HomeMy WebLinkAboutC-2219PROJECT NO. 5441036
CONTRACT FOR THE
CITY OF ARCADIA
Rehabilitation of E/B Huntington Drive
from Holly Avenue to Westerly City Limit
and Sidewalk Gap Closure
1. PARTIES AND DATE.
This Contract is made and entered into this day of �� 2006, by and
between the CITY OF ARCADIA (hereinafter called the "Owner") and SILVIA CONSTRUCTION,
INC. (hereinafter called the "Contractor').
2. RECITALS.
2.1 The Owner is a charter City organized under the laws of the State of California, with
power to contract for services necessary to achieve its purpose;
2.2 Contractor, in response to a Notice Inviting Bids issued by Owner on April 2006, has
submitted a bid proposal for the Rehabilitation of E/B Huntington Drive from Holly Avenue to Golden
West Avenue and Sidewalk Gap Closure project described in the Contract.
2.3 Owner has duly opened and considered the Contractor's bid proposal, and duly
awarded the bid to Contractor in accordance with the Notice Inviting Bids and the other Bid
Documents, and has given written notice to Contractor on May 17, 2006.
2.4 Contractor has obtained, and delivers concurrently herewith, Performance and
Payment Bonds and evidences of insurance coverage as required by the Contract.
3. TERMS.
3.1 Incorporation of Documents.
This Contract includes and hereby incorporates in full by reference the following documents,
including all exhibits, drawings, specifications and documents therein, and attachments and
addenda thereto:
a. Notice Inviting Bids
b. Instructions to Bidders
C. Contract Bid Forms
d. Contract
e. Contract Appendix
Part "A"
- General Conditions
Part "B"
- Supplementary General Conditions
Part "C"
- Special Provisions
Part "D"
- Specifications
Part "E"
- Drawings (under separate cover)
CONTRACT -1
PROJECT NO. 5441036
Part "I"' Performance Bond
Part "G" Payment Bond
Part "H" Escrow Agreement for Security
Deposits (optional)
f. ADDENDUM NO. dated
The above documents, including the General Conditions, are an integral part of the Contract
Documents. In addition to signing this Contract, Contractor shall initial this paragraph immediately
below acknowledging that he or she has read, understood and agrees with all of the terms of the
Contract Documents, including, but not limited to, provisions of the General Conditions relating to
indemnification, insurance, standards of performance, termination, compensation and time of the
essence performance. Contractor shall not disclaim knowledge of the meaning and effect of any
term or provision of the Contract Documents, and agrees to strictly abide by their meaning and
intent. In the event that Contractor fa" Initial below, the Owner shall have the right to
declare the Contract unexecuted d t award the Contract to another contractor in
accordance with state law. v
3.2 Contractor's trtasicP uougaiioe•
Contractor promises and agrees, at its own cost and expense, to furnish to the Owner all
labor, materials, tools, equipment, services, and incidental and customary work for the construction
of Project No. 5441036 necessary to fully and adequately complete Rehabilitation of E/B Huntington
Drive from Holly Avenue to Westerly City Limit and Sidewalk Gap Closure project including any
alternates selected by the Owner, and all structures and facilities described in the Contract
(hereinafter the "Work "), for a total Seven Hundred Sixty Nine Thousand Six Hundred Twenty Two
Dollars and Seventy Five Cents ($769,622.75) as specified in the Contract Bid Forms submitted by
the Contractor in response to the above referenced Notice Inviting Bids. Such amount shall be
subject to adjustment in accordance with the applicable terms of this Contract. All Work shall be
subject to, and performed in accordance with the above referenced documents.
3.3 Standard of Performance.
Contractor shall perform all Work under this Contract in a skillful and workmanlike manner,
and consistent with the standards generally recognized as being employed by professionals in the
same discipline in the State of California. Contractor represents and maintains that it is skilled in the
professional calling necessary to perform the Work. Contractor warrants that all employees and
subcontractors shall have sufficient skill and experience to perform the Work assigned to them.
Finally, Contractor further represents that it, its employees and subcontractors have all licenses,
permits, qualifications and approvals of whatever nature that are legally required to perform the
Work, and that such licenses and approvals shall be maintained throughout the term of this
Contract.
