HomeMy WebLinkAbout5182
RESOLUTION NO. 5182
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ARCADIA
CHANGING THE FEES FOR BUILDING CODE VARIANCES, BUILDING
PERMITS, GRADING PLAN CHECKING, GRADING PERMITS,
PLUMBING PERMITS, PLUMBING PLAN CHECKING, ELECTRICAL
PERMITS, MECHANICAL PERMITS, MECHANICAL PLAN CHECKING,
MOVE EXAMINATION, RELOCATION PERMIT, REMOVAL PERMIT,
DEMOLITION PERMIT, SIGN PERMIT AND SWIMMING POOL
PERMIT, AND REPEALING RESOLUTION NO. 5133.
The City Council of the Ci~ of Arcadia does hereby resolve, find and
determine as follows:
SECTION 1. That the fees set forth in this resolution are necessary
for the purpose of defraying the City of Arcadia's expenditures and costs for
the purposes set forth in this resolution.
SECTION 2. Pursuant to Section 8040 of the Arcadia Municipal Code, the
fee for filing an application for a variance to the Codes shall be $122.15.
SECTION 3. Pursuant to Section 8130.5 of the Arcadia Municipal Code,
the fee for filing an application for a building permit shall be as set forth
in the following schedule:
BUILDING PERMIT FEES
Total Valuation
Fee
$1.00 to $500.00
$501.00 to $2,0000.00
$23.25
$2,001.00 to $25,000.00
$23.25 for the first $500.00 plus
$2.45 for each additional $100.00
or fraction thereof, to and
including $2,000.00.
$60.00 for the first $2,000.00 plus
$9.75 for each additional $1,000.00
or fraction thereof, to and
including $25,000.00.
$284.25 for the first $25,000.00
plus $7.40 for each additional
$1,000.00 or fraction thereof, to
and including $50,000.00.
$25,001.00 to $50,000.00
- 1 -
5182
$50,001.00 to $100,000.00
$469.25 for the first $50,000 plus
$4.90 for each additional $1,000.00
or fraction thereof, to and
including $100,000.00.
$714.25 for the first $100,000.00
plus $4.05 for each additional
$1,000.00 or fraction thereof.
$100,001.00 and up
OTHER INSPECTIONS
For an extra inspection made necessa~ due to work not being ready at
the time specified or due to work not corrected after prior written
notice:
Each $32.60
For inspection for which no fees are herein prescribed and for
emergency inspections:
For the time consumed per hour Each $32.60
With a minimum charge of 1/2 hour $16.30
SECTION 4. Pursuant to Section 8130.26(a) of the Arcadia Municipal
Code, the plan checking fee for filing an application for a grading permit
shall be as set forth in the following schedule:
GRADING PLAN CHECKING FEE
Volume
Fee
50 cubic yards or less
51 to 100 cubic yards
101 to 1,000 cubic yards
1,001 to 10,000 cubic yards
$23.25
$29.10
$34.90
$40.70
10,001 to 100,000 cubic yards
$40.70 for the first 10,000 cubic
yards, plus $16.25 for each
additional 10,000 cubic yards or
fraction thereof.
100,001 to 200,00 cubic yards
$186.95 for the first 100,000 cubic
yards, plus $9.75 for each
additional 10,000 cubic yards or
fraction thereof.
- 2 -
5182
200,001 cubic yards or more
$284.45 for the first 200,000 cubic
yards, plus $4.90 for each
additional 10,000 cubic yards or
fraction thereof.
Additional plan review required by changes, additions or revisions to
approved plans (minimum charge - 1/2 hour):
$24.40/hour
SECTION 5. Pursuant to Section 8130.26(b) of the Arcadia Municipal
Code the fee for filing an application for a grading permit shall be as set
forth in the following schedule:
GRADING PERMIT FEES
Volume
Fee
50 cubic yards or less
$23.25
$29.10
51 to 100 cubic yards
101 to 1,000 cubic yards
$29.10 for the first 100 cubic
yards plus $11.45 for each
additional 100 cubic yards or
fraction thereof.
1,001 to 10,000 cubic yards
$132.15 for the first 1,000 cubic
yards, plus $9.80 for each
additional 1,000 cubic yards or
fraction thereof.
