STAFF REPORT
Public Works Services Department
DATE: August 6, 2013
TO: Honorable Mayor and City Council
FROM: Tom Tait, Public Works Services Director
By: Mark Rynkiewicz, P.E., Associate Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY VARGAS OLSON
ENTERPRISES, INC. FOR THE WILDERNESS PARK RESTROOM
PROJECT AS COMPLETE AND AUTHORIZE THE FINAL PAYMENT TO
BE MADE IN ACCORDANCE WITH THE CONTRACT DOCUMENTS,
SUBJECT TO THE RETENTION OF $7,200
Recommendation: Approve
SUMMARY
The Public Works Services Department was notified by the Department of Justice
regarding the inaccessibility of the restrooms at Wilderness Park for people that are
handicapped or have disabilities. In response, the City included the Wilderness Park
Restroom Remodel Project as part of Fiscal Year 2012 -13 Capital Improvement
Program. On March 19, 2013, the City Council awarded a contract to Vargas Olson
Enterprises, Inc. for the construction of Wilderness Park Restroom Project in the
amount of $144,000. No change orders were issued for this contract and all terms and
conditions of this project have been complied with. The restrooms were constructed to
staffs satisfaction for a total project cost of $144,000. It is recommended that the City
Council accept all work performed by Vargas Olson Enterprises Inc. as complete and
authorize the final payment to be made in accordance with the contract documents,
subject to the retention of $7,200.
DISCUSSION
On March 19, 2013, the City Council awarded a contract to Vargas Olson Enterprises,
Inc. for the construction of Wilderness Park Restroom Project in the amount of
$144,000. The completed work consisted of construction of a 525 square foot restroom
facility that included ADA compliant space and railings. The men's restroom included
two urinals, one toilet, and two sinks. The women's restroom included three toilets and
two sinks. The facility also included a janitor's closet that will provide access for
Accept Wilderness Park Restroom Project
August 6, 2013
Page 2 of 2
mechanical and plumbing maintenance. Also part of the project was the installation and
connection for utilities such as water, sewer and electricity.
Vargas Olson has completed the project to staff's satisfaction and there were no change
orders to the project.
FISCAL IMPACT
The Wilderness Park Restroom Project was budgeted in the Fiscal Year 2012 -13
Capital Improvement Program for construction cost of $150,000. The total project cost
of $144,000 is within the approved budget for the Project.
RECOMMENDATION
It is recommended that the City Council accept all work performed by Vargas Olson
Enterprises, Inc. for the Wilderness Park Restroom Project as complete and authorize
the final payment to be made in accordance with the contract documents, subject to the
retention of $7,200.