HomeMy WebLinkAboutItem 2h - Contract for Huntington Drive Capacity Phase 2 Improvements�� � GPL1POft1�*Iq"j,� f
-r
a
1--poe via
Flu goat 5, 1—
42u'tt STAFF REPORT
Development Services Department
DATE: December 16, 2014
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager /Development Services Director
Philip A. Wray, Deputy Director of Development Services /City Engineer
By: Kevin L. Merrill, Associate Engineer
SUBJECT: CONTRACT WITH GMC ENGINEERING, INC. IN THE AMOUNT OF
$506,373 FOR PHASE TWO OF THE HUNTINGTON DRIVE CAPACITY
IMPROVEMENTS PROJECT
Recommendation: Approve
SUMMARY
In 2012, the City undertook a project to complete traffic improvements along Huntington
Drive at Santa Anita Avenue, Santa Clara Street, and Colorado Place. The project was
funded in part by a grant from the Los Angeles County Metropolitan Transportation
Authority ( "Metro ") and was completed in December 2012 at a cost substantially lower
than the budget. Metro has allowed a time extension on the grant to complete additional
work items that would enhance the intersections, such as the installation of a raised
median in Huntington Drive from Santa Clara Street to Colorado Place, street widening
west of San Rafael Road, signal phasing improvements, restriping to enhance capacity,
and sidewalk enhancements in the area. The project was advertised for bids in
September 2014, and were opened on October 7, 2014. The successful low bid was
from GMC Engineering, Inc., in the amount of $506,373.
On October 21, 2014, the bid was originally presented to the City Council for award.
At that meeting, two neighboring property owners expressed concerns about the project
because they felt that the proposed raised median in Huntington Drive would create the
need for U -turns at both adjacent intersections.
U -turns were already planned to be allowed at the Santa Clara Street intersection;
however, U -turns were not thought to be feasible at Colorado Place. Upon
further investigation of the Colorado Place intersection, the raised median can be
modified to create the minimum allowable clearance needed to accommodate U- turns;
however, larger vehicles may have difficulty negotiating the U -turn. If upon completion,
there is a desire to create more clearance to accommodate turns, the median can be
Contract with GMC Engineering
December 16, 2014
Page 2 of 6
modified and the recently- approved hotel development on the Santa Anita Inn site has
been conditioned to dedicate additional street right -of -way that will help accommodate
the larger turns.
It is recommended that the City Council award a contract for Phase Two of the
Huntington Drive Capacity Improvements Project in the amount of $506,373.
BACKGROUND
The Huntington Drive Capacity Improvement Project was intended to enhance the
capacity of three intersections on the Huntington Drive corridor at Santa Anita Avenue,
Santa Clara Street, and Colorado Place. The project was funded by a Metro Grant
where the City is responsible for 60% and Metro 40% of the total costs. The
initial project added left turn lanes on Santa Anita Avenue, a right turn lane on Santa
Clara Street, and a through lane at Colorado Place, as well as other traffic signal,
signing, and striping improvements.
The project was originally intended to include two additional important elements that
were subsequently left out. They were the widening of the north side of Huntington
Drive between San Rafael Road and Colorado Place to add a through lane on
Huntington Drive, and the construction of a raised center median in Huntington Drive
between Colorado Place and Santa Clara Street. The widening was dependent on an
offer of dedication from the property owner of 161 Colorado Place as a condition of
approval of the medical office development at that location. The dedication was
anticipated at the time of the City's initial project construction, but was delayed due to
the delays in that development project. The required dedication has now been provided
to the City. The raised center median was proposed for Huntington Drive in the initial
project, but was removed because of conflicts with Gold Line construction. The Gold
Line construction had closed Colorado Boulevard from Colorado Place to Santa Anita
Avenue, which restricted access to the entire neighborhood north of Huntington Drive
and west of Santa Anita Avenue. In fairness to this neighborhood, full access to San
Rafael Road was determined to be necessary for the duration of the Gold Line
construction and the raised median was removed from the original project. The Gold
Line work on Colorado Boulevard is now complete.
The initial construction project only used approximately 60% of the budget. The City
requested that Metro extend the time limit for expending the grant funds in order to
allow the City to complete the entire project. Metro agreed and granted the City an
extension until the summer of 2015.