10,001 to 100,000 cubic yards
$220.35 for the first 10,000 cubic
yards plus $44.10 for each
additional 10,000 cubic yards or
fraction thereof.
100,001 cubic yards or more
$617.25 for the first 100,000 cubic
yards plus $24.50 for each
additional 10,000 cubic yards or
fraction thereof.
OTHER INSPECTIONS
For an extra inspection made necessary due to work not being ready at
the time specified or due to work not corrected after prior written
notice:
Each $32.60
- 3 -
5182
For inspection for which no fees are herein prescribed and for
emergency inspections:
For the time consumed per hour
With a minimum charge 1/2 hour
Each $32.60
16.30
SECTION 6. Pursuant to Subsection 30.5 of Part III of Section 8220 of
the Arcadia Municipal Code the fee for filing an application for a plumbing
permit shall be as set forth in the following schedule:
PERMIT ISSUANCE
PLUMBING PERMIT FEES
1.
2.
Permit issuance fee for each permit
Where additional fixtures, or equipment have
not been included in the original permit, a
supplemental permit fee is required
UNIT FEE SCHEDULE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
For each plumbin9 fixture or trap or set
of fixtures on one trap (includin9 water,
drainage piping, and backflow protection
therefor
For each building sewer and each trailer
pa rk sewer
Rainwater systems - per drain (inside
buil di ng:
For each cesspool (where permitted)
For each private sewage disposal system
For each water heater and/or vent
For each gas piping system of one to five
outl ets
For each gas piping system over five outlets,
per outlet
For each industrial waste pretreatment inter-
ceptor, including its trap and vent, excepting
kitchen-type grease interceptors functioning
as fixture traps
For installation, alteration, or repair of
water piping and/ot water treating equipment
each
For repair or alteration of drainage or vent
piping, each fixture
For each lawn sprinkler system on anyone
meter including backflow protection devices
therefor
For atmospheric-type vacuum breakers not
included in Item 1: 1-5
Over 5, each
- 4 -
$23.25
$ 8.15
$ 6.55
$16.30
$ 6.55
$24.50
$49.00
$ 8.15
$ 8.15
$ 1.60
$13.10
$ 6.55
$ 6.55
$ 9.80
$ 8.15
$ 1.60
5182
14. For each backflow protective device other
than atmospheric-type vacuum breaker:
2 inches and smaller
over 2 inches
15. For each swimming pool piping (including
spas and hot tubs)
16. For each swimming pool "p" trap
17. For each swimming pool, spa and hot tub
water heater (including gas piping)
18. For each sewer cap and/or cesspool fill
19. For each sewer connection on property (inc-
luding each dwelling unit in a multiple
fami 1y development)
OTHER
$ 8.15
$16.30
$16.30
$ 6.55
$24.50
$ 8.15
$16.30
1. For an extra inspection made necessa~ due
to work not being ready at the time specified
or due to work not corrected after prior
written notice Each $32.60
2. For inspection of plumbing facilities for
which no fees are herein prescribed and for
emergency inspections
For the time consumed per hour Each $32.60
With a minimum charge 1/2 hour $16.30
PLUMBING PLAN CHECKING FEES
For plumbing plans which require plan checking,
a plan checking fee equal to 65~ of the plumbing
permit fee shall be paid to the Building Official
at the time plans are submitted for plan check.
SECTION 7. Pursuant to Subsection 92-4 of Part III of Section 8330 of
the Arcadia Municipal Code the fee for filing an application for an electrical
permit shall be as set forth in the following schedule.
ELECTRICAL PERMIT FEE
PERMIT ISSUANCE
1-
2.
For the issuance of each permit
For issuing each supplemental permit
SERVICES
1.
For residential service of 600 volts or
less and not over 400 amps in rating,
including one meter each
For each commercial service 200 amps or
less, including one meter each
2.
- 5 -
$23.25
$ 8.15
$ 8.15
$16.30
5182
3.
4.
For each commercial service 200 amps to
1,000 amps, including one meter each
For commercial services over 600 volts or
over 1,000 amps in rating, including one
meter each
For each additional meter
For each distribution panel
5.
