HomeMy WebLinkAboutItem 2g - Huntington Drive Capacity Improvements Phase 2. GQsLIFORN
—�9
A.6ust 5, 1903
V
DATE: October 21, 2014
STAFF REPORT
Development Services Department
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager /Development Services Director
Philip A. Wray, Deputy Director of Development Services /City Engineer
By: Kevin L. Merrill, Associate Engineer
SUBJECT: CONTRACT WITH GMC ENGINEERING, INC. IN THE AMOUNT OF
$506,373 FOR PHASE TWO OF THE HUNTINGTON DRIVE CAPACITY
IMPROVEMENTS PROJECT AND APPROVE A 10% CONTINGENCY
Recommendation: Approve
SUMMARY
In 2012, the City undertook a project to complete traffic improvements to three very
important intersections along Huntington Drive at Santa Anita Avenue, Santa Clara
Street, and Colorado Place. The project was funded in part by a grant from the Los
Angeles County Metropolitan Transportation Authority (Metro) with matching funds from
the City. The project was completed in December 2012 at a cost substantially lower
than the budget.
After completion, Metro re- evaluated the funding status. They informed the City that
they would support an extension of time to complete the balance of the scope of work
items that were unable to be constructed originally for various reasons. KOA
Corporation, the engineer of record for the project, was hired to prepare the design
plans for the balance of the work, which will include the installation of a median west of
Santa Clara on Huntington, signal phasing improvements, restriping to enhance
capacity, and sidewalk enhancements in the area.
The project was advertised for bids in September 2014, and bids were opened on
October 7, 2014. The successful low bid was from GMC Engineering, Inc., in the
amount of $506,373. It is recommended that the City Council award a contract for
Phase Two of the Huntington Drive Capacity Improvements Project in the amount of
$506,373, and approve a 10% contingency.
Contract with GMC Engineering
October 21, 2014
Page 2 of 5
BACKGROUND
The Huntington Drive Capacity Improvement Project was intended to enhance the
capacity of three intersections on the Huntington Drive corridor at Santa Anita Avenue,
Santa Clara Street, and Colorado Place. The project was funded by a Metro Grant
where the City is responsible for 60% and Metro 40% of the total costs. The
initial project added left turn lanes at Santa Anita Avenue, a right turn lane at Santa
Clara Street, and a through lane at Colorado Place, as well as other traffic signal,
signing, and striping improvements.
The project was originally intended to include two additional important elements that
were subsequently left out. They were the widening of the north side of Huntington
Drive between San Rafael Road and Colorado Place to add a through lane on
Huntington Drive, and the construction of a raised center median in Huntington Drive
between Colorado Place and Santa Clara Street. The widening was dependent on an
offer of dedication from the property owner of 161 Colorado Place as a condition of
approval of the medical office development at that location. The dedication was
anticipated at the time of the City's initial project construction, but was delayed due to
the delays in that development project. The required dedication has now been provided
to the City. The raised center median was proposed for Huntington Drive in the initial
project, but was removed because of conflicts with Gold Line construction. The Gold
Line construction had closed Colorado Boulevard from Colorado Place to Santa Anita
Avenue, which restricted access to the entire neighborhood north of Huntington Drive
and west of Santa Anita Avenue. In fairness to this neighborhood, full access to San
Rafael Road was determined to be necessary for the duration of the Gold Line
construction and the raised median was removed from the original project. The Gold
Line work on Colorado Boulevard is now complete.
The initial construction project only used approximately 60% of the budget. The City
requested that Metro extend the time limit for expending the grant funds in order to
allow the City to complete the entire project. Metro agreed and granted the City an
extension until the summer of 2015.
KOA Corporation, the engineer of record for the project, was retained to prepare the
design plans for the balance of the work. In addition, KOA evaluated the post -
construction conditions, made recommendations for modifications, and received input
from the Police Department and others who frequent the intersection. From these
efforts, the following scope was developed:
• Widen Huntington Drive between Colorado Place and Santa Clara Street to
make room for an additional through lane in each direction
• Install a raised center median between Colorado Place and Santa Clara Street
• Make operational improvements for southbound to westbound right -turns to
eliminate the conflict with the northbound to westbound left -turn movement
Contract with GMC Engineering
October 21, 2014
Page 3 of 5
• Add signs and improve striping for the northbound to eastbound right -turns
• Install sidewalk in front of the 100 -to -1 Club and improve the southwest corner of
Huntington Drive and Santa Clara Street for pedestrian and ADA purposes
• Improve the pedestrian crosswalk phasing sequence at Colorado Place and
Huntington Drive intersection
• Implement traffic signal coordination improvements
• Miscellaneous striping and signage modifications
The scope was initially presented to the City Council at a study session on November 5,
2013. The City Council provided direction to proceed with the scope as proposed, and
KOA proceeded with the construction plans. A second study session was held with the
City Council on July 1, 2014, to brief the new City Council on the project, and again
review the scope of improvements, particularly the raised center median on Huntington
Drive. Direction was given to proceed with the project and to notify the surrounding
residents and businesses of the City's intention.