KOA Corporation, the engineer of record for the project, was retained to prepare the
design plans for the balance of the work. In addition, KOA evaluated the post -
construction conditions, made recommendations for modifications, and received input
from the Police Department and others who frequent the intersection. From these
efforts, the following scope was developed:
Contract with GMC Engineering
December 16, 2014
Page 3 of 6
• Widen Huntington Drive between Colorado Place and Santa Clara Street to
make room for an additional through lane in each direction
• Install a raised center median between Colorado Place and Santa Clara Street
• Make operational improvements for southbound to westbound right -turns to
eliminate the conflict with the northbound to westbound left -turn movement
• Add signs and improve striping for the northbound to eastbound right -turns
• Install sidewalk in front of the 100 -to -1 Club and improve the southwest corner of
Huntington Drive and Santa Clara Street for pedestrian and ADA purposes
• Improve the pedestrian crosswalk phasing sequence at Colorado Place and
Huntington Drive intersection
• Implement traffic signal coordination improvements
• Miscellaneous striping and signage modifications
The scope was initially presented to the City Council at a study session on November 5,
2013. The City Council provided direction to proceed with the scope as proposed, and
KOA proceeded with the construction plans. A second study session was held with the
City Council on July 1, 2014, to brief the new City Council on the project, and again
review the scope of improvements, particularly the raised center median on Huntington
Drive. Direction was given to proceed with the project, and to notify the surrounding
residents and businesses of the City's intention.
DISCUSSION
Notices of the project, including the raised center median, were mailed to all residents
north of Huntington Drive between Santa Anita Avenue and Colorado Place and the
businesses along Huntington Drive. Two responses of opposition were received and
are attached to this staff report. One response was from a resident of the neighborhood
north of Huntington Drive complaining of the inconvenience to local residents that may
be caused by the raised median. For those drivers that make left turns from San Rafael
Road, the median will cause them to find another route to Huntington Drive. While it is
clear this will be an inconvenience to residents, the widening of Huntington Drive will
make left turns more difficult and dangerous because the stop on San Rafael Road will
be moved back, and sight lines of oncoming traffic from the east will be more
challenging. The other response was from the owner of the existing and proposed
office buildings located on the north side of Huntington Drive, at 125 Huntington Drive
and 161 Colorado Place. This comment alleges that the loss of left turns into San
Rafael Drive will inconvenience patrons travelling eastbound. It was pointed out that left
turn access would still be available into their site at their main driveway west of San
Rafael Road, and U -turns will be allowed at Huntington Drive and Santa Clara Street.
Further, this applicant was made aware of the planned median when the new project
was proposed and, in fact, the traffic study for this project included a review of the
turning motions with the future median in place. In general, it has been explained to
complainants that the median is recommended because Huntington Drive is an
extremely important corridor, and this segment is a confluence of traffic from several
Contract with GMC Engineering
December 16, 2014
Page 4 of 6
different directions. Traffic will increase over time in this area, especially with the new
developments planned, and continuing to allow left turns in this area will only create
more conflicts and hindrances to the traffic flow.
The plans and specifications for the project were completed in August, 2014. The most
current Engineer's Estimate for construction of the project was $600,000. The project
was advertised for bids in September 2014, and bids were opened on October 7, 2014.
There were 11 bidders as follows:
GMC Engineering, Inc.
$506,373.00
Gentry Brothers, Inc.
$521,507.00
Unique Performance Construction
$549,799.00
Los Angeles Engineering, Inc.
$568,946.00
All American Asphalt
$587,000.00
Tora
$588,752.00
Sully - Miller Contracting Co.
$594,895.00
PTM General Engineering
$596,569.00
Palp, Inc., dba Excel Paving Co.
$599,252.00
E C Construction
$657,381.30
Roadway Engineering
$667,008.75
The low bidder was GMC Engineering, Inc. in the amount of $506,373. GMC
Engineering's qualifications and work history were investigated and found to be
satisfactory. They have the required license and have successfully completed similar
projects in the past.
The low bid was presented to the City Council for award at the City Council meeting of
October 21, 2014. At that meeting, the owner of the 100 -to -1 Club and the owner's
representative for the office building at 125 West Huntington Drive expressed their
opposition to the median because patrons of their businesses would not have left turn
access into and out of their sites, and would depend on U -turns at the adjacent
intersections. U -turns at Santa Clara Street will be allowed, which was the concern of
the property owner of 125 West Huntington Drive. U -turns at Colorado Place would not
be allowed because there is insufficient street width. The City Council delayed the
decision to award a construction contract for the project in order for the issue to be
investigated further.