6.
NEW RESIOENTIAL CONSTRUCTION
In addition to the fees for permit issuance and
services as outlined above:
1.
For each new single, duplex and multiple
family dwelling - for each square foot
of gross floor area
For buil di ngs accessory to new res identi al
buildings constructed in conjunction with
those residential buildings - for each
square foot of gross floor area
2.
OTHER CONSTRUCTION
In addition to the fees for permit issuance and
services as outlined above, fees for residential
additions and alterations and other buildings shall
be as foll ows:
For receptacle, switch, lighting outlets
First 20 each
Addi tional each
For lighting fixtures, sockets or other
lamp devices
Fi rst 20 each
Additional each
For pole or platform mounted lighting
fixtures such as tennis courts, parking lot
standards and walkway lighting fixtures
Fi rst 6 each
Additional each
For fixed residential appliances not
exceeding 1 hp, kw or kva each
For fixed factory wired non-residential
appliances not exceeding 1 hp, kw or kva each
For residential, commercial or industrial
220 or 240 volt receptacle each
NOTE: For other types of air conditioners and other
motor driven appliances having larger electrical
ratings, see POWER SCHEDULE.
1.
2.
3.
4.
5.
6.
- 6 -
$32.60
$81.65
$ 8.15
$ 8.15
$ .016
$ .009
$ .80
$ .48
$ .80
$ .48
$ 3.25
$ 1.60
$ 3.25
$ 3.25
$ 3.25
5182
POWER SCHEDULE
For motors, generators, transformers, rectifiers,
converters, capacitors and other motor driven
appliances such as heating, air conditioners, and
cooking and baking equipment:
Rating in hp, kw, kva or kvar:
1.
2.
3.
4.
5.
Up to and including 1 each
Over 1 and not over 10 each
Over 10 and not over 50 each
Over 50 and not over 100 each
Over 100 each
Note: For equipment having more than one motor, trans-
former, heater, etc., the sum of the combined ratings
may be used.
Note: These fees include all switches, circuit
breakers, contactors, thermostats, relays and other
directly related control equipment.
BUSWAYS
For trolley and plug-in type busways - each 100
feet or fraction thereof
SIGNS
Signs, outline lighting and marquees
1.
2.
For one sign and one branch circuit each
For addi tional branch ci rcui ts each
CARNIVALS, CHRISTMAS TREE LOTS, FOREWORKS STANDS,
SALES LOTS, ETC.
1.
For electric generators and electrically
driven rides each
For mechanically driven rides and walk
through attractions with lighting each
For arena and booth lighting each
For Christmas tree lots, fireworks stands,
sales booths, etc., each
2.
3.
4.
- 7 -
$ 4.05
$ 8.15
$20.45
$40.80
$65.30
$ 4.90
$32.60
$ 3.25
$ 8.15
$ 4.05
$ 4.05
$16.30
5182
TEMPORARY POWER
1. For temporary service pole or pedestal
installed in conjunction with temporary
buil di ngs each $32.60
2. For temporary service pole and one distri-
bution system for construction sites each $16.30
3. For additional distribution panels installed
in conjunction with temporary power poles each $ 8.15
SWIMMING POOLS, SPAS, HOT TUBS, ETC.
1. For not more than one sub panel, three motors,
integral lighting fixtures and all wiring and
lighting for operation of same $40.80
NOTE: For additional electrical outlets or equipment,
see OTHER CONSTRUCTION or POWER SCHEDULE
OTHE R IN SPECTI ON
1. For an extra inspection made necessary due to
work not being ready at the time specified or
due to work not corrected after prior written
not ice each $32.60
2. For inspection of electrical equipment for
which no fees are herein prescribed and for
emergency inspections
For the time consumed
per hour $32.60
Wi th a mi nimum charge of
1/2 hour $16.30
ELECTRICAL PLAN CHECKING FEES
When service switch size exceeds 400 amps or 300
volts or when connected load exceeds 400 amps, a
plan checking fee equal to 65t of the electrical
permit fee shall ber paid to the Building Official
at the time plans are submitted for plan check.