DISCUSSION
Notices of the project, including the raised center median, were mailed to all residents
north of Huntington Drive between Santa Anita Avenue and Colorado Place and the
businesses along Huntington Drive. Two responses of opposition were received and
these are attached to the staff report. One response was from a resident of the
neighborhood north of Huntington Drive complaining of the inconvenience to local
residents that may be caused by the raised median. For those drivers that make left
turns from San Rafael Road, the median will cause them to find another route to
Huntington Drive. While it is clear this will be an inconvenience to residents, the
widening of Huntington Drive will make left turns more difficult and dangerous because
the stop on San Rafael Road will be pulled back and sight lines of oncoming traffic from
the east will be more challenging. The other response was from the owner of the
existing and proposed office buildings located on the north side of Huntington Drive, at
125 Huntington Drive and 161 Colorado Place. This comment alleges that the loss of
left turns into San Rafael Drive will inconvenience patrons travelling eastbound. It was
pointed out that left turn access would still be available into the site at the main driveway
west of San Rafael Road, and U -turns will be allowed at Huntington Drive and Santa
Clara Street. Further, this applicant was made aware of the planned median when the
new project was proposed and, in fact, the traffic study for this project included a review
of the turning motions with the future median in place. In general, it has been explained
to complainants that the median is recommended because Huntington Drive is an
extremely important corridor, and this segment is a confluence of traffic from several
different directions. Traffic will increase over time in this area, especially with the new
developments planned, and continuing to allow left turns in this area will only create
more conflicts and hindrances to the traffic flow.
Contract with GMC Engineering
October 21, 2014
Page 4 of 5
The plans and specifications for the Project were completed in August, 2014. The most
current Engineer's Estimate for construction of the project was $600,000. The project
was advertised for bids in September 2014, and bids were opened on October 7, 2014.
There were 11 bidders as follows:
GMC Engineering, Inc.
$506,373.00
Gentry Brothers, Inc.
$521,507.00
Unique Performance Construction
$549,799.00
Los Angeles Engineering, Inc.
$568,946.00
All American Asphalt
$587,000.00
Tora
$588,752.00
Sully - Miller Contracting Co.
$594,895.00
PTM General Engineering
$596,569.00
Palp, Inc., dba Excel Paving Co.
$599,252.00
E C Construction
$657,381.30
Roadway Engineering
$667,008.75
The low bidder was GMC Engineering, Inc. in the amount of $506,373. GMC
Engineering's qualifications and work history were investigated and found to be
satisfactory. They have the required license and have successfully completed similar
projects in the past. It is anticipated that work will begin by mid - November 2014 and will
be completed by February 27, 2015.
ENVIRONMENTAL IMPACT
The Initial Study and Mitigated Negative Declaration were noticed and made available
for review for the 30 day period required under CEQA and on January 3, 2012, the City
Council adopted the Mitigated Negative Declaration. This project is in conformance with
the previous environmental review.
FISCAL IMPACT
In the Capital Improvement Programs for Fiscal Year 2009/10 through Fiscal Year
2011 -12, the City Council approved a total budget of $2,500,000. The initial
construction project expended $1,400,000, leaving approximately $1,100,000 available
for Phase 2. Therefore, there are sufficient funds remaining to cover the construction of
this phase of the project. Including the construction bid, the total project costs are
estimated as follows:
Contract with GMC Engineering
October 21, 2014
Page 5 of 5
Design
Inspection
Administration
Materials Testing
Construction Contract
10% Contingency
TOTAL PROJECTED COSTS
RECOMMENDATION
$75,000
$20,000
$10,000
$15,000
$506,373
$50,637
$677,010
It is recommended that the City Council authorize and direct the City Manager to
execute a contract with GMC Engineering, Inc. in the amount of $506,373 for Phase
Two of the Huntington Drive Capacity Improvements Project and approve a 10%
contingency.