3.4 Period of Performance.
Contractor shall have ten (10) Calendar Days from the date of notice of award to supply
owner will all the required documents and certifications. Upon receipt of correctly executed
documents and certifications, the owner shall issue a Notice to Proceed. The contractor shall
perform and complete all Work under this contract. Work shall commence within ten (10) days of
CONTRACT -2
PROJECT NO. 5441036
the Notice to Proceed and be completed within 35 calendar days beginning ten (10) days after the
date on which the Notice to Proceed is sent by the owner. Moreover, Contractor shall perform its
Work in strict accordance with any completion schedule, construction schedule or project milestones
developed pursuant to provisions of the Contract, including but not limited the Project Schedule
located in the Specifications. Also, the work performed under this contract shall be done between
June 19, 2006 and August 25, 2006.
Contractor agrees that if such Work is not completed within the aforementioned period
and/or pursuant to any such completion schedule, construction schedule or project milestones
developed pursuant to provisions of the Contract, including but not limited to the Project Schedule >'
located in the Specifications, it is understood, acknowledged and agreed that the Owner will suffer
damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the Owner as
fixed and liquidated damages the sum of SEVEN HUNDRED TWENTY DOLLARS AND ZERO '
CENTS ($720.00) PER DAY as provided by the applicable provisions of the General Conditions,
found in Part "B" of the Contract Appendix.
3.5 Owner's Basic Obligation.
Owner agrees to engage and does hereby engage Contractor as an independent contractor
to furnish all materials and to perform all Work according to the terms and conditions herein
contained for the sum set forth above. Except as otherwise provided in the Contract, the Owner {
shall pay to Contractor, as full consideration for the satisfactory performance by the Contractorof the
services and obligations required by this Contract, the above referenced compensation in
accordance with compensation provisions set forth in the Contract. 'rk
3.6 Contractor's Labor Certification.
Contractor maintains that he is aware of the provisions of Section 3700 of the California;
Labor Code which require everyemployerto be insured against liability for Worker's Compensation
or to undertake self- insurance in accordance with the provisions of that Code, and agrees to comply h
with such provisions before commencing the performance of the Work. A certification form for this 'I
purpose is attached hereto as Exhibit "A" and incorporated herein by reference, and shall be
executed simultaneously with this Contract.
3.7 Attomevs' Fees.
If either parry commences an action against the other party, either legal, administrative or
otherwise, arising out of or in connection with this Contract, the prevailing party in such action shall
be entitled to have and recover from the losing party reasonable attorneys' fees and all other costs
of such action.
3.8 Successors.
The parties do for themselves, their heirs, executors, administrators, successors, and
assigns agree to the full performance of all of the provisions contained in this Contract. Contractor
may not either voluntarily or by action of law, assign any obligation assumed by Contractor
hereunder without the prior written consent of the Owner.
CONTRACT -3
PROJECT NO. 5441036
3.9 Notices.
All notices hereunder and communications regarding interpretation of the terms of the
Agreement or changes thereto shall be provided by the mailing thereof by registered or certified
mail, return receipt requested, postage prepaid and addressed as follows:
Contractor
Silvia Construction Inc.
9007 Center Avenue
Rancho Cucamonga CA 91730 -5311
Attn: Joseph W. Silvia
President
Surety �a
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
801 NORTH BRAND BLVD., SUITE PENTHOUSE
GLENDALE, CA 91203
W,.
Attn: STEVEN DRAKE /DONNA KELLYi,l
Owner With Copies To:
*ti
City of Arcadia
Class BY:
240 W. Huntington Drive
Arcadia, CA 91007
ha^
Attn: Phil Wray
568194 City Attorney,
City Engineer
Any notice so given shall be considered received by the other party three (3) days after
jl
deposit in the U.S. Mail, first class postage prepaid, addressed to the party at the above address.
Actual notice shall be ed adeq�u to notice on th ctual notice occurred, regardless of the
method of service /'
p
�f
CONTRACTOR ITY OF ARCADIA
By' By:
Na Name
��,
ESIDENT, JOSEPH W. SILVIA
itle Title
A
Ta t.D. Number: Aft t: 0 `
r�
33- 0348408 By:
Number Vida o man
Chief Deputy City Clerk
Contractor's License: Approved as to form:
Class BY:
Stephen P. Deitsch
ha^
568194 City Attorney,
Number
jl
CONTRACT -4
t
,
PROJECT NO. 5441034
EXHIBIT "A"
CERTIFICATION
LABOR CODE - SECTION 1861
I, the undersigned Contractor, am aware of the provisions of Section 3700 et seq. of
the California Labor Code which require every employer to be insured against liability for
Worker's Compensation orto undertake self- insurance in accordance with the provisions of
the Code. I agree to and will comply with such provisions before commencing the Work
governed by this Contract.
Name of Contra r. SILV Ci
By:
SEPH W. SILVIA
Name
PRESIDENT
Title
MAY 22, 2006
Date
CONTRACT (EXHIBIT A)