ANNUAL ELECTRICAL MAINTENANCE PERMIT
$45.70
NOTE: Maintenance permits are only issued to manu-
facturing plans, commercial establishments, hospitals
and similar occupancies having duly licensed journeymen
electricians as permanent employees.
- 8 -
5182
This annual permit does not absolve the organization
fran any fees, inspections or other requirements of this
Code as pertains to electrical installations.
SECTION 8. Pursuant to Section 8432 of the Arcadia Municipal Code the
fee for filing an application for a mechanical permit shall be as set forth in
the following schedule.
MECHANICAL PERMIT FEES
PERMIT ISSUANCE
1.
2.
For the issuance of each permit
For issuing each supplemental permit
$23.25
$ 8.15
UNIT FEE SCHEDULE
1. For the installation or relocation of each
forced-air or gravity-type furnace or burner,
including ducts and vents attached to such
appliance, up to and including 100,000 Btu/h $ 9.80
2. For the installation or relocation of each
forced-air or gravity-type furnace or burner,
i ncludi ng ducts and vents attached to such
appliance, over 100,000 Btu/h $12.25
3. For the installation or relocation of each
floor furnace, including vent $ 9.80
4. For the installation or relocation of each
suspended heater, recessed wall heater or
floor mounted unit heater $ 9.80
5. For the installation, relocation or replace-
ment of each appliance vent installed and not
included in an appliance permit $ 4.90
6. For the repair of, alteration of, or addition
to each heating appliance, refrigeration unit,
cooling unit, absorption unit, or each heating
cooling, absorption or evaporative cooling
system, including installation of controls
regulated by this code $ 9.80
7. For the installation or relocation of each
boiler or compressor to and including three
horsepower, or each absorption system to and
including 100,000 Btu/h $ 9.80
8. For the installation or relocation of each
boiler or compressor over 3 horsepower to
and including 15 horsepower or each absorption
system over 100,000 Btu/h and including
500,000 Btu/h $18.00
9. For the installation or relocation of each
boil er or canpressor over 15 horsepower to
and including 30 horsepower or each absorp-
- 9 -
5182
tion system over 500,000 Btu/h to and
including 1,000,000 Btu/h $24.50
10. For the installation or relocation of each
boil er or compressor over 30 horsepower to and
including 50 horsepower, or for each absorption
system over 1,000,000 Btu/h to and including
1,750,000 Btu/h $36.75
11. For the installation or relocation of each
boiler or refrigeration compressor over 50
horsepower, or each absorption system over
1,750,000 Btu/h $61.25
12. For each air-handling unit to and including
10,000 cubic feet per minute, including ducts
attached thereto $ 7.35
NOTE: This fee shall not apply to an air-
handling unit which is a portion of a factory
assembled appliance, cooling unit, evaporative
cooler or absorption unit for which a permit is
required elsewhere in this code.
13. For each air-handling unit over 10,000 cfm $12.25
14. For each evaporative cooler other than
portable type $ 7.35
15. For each ventilation fan connected to a
sing 1 educt $ 4.90
16. For each ventilation system which is not a
portion of any heating or air conditioning
system authorized by a permit $ 7.35
17. For the installation of each hood which is
served by mechanical exhaust, including ducts
for such hood $ 7.35
18. For the installation or relocation of each
domestic-type inci nerator $12.25
19. For the installation or relocation of each
commerci al or i ndu stri al-type i nci nerator $48.95
20. For each appliance or piece of equipment
regulated by this code but not classed in
other appliance categories, or for which no
other fee is listed in this Code $ 7.35
OTHER INSPECTIONS
For an extra inspection made necessary due to work
not being ready at the time specified or due to work
not corrected after prior written notice each $32.60
For inspection for which no fees are herein
prescribed and for emergency inspection:
For the time consumer per hour $32.60
Wi th a mi nimum charge 1/2 hour $16.30
- 10 -
5182
MECHANICAL PLAN CHECKING FEES
For mechanical plans which require plan checking,
a plan checking fee equal to 65% of the mechanical
permit fee shall be paid to the Building Official at
the time plans are submitted for plan check.