Approved
Dominic Lazza d
City Manager
Attachments
Kevin Merrill
From:
Ted Zhou <ted848848 @gmail.com>
Sent:
Tuesday, August 05, 2014 4:23 PM
To:
Kevin Merrill
Subject:
Upcoming street construction on Huntngton drive from Santa Clara Street to Colorado
street
Follow Up Flag: Follow up
Flag Status: Completed
Hi Mr. Merrill:
I am an Arcadia resident and live close to Santa Clara street and San Rafael road. I think the proposed median
to restrict left turn movements will only add the inconvenience to the local residents. In fact, most the time
except for traffic hour, the left turn is not difficult at all. Were there many traffic accidents reported due to this
left turn issue? Is there a traffic flow study or alternative ways to address the left turn issue? Is it possible that
you can provide a site plan showing the proposed Phase II work? I thank you for provide the requested
information and address the concerns.
Regards,
Ted
VG PROPERTY INVESTMENTS, LLC.
25 E. Huntington Drive
Arcadia, CA 91006
September 29, 2014
Philip A. Wray
Deputy Director of Development Services /City Engineer
City of Arcadia
240 West Huntington Drive
Post Office Box 60021
Arcadia, CA 91066 -6021
(626) 548 -8777 Office
(626) 548 -8778 Fax
RE: Upcoming Street Construction on Huntington Drive from Santa Clara Street to Colorado Street
Phil,
Thanks for meeting with me recently to discuss the City's plans to complete its 2012 project to improve
Huntington Drive from Santa Anita Avenue to Colorado Place. As we discussed in our recent meeting
and in May of 2012, VG Property Investments, LLC firmly believes that the changes being proposed by
the City will result in several negative impacts on our property at 125 W. Huntington Drive. Specifically,
1. The banning of left turns from Huntington Drive onto San Rafael will eliminate what has
historically been the main entrance to our existing office building. Our long -term tenant, WorleyParsons,
views this as a "loss" of easy access to the premises. Since we will be entering into renewal negotiations
with them in January, 2015, the tenant's broker could (and no doubt will) use this "loss" to the
landlord's disadvantage.
2. Eliminating left turns from San Rafael onto Huntington Drive will dictate that all of the
tenants' employees that need to travel east on Huntington Drive will have to use the existing driveway
on the west side of the building. This will result in a back -log of vehicles at this exit at the close of the
day. Additionally, once our new medical offices and parking garage are operational, traffic from the
garage will also be utilizing this driveway, resulting in even more back -log. In lieu of using this driveway,
employees may decide to utilize the neighborhood streets to the north of the building to attain access
to Santa Anita Drive. Either way, at full occupancy, these buildings could be releasing up to 583 vehicles.
We understand that vehicles will be able to make a legal left turn at San Juan, but the vehicles parked in
our existing parking lot will not have access to San Juan, leaving them at a distinct disadvantage.
3. Ease of access and access visibility are paramount when launching new real estate. If
the City constructs the median, the main entry to the campus will become a driveway versus a marked
street (San Juan, or San Raphael. If someone travelling east on Colorado Place misses the driveway, they
will have to make a left turn onto another street past San Rafael, perform another left into a parking lot
or driveway and return to Huntington Drive to turn right onto San Rafael or the driveway. Alternatively,
the driver could proceed to the first legal u -turn which would be Monterey in Monrovia. Clearly this
does not create an ideal scenario for a start-up medical campus.
We fully understand and appreciate that the City of Arcadia is growing and changing in many positive
ways. We want the growth of our project (Huntington Center) to be a viable part of the City's success.
To provide us with the best support to attain that goal, we ask that the City reconsider our original
requests made on May 15, 2014:
" (i) reconsider the decision to eliminate left turns from Huntington Drive onto San Rafael; (ii)
consider the installation of a turning inlet onto San Rafael; (iii) allow u -turns at the existing light
at the intersection of Huntington Drive and Santa Anita; or (iv) allow u -turns at the intersection
of Huntington Drive and Santa Clara."
At this time, it appears that allowing u -turns at the Huntington Drive /Santa Anita intersection may be
the most viable alternative. Given the land dedicated by VG Property Investments to the City last
September, there should be adequate turning radius to complete a u -turn in a safe manner.
Thank you for your time and consideration. Mike Soo and I are available to meet with you and /or others
to reach a solution that will work for the success of both the City and VG Property Investments.
Sincerely,
Sharon A. Logan
Asset Manager
cc: Mike Soo