Loading...
HomeMy WebLinkAboutItem 2d: Contract with Vargas Olson Ent., Inc. for Construction Maintenance Services at various City facilities.DATE: January 15, 2013 Public Works Services Department TO: Honorable Mayor and City Council FROM: Tom Tait, ' Public Works Services Directory By: Dave McVey, General Services Superintendent SUBJECT: AUTHORIZE THE CITY MANAGER TO EXECUTE A ONE YEAR CONTRACT EXTENSION WITH VARGAS OLSON ENTERPRISES, INC. FOR CONSTRUCTION MAINTENANCE SERVICES AT VARIOUS CITY FACILITIES IN THE AMOUNT NOT TO EXCEED $105,770 Recommendation: Approve On February 1, 2011, the City Council authorized the City Manager to execute a one year agreement with optional contract extensions to Vargas Olson Enterprises, Inc. for construction maintenance services at various City facilities. Vargas Olson Enterprises, Inc. is reaching the end of their first contract extension and has submitted a written offer to extend the existing contract for an additional year with no increase in pricing. Based on the excellent service provided by Vargas Olson Enterprises, Inc, during previous years, it is recommended that the City Council authorize the City Manager to execute a one year contract extension with Vargas Olson Enterprises, Inc. for construction maintenance services at various City facilities in the amount not to exceed $105,770. The Public Works Services Department is responsible for the maintenance of all City facilities, which includes preventative maintenance programs at City parks and all City owned facilities. As part of the City's ongoing facilities maintenance program, the construction maintenance services contract allows the contractor to conduct a variety of scheduled and unscheduled building improvements which are funded through the Capital Improvement Program (CIP) and each department's operations and maintenance budget. In addition, the construction maintenance services contract allows for any extraordinary services, such as emergency responses for sanitary sewer overflows, which can cause damage to public facilities and/or private homes. Honorable Mayor and City Council January 13, 2013 Page 2 of 2 The current Vargas Olson Enterprises, Inc. contract amount is a "not-to-exceed" amount. The work performed is based on Capital Improvement Projects and extraordinary repair work needed throughout the year. Vargas Olson Enterprises, Inc. is reaching the end of their first contract extension and has submitted a written offer to extend the existing contract for an additional year with no increase in pricing. Based on their excellent service in previous years, it is recommended that the City Council approve a one year contract extension to Vargas Olson Enterprises, Inc. for construction maintenance services at various City facilities in the amount not to exceed $105,770. WRWRENOM Sufficient funds have been budgeted in the 2012-13 Capital Improvement Program and funds are budgeted in each department's Operating and Maintenance budget accounts for facility maintenance. W Ax 90 D A a -M I • I Award a one year contract extension with Vargas Olson Inc. for construction: services maintenance at various City facilities in the amount not to exceed $105,770. 2. Authorize the City Manager and City Clerk to execute a contract amendment in a form approved by the City Attorney. MR16= Dominic Lazzarettb--' City Manager