SECTION 9. pursuant to Section 8632.4 of the Arcadia Municipal Code
the fee for filing an application for a move examination shall be eight dollars
and fifteen cents ($8,15) for each one hundred (100) square feet or fraction
thereof of floor space, whether usable or not, contained within the building
proposed to be relocated.
SECTION 10. pursuant to Section 8633 of the Arcadia Municipal Code the
fee for fIling an application for a relocation permit shall be $13.10 per one
thousand dollars ($1,000.00) valuation, or fraction thereof, of the building to
be relocated, For the purpose of computing such fee, valuation shall include
the reasonable cost of moving such structure and the reasonable value of all
new construction, alterations, additions, repairs, replacements and foundations
in connection therewith.
SECTION 11. Pursuant to Section 8642 of the Arcadia Municipal Code the
fee for filing an application for a removal permit shall be $171.40.
SECTION 12. pursuant to Section 8652 of the Arcadia Municipal Code the
fee for filing an application for a demolition permit shall be as set forth in
the following schedule:
DEMOLITION PERMIT FEE
Square footage of Building
500 sq. ft. or less
501 to 1,000 sq. ft.
1,001 to 3,000 sq. ft.
3,001 to 10,000 sq. ft.
10,001 sq. ft, or more
Fee
$13.10
$24.50
$40.80
$57.20
$130.65
SECTION 13. Pursuant to Section 8712 of the Arcadia Municipal Code the
fee for filing an application for a sign permit shall be the same as required
for a building of equivalent valuation and shall also include a plan check fee
which shall be 50 percent of the permit fee.
- 11 -
5182
SECTION 14. Pursuant to Section 8742 of the Arcadia Municipal Code the
fee for filing an application for a swimming pool permit shall be the same as
required for a building of equivalent valuation. The valuation shall be
calculated at the rate of $138.85 per perimeter foot of the swimming pool
and/or spa.
OTHER INSPECTIONS
For an extra inspection made necessary due to work not being
ready at the time specified or due to work not corrected after
prior written notice
Each
$32.60
For inspection for which no fees are herein prescribed and
for emergency inspections
For the time consumed per hour each $32.60
With a minimum charge of 1/2 hour $16.30
SECTION 15. This Resolution shall become effective August 1, 1984.
SECTION 16. Neither the adoption of this resolution nor the repeal
hereby of any resolution shall in any manner be construed as affecting any such
fee, nor to affect the validity of any bond or cash deposit in lieu thereof,
posted, filed or deposited therefor and all rights and obligations thereunder
appertaining shall continue in full force and effect.
SECTION 17. If any section, subsection, sentence, clause, phrase or
portion of this resolution is, for any reason, held to be invalid or
unconstitutional by the decision of any court or competent jurisdiction, such
decision shall not affect the validity of the remaining portions of this
resolution. The City Council of the City of Arcadia hereby declares that it
would have adopted this resolution and each section, subsection, sentence,
clause, phrase or portion thereof irrespective of the fact that anyone or more
sections, subsections, sentences, clauses, phrases or portions be declared
i nvali d or unconstitutional.
SECTION 18. The City Council hereby finds that the fees specified in
this resolution will not produce an amount in excess of that estimated to fund
the operation of the City of Arcadia Building Division. Based on the
foregoing, the City Council hereby finds this resolution is exempt from the
requirements of the California Environmental Quality Act as specified in Title
14 Section 15079.1 of the California Administrative Code.
SECTION 19. The City Clerk shall certify to the adoption of this
resolution.
- 12 -
5182
Passed, approved and adopted this 1
, 1984.
ATTEST:
~l~
City Clerk of the City of Arcadia
STATE OF CAt. IFORN IA )
COUNTY OF LOS ANGELES) SS:
CITY OF ARCADIA )
I, CHRISTINE VAN MAANEN, City Clerk of the City of Arcadia, hereby
certify that the following Resolution No. 5182 was passed and adopted by the
City Council of the City of Arcadia, signed by the Mayor and attested to by the
City Clerk at a regular meeting of said Council on the ~ 7th day of July
1984, and that said Ordinance was adopted by the followIng vote, to-wit:
AYES:
NOES:
ABSENT:
Councilmen Gilb, Lojeski, Pellegrino, Young and Hannah
None
None
~~~-
- 13 -
5182