and the westbound segment was completed this summer. Staff Report October 18, 2011 Page 2 DISCUSSION Work began on Thursday, August 8, 2011 and was complete by Friday August 26, 2011. There were three (3) contract change orders (see table below) increasing the contract amount by a total of $26,564.20 which is six percent (6%) over the original contract. Fifty percent (50%) of the total contract change orders was an extra cost to install conduits for fiber optic communications to traffic signals. The conduits were planned for a future Capital Improvement Project; however, staff decided to install them now before paving for efficiency and to keep future costs down. The remaining change order costs were due to unforeseen conditions, buried interfering utilities, and adjustments to bid item quantities to reflect actual quantities. CO 1 Install conduits, pull boxes and an additional $16,163.00 curb ramp CO 2 Remove (3) pressure Plate Traffic Detectors $4,580.00 CO 3 Final Quantity Adjustments $5,721.20 The contractor performed the work successfully, quickly and the structural integrity was restored to the pavement. Costs were within budget and the construction caused only minor disruption to businesses and residents. FISCAL IMPACT This project was included in the fiscal year 2010/11 Capital Improvement Program with a budget of $600,000 in Proposition C funding. Sufficient funding is budgeted for all project costs. RECOMMENDATION, That the City Council accepts all work performed by Gentry Brothers, Inc. for the Rehabilitation of Westbound Huntington Drive between Holly Avenue and Baldwin Avenue as complete and authorize the final payment to be made in accordance with the contract documents. Approved by: D -/.0 ��-►. a.� Donald Penman, City Manager JK:PAW:TK:pa