HomeMy WebLinkAboutItem 2h: Reject the bids for the renovation of Cay Mortenson Library Auditorium and re-bid the contract.1111100 - , 1 Public Works Services Department TO: Honorable Mayor and City Council FROM: Tom Tait, Public Works Services Director By: Dave McVey, General Services Superintendent SUBJECT: REJECT THE BIDS FOR THE RENOVATION OF CAY MORTENSON LIBRARY AUDITORIUM PROJECT AND DIRECT STAFF TO RE -BID THE CONTRACT Recommendation: Approve Al IMM®RY The Fiscal Year 2012 -13 Capital Improvement Plan Budget includes a construction project to renovate the Cay Mortenson Library Auditorium. A formal bid was conducted to solicit bids for the project and on October 16, 2012, eight responsive bids were received. However, all bids came out significantly higher than the project's approved budget. In order to reduce project bid costs, the project's scope of work will need to be scaled down. Therefore, it is recommended that the City Council reject the bids submitted for the renovation for Cay Mortenson Library Auditorium Project and direct staff to re -bid the project. DISCUSSION The Cay Mortenson Library Auditorium is over 50 years old and is in need of improvements to the audiovisual and lighting system for the facility. The Auditorium is used extensively for Library programs, including activities for community groups and organizations highlighting uses for civic, cultural, charitable, intellectual, and educational programs and community functions. The Auditorium's existing electrical panel, overhead lighting, audiovisual equipment, and interior design have not been improved for more than 50 years since the facility was built. Current technology has surpassed the functionality of the Auditorium. As a result, performances and instructional presentations have become increasingly challenging due to the limited capabilities of the Auditorium's outdated audio visual and lighting systems. The most essential proposed improvements include energy efficient equipment and energy efficient lighting fixtures and bulbs. In addition, the facility would Honorable Mayor and City Council November 6, 2012 Page 2of3 benefit from aesthetic improvements such as painting, replacement of the carpet and vinyl flooring, structural improvements to the entry way into the auditorium, and new kitchen cabinets. In order to address all these renovation issues, the Fiscal Year 2012 -13 Capital Improvement Plan Budget included a construction project to renovate the Cay Mortenson Library Auditorium in the amount of $160,000. A Notice Inviting Bids was published in the City's adjudicated newspaper and bid packages were distributed to area contractors. The City Clerk received nine sealed bids on October 16, 2012, with the following result: IBN Construction Inc. MDE Group Inc. Lundgren Builders G2K Construction Inc. Mallcraft Inc. Western Alta Construction Cal -City Construction Inc. Fast -Track Construction Corp. Magic Hammer Development, Inc. Location Orange, CA Riverside, CA Valencia, CA Encino, CA Pasadena, CA Tustin, CA Cerritos, CA Culver City, CA Tarzana, CA $293,550 $297,852 $343,843 $345,000 $358,000 $358,534 $360,128 $445,340 Non - responsive Nine bids were received for this solicitation, however, after the bids were received, one bidder, Magic Hammer Development, Inc., withdrew their bid submittal because they forgot to include the material costs in their bid proposal, which was required in the bid specifications. The Fiscal Year 2012 -13 Capital Improvement Plan budget for the renovation of Cay Mortenson Library Auditorium Project is $160,000, which is significantly less than the bid amounts that were received. In order to stay within the project's approved budget, the scope of work from the original bid specifications will need to be scaled down to only include the major components of the renovation project, which affect the functionality of the auditorium. As such, the new scope of work will focus on the upgrade of the existing audio /visual and lighting systems, and the installation of new sound proofing in the auditorium. All the bid costs received for this project went over the Fiscal Year 2012 -13 Capital Improvement Plan's approved budget for this project. Therefore, it is recommended that the City Council reject all bids and direct staff to scale down the project to include only necessary improvements that will improve the audio visual and lighting systems and to re -bid the project. A few of the other components that were previously included in the design will be listed as bid alternates. If the bids come in low, these components can be included, otherwise they will be included as an additional phase should that be the direction. Honorable Mayor and City Council November 6, 2012 Page 3 of 3 Ja6w, OlTJUU4ffl $160,000 has been budgeted from Fiscal Year 2012-13 Capital Improvement Plan Budget for the Renovation of Cay Mortenson Library Auditorium Project. It is recommended that the City Council approve the following: 1. Reject all bids for the Renovation of Cay Mortenson Library Auditorium Project. ?I"-_TqTT94 "s- � �00 Ad Dominic Lazzarefto City Manager