HomeMy WebLinkAboutItem 2b: Accept the City Hall Interior Renovation Project.'. GQ�LIFORN
—�9
F
mco�oo.aica
Au6usf 5, 1903
STAFF REPORT
Development Services Department
DATE: April 2, 2013
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager /Development Services Director
Philip A. Wray, Deputy Director of Development Services /City Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY VARGAS OLSON
ENTERPRISES FOR THE CITY HALL INTERIOR RENOVATION
PROJECT AS COMPLETE
Recommended Action: Approve
SUMMARY
On July 17, 2012, the City Council awarded a contract to Vargas Olson Enterprises in
the amount of $257,673, plus a 10% contingency, for City Hall Interior Renovation.
There were six (6) change orders for extra work, increasing the contract by $66,133.
Although the change order amount is above the 10% initially approved by the City
Council, it is within the guidelines of the City's Standard Specifications for Public Works
Construction, and the State Public Contracts Code. The work was determined to be
necessary, critical, and timely to the finished product. The contractor's prices are
competitive and the total cost is within the overall project budget. The terms and
conditions of this project have been complied with, and the required work has been
performed to staff's satisfaction, for a final cost of $323,806. It is recommended that the
City Council accept the project as complete, and authorize the final payment in
accordance with the approved contract documents.
BACKGROUND
The City Hall Interior Renovation project is Phase 2 of the City's overall City Hall
Renovation Plan. The scope of work for the interior renovation included the following:
1. Carpet throughout all buildings
2. Tile flooring in the entry lobby
3. Wall covering in the main hallway
4. Painting throughout all buildings
5. Door replacement in the main hallway
6. Baseboards in various locations
Final City Hall Interior Renovation
April 2, 2013
Page 2
7. Abatement of hazardous materials in flooring and paint
8. Miscellaneous door removal and wall construction
Bids were opened for the project on July 3, 2012, and the City Council awarded a
contract to Vargas Olson Enterprises in the amount of $257,673 on July 17, 2012.
DISCUSSION
Construction began in late August 2012, and continued into February 2013. The project
was divided into eight (8) phases to accommodate staff relocations for each phase
within the building. As the furniture was cleared out of each phase, unforeseen
conditions were exposed, such as:
• Old communications, data, and electrical lines and boxes
• Unneeded vents and openings in the walls
• Missing baseboards
• Damaged or mismatching wall surfaces and textures
• Additional areas of hazardous flooring materials
• Uneven floors
• Unnecessary partitions, shelves, and panels
Additional demolition, clean up, and restoration work was requested of the contractor to
address these items. In addition, two rooms were added to the project that were not in
the original scope: the Cashier's safe /storage room, and the utility room in the City
Manager's wing of lower City Hall.
On October 31, 2012, the City Council, at a special workshop, considered changes to
the lower City Hall Administrative Services Department wing and gave staff direction to
proceed with the work. This involved moving the main entrance and public lobby area
to the south end of the building so that it matches the City Manager's main entrance.
Staff worked with the contractor to integrate the changes into the scheduled demolition
and restoration for that phase of the project. The extra work consisted of the following:
• Demolition of one wall
• Relocation of one door
• Removal of one exterior door (inside wall only)
• Installation of two new walls and a new door
• Various electrical, data, communications, fire sprinkler, and ceiling relocations
and repairs
The contractor's quality of work was excellent and his willingness to work with the City
and around normal City Hall business functions was Exceptional. The total amount of all
additional work is $66,133. The costs for the additional work are in line with the costs
and hourly rates in the original bid.
Final City Hall Interior Renovation
April 2, 2013
Page 3
This brought the total contract to $323,806, still below the Engineers Estimate for the
project of $350,000.
FISCAL IMPACT
The FY 2012 -13 Capital Improvement Program budget for the City Hall Interior
Renovation project was combined with the Exterior Renovation Project (Phase 3), with a
total budget of $895,000. All Phase 2 work, which included other items like moving
expenses, abatement services, communications and electrical, storage bin rentals,
signage, artwork, partitions, and furniture, was estimated at approximately $595,000.
This total contract, including the change orders, is $323,806, which is within the
budgeted amount. Contracts for signage, artwork, and additional furniture are still
outstanding, but will also be within the original budgeted amount.
RECOMMENDATION
That the City Council accept all work performed by Vargas Olson Enterprises for the
City Hall Interior Renovation Project as complete.
Approved,
Dominic Lazza
CI y Manager
J K: PAW: pa