The proposed design of the Huntington Drive and Colorado Place intersection was
investigated and it was determined that by shortening the end of the median, the
minimum width could be achieved to allow U- turns. This will be sufficient for all
passenger vehicles. Because this is not a standard four -way intersection, it does not
accommodate U -turns for larger vehicles where they could partially utilize the
intersecting street to make a wider U -turn. In the absence of the intersecting street, a
larger vehicle making a U -turn would have to either utilize some of the adjacent lane on
the right to make a wider turn, make a three -point turn, or pull forward to the Santa Anita
Contract with GMC Engineering
December 16, 2014
Page 5 of 6
Inn driveway and utilize the drive approach for part or all of the turn. To accommodate
larger vehicle U- turns, the south side of Huntington Drive would need to be widened
slightly; as such, additional right -of -way would be necessary from the Santa Anita Inn
property. The additional dedication was required as a condition of approval of the
proposed new hotel development. However, because the dedication is not required
until a building permit is requested, there is no way to control or predict the timing of the
dedication and the potential coordination and construction.
It is recommended that the project proceed as originally designed, but that the
intersection be monitored upon completion for the need to accommodate U- turns. The
modifications needed to account for U -turns are minor in nature.
It is recommended that the City Council award a contract for Phase Two of the
Huntington Drive Capacity Improvements Project in the amount of $506,373, and
approve a 10% contingency. It is further recommended that the City Council direct staff
to monitor the post construction activity closely to determine the need for modifications
to accommodate U- turns.
ENVIRONMENTAL IMPACT
The Initial Study and Mitigated Negative Declaration were noticed and made available
for review for the 30 day period required under CEQA and on January 3, 2012, the City
Council adopted the Mitigated Negative Declaration. This project is in conformance with
the previous environmental review.
FISCAL IMPACT
In the Capital Improvement Programs for Fiscal Year 2009 -10 through Fiscal Year
2011 -12, the City Council approved a total budget of $2,500,000. The initial
construction project expended $1,400,000, leaving approximately $1,100,000 available
for Phase 2. Therefore, there are sufficient funds remaining to cover the construction of
this phase of the project. Including the construction bid, the total project costs are
estimated as follows:
Design
$75,000
Inspection
$20,000
Administration
$10,000
Materials Testing
$15,000
Construction Contract
$506,373
10% Contingency
$50,637
TOTAL PROJECTED COSTS $677,010
Contract with GMC Engineering
December 16, 2014
Page 6 of 6
RECOMMENDATION
It is recommended that the
execute a contract with GMC
Two of the Huntington Driv e
contingency.
Approved.
Dorrrinio Laazare�t�
CWy Manager
City Council authorize and direct
Engineering, Inc. in the amount o
Capacity Improvements Project,
Attachments — Responses of Opposition
Contract
the City Manager to
f $506,373 for Phase
and approve a 10%
Kevin Merrill
From:
Sent: Tuesday, August 05, 2014 4:23 PM
To: Kevin Merrill
Subject: Upcoming street construction on Huntngton drive from Santa Clara Street to Colorado
street
Follow Up Flag: Follow up
Flag Status: Completed
Hi Mr. Merrill:
I am an Arcadia resident and live close to Santa Clara street and San Rafael road. I think the proposed median
to restrict left turn movements will only add the inconvenience to the local residents. In fact, most the time
except for traffic hour, the left turn is not difficult at all. Were there many traffic accidents reported due to this
left turn issue? Is there a traffic flow study or alternative ways to address the left turn issue? Is it possible that
you can provide a site plan showing the proposed Phase II work? I thank you for provide the requested
information and address the concerns.
Regards,
Ted
VG PROPERTY INVESTMENTS, LLC.
25 E. Huntington Drive
Arcadia, CA 91006
September 29, 2014
Philip A. Wray
Deputy Director of Development Services /City Engineer
City of Arcadia
240 West Huntington Drive
Post Office Box 60021
Arcadia, CA 91066 -6021
(626) 548 -8777 Office
(626) 548 -8778 Fax
RE: Upcoming Street Construction on Huntington Drive from Santa Clara Street to Colorado Street
Phil,
Thanks for meeting with me recently to discuss the City's plans to complete its 2012 project to improve
Huntington Drive from Santa Anita Avenue to Colorado Place. As we discussed in our recent meeting
and in May of 2012, VG Property Investments, LLC firmly believes that the changes being proposed by
the City will result in several negative impacts on our property at 125 W. Huntington Drive. Specifically,
1. The banning of left turns from Huntington Drive onto San Rafael will eliminate what has
historically been the main entrance to our existing office building. Our long -term tenant, WorleyParsons,
views this as a "loss" of easy access to the premises. Since we will be entering into renewal negotiations
with them in January, 2015, the tenant's broker could (and no doubt will) use this "loss" to the
landlord's disadvantage.
2. Eliminating left turns from San Rafael onto Huntington Drive will dictate that all of the
tenants' employees that need to travel east on Huntington Drive will have to use the existing driveway
on the west side of the building. This will result in a back -log of vehicles at this exit at the close of the
day. Additionally, once our new medical offices and parking garage are operational, traffic from the
garage will also be utilizing this driveway, resulting in even more back -log. In lieu of using this driveway,
employees may decide to utilize the neighborhood streets to the north of the building to attain access
to Santa Anita Drive. Either way, at full occupancy, these buildings could be releasing up to 583 vehicles.
We understand that vehicles will be able to make a legal left turn at San Juan, but the vehicles parked in
our existing parking lot will not have access to San Juan, leaving them at a distinct disadvantage.
3. Ease of access and access visibility are paramount when launching new real estate. If
the City constructs the median, the main entry to the campus will become a driveway versus a marked
street (San Juan, or San Raphael. If someone travelling east on Colorado Place misses the driveway, they
will have to make a left turn onto another street past San Rafael, perform another left into a parking lot
or driveway and return to Huntington Drive to turn right onto San Rafael or the driveway. Alternatively,
the driver could proceed to the first legal u -turn which would be Monterey in Monrovia. Clearly this
does not create an ideal scenario for a start-up medical campus.
We fully understand and appreciate that the City of Arcadia is growing and changing in many positive
ways. We want the growth of our project (Huntington Center) to be a viable part of the City's success.
To provide us with the best support to attain that goal, we ask that the City reconsider our original
requests made on May 15, 2014:
" (i) reconsider the decision to eliminate left turns from Huntington Drive onto San Rafael; (ii)
consider the installation of a turning inlet onto San Rafael; (iii) allow u -turns at the existing light
at the intersection of Huntington Drive and Santa Anita; or (iv) allow u -turns at the intersection
of Huntington Drive and Santa Clara."
At this time, it appears that allowing u -turns at the Huntington Drive /Santa Anita intersection may be
the most viable alternative. Given the land dedicated by VG Property Investments to the City last
September, there should be adequate turning radius to complete a u -turn in a safe manner.
Thank you for your time and consideration. Mike Soo and I are available to meet with you and /or others
to reach a solution that will work for the success of both the City and VG Property Investments.
Sincerely,
Sharon A. Logan
Asset Manager
cc: Mike Soo
CITY OF ARCADIA
HUNTINGTON DRIVE CAPACITY IMPROVEMENTS
PHASE 2
Project No. 41854309
CONTRACT
BETWEEN
CITY OF ARCADIA
AND
GMC ENGINEERING, INC.
RVPUB\DRD \570015 GB - STATE & LOCAL (505/507/660) (7/24/00)
(PROJECT NO. 41854309)
CONTRACT FOR THE
CITY OF ARCADIA
HUNTINGTON DRIVE CAPACITY IMPROVEMENTS -PHASE 2
PARTIES AND DATE.
This Contract is made and entered into this day of , 2014, by and
between the CITY OF ARCADIA (hereinafter called the "Owner ") and GMC ENGINEERING, INC.
(hereinafter called the "Contractor ").
2. RECITALS.
2.1 The Owner is a charter City organized under the laws of the State of California, with
power to contract for services necessary to achieve its purpose;
2.2 Contractor, in response to a Notice Inviting Bids issued by Owner on September
2014, has submitted a bid proposal for construction the HUNTINGTON DRIVE CAPACITY
IMPROVEMENTS -PHASE 2 described in the Contract.
2.3 Owner has duly opened and considered the Contractor's bid proposal, and duly
awarded the bid to Contractor in accordance with the Notice Inviting Bids and the other Bid
Documents, and has given written notice to Contractor on October 22, 2014.
2.4 Contractor has obtained, and delivers concurrently herewith, Performance and
Payment Bonds and evidences of insurance coverage as required by the Contract.
3. TERMS.
3.1 Incorporation of Documents.
This Contract includes and hereby incorporates in full by reference the following documents,
including all exhibits, drawings, specifications and documents therein, and attachments and
addenda thereto:
a. Notice Inviting Bids
b. Instructions to Bidders
C. Contract Bid Forms
d. Contract
e. Contract Appendix
Part "A"
- General Conditions
Part "B"
- Supplementary General Conditions
Part "C"
- Special Provisions
Part "D"
- Specifications
Part "E"
- Drawings (under separate cover)
RVPUWDRD\570015 CONTRACT-1 GB - STATE & LOCAL (505/507/660) (7/24/00)
(PROJECT NO. 41854309)
Part "F" - Performance Bond
Part "G" - Payment Bond
Part "H" - Escrow Agreement for Security
Deposits (optional)
ADDENDUM NO. dated
The above documents, including the General Conditions, are an integral part of the Contract
Documents. In addition to signing this Contract, Contractor shall initial this paragraph immediately
below acknowledging that he or she has read, understood and agrees with all of the terms of the
Contract Documents, including, but not limited to, provisions of the General Conditions relating to
indemnification, insurance, standards of performance, termination, compensation and time of the
essence performance. Contractor shall not disclaim knowledge of the meaning and effect of any
term or provision of the Contract Documents, and agrees to strictly abide by their meaning and
intent. In the event that Contractor fails to initial below, the Owner shall have the right to
declare the Contract unexecuted and to award the Contract to another contractor in
accordance with state law.
Contractor, s Initials
3.2 Contractor's Basic Obligation.
Contractor promises and agrees, at its own cost and expense, to furnish to the Owner all
labor, materials, tools, equipment, services, and incidental and customary work for the construction
necessaryto fully and adequately complete HUNTINGTON DRIVE CAPACITY IMPROVEMENTS -
PHASE 2, including any alternates selected by the Owner, and all structures and facilities described
in the Contract (hereinafter the "Work "), for a total of Five Hundred Six Thousand Three Hundred
Seventy Three Dollars and Zero Cents ($506,373.00) as specified in the Contract Bid Forms
submitted by the Contractor in response to the above referenced Notice Inviting Bids. Such amount
shall be subject to adjustment in accordance with the applicable terms of this Contract. All Work
shall be subject to, and performed in accordance with the above referenced documents.
3.3 Standard of Performance.
Contractor shall perform all Work under this Contract in a skillful and workmanlike manner,
and consistent with the standards generally recognized as being employed by professionals in the
same discipline in the State of California. Contractor represents and maintains that it is skilled in the
professional calling necessary to perform the Work. Contractor warrants that all employees and
subcontractors shall have sufficient skill and experience to perform the Work assigned to them.
Finally, Contractor further represents that it, its employees and subcontractors have all licenses,
permits, qualifications and approvals of whatever nature that are legally required to perform the
Work, and that such licenses and approvals shall be maintained throughout the term of this
Contract.
3.4 Period of Performance.
Contractor shall perform and complete all Work under this Contract 90 calendar days,
beginning ten (10) calendar days after the date on which the Notice to Proceed is sent by the Owner
RVPUWDRD\570015 CONTRACT-2 GB - STATE & LOCAL (505/507/660) (7/24/00)
(PROJECT NO. 41854309)
to the Contractor. Moreover, Contractor shall perform its Work in strict accordance with any
completion schedule, construction schedule or project milestones developed pursuant to provisions
of the Contract, including but not limited to the Project Schedule located in the Specifications.
Contractor agrees that if such Work is not completed within the aforementioned period
and /or pursuant to any such completion schedule, construction schedule or project milestones
developed pursuant to provisions of the Contract, including but not limited to the Project Schedule
located in the Specifications, it is understood, acknowledged and agreed that the Owner will suffer
damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the Owner as
fixed and liquidated damages the sum of one thousand dollars ($1,000) PER DAY as provided by
the applicable provisions of the General Conditions.
3.5 Owner's Basic Obligation.
Owner agrees to engage and does hereby engage Contractor as an independent contractor
to furnish all materials and to perform all Work according to the terms and conditions herein
contained for the sum set forth above. Except as otherwise provided in the Contract, the Owner
shall pay to Contractor, as full consideration for the satisfactory performance by the Contractor of the
services and obligations required by this Contract, the above referenced compensation in
accordance with compensation provisions set forth in the Contract.
3.6 Contractor's Labor Certification.
Contractor maintains that he is aware of the provisions of Section 3700 of the California
Labor Code which require every employer to be insured against liability for Worker's Compensation
or to undertake self- insurance in accordance with the provisions of that Code, and agrees to comply
with such provisions before commencing the performance of the Work. A certification form for this
purpose is attached hereto as Exhibit "A" and incorporated herein by reference, and shall be
executed simultaneously with this Contract.
3.7 Attorneys' Fees.
If either party commences an action against the other party, either legal, administrative or
otherwise, arising out of or in connection with this Contract, the prevailing party in such action shall
be entitled to have and recover from the losing party reasonable attorneys' fees and all other costs
of such action.
3.8 Successors.
The parties do for themselves, their heirs, executors, administrators, successors, and
assigns agree to the full performance of all of the provisions contained in this Contract. Contractor
may not either voluntarily or by action of law, assign any obligation assumed by Contractor
hereunder without the prior written consent of the Owner.
RVPUWDRD\570015 CONTRACT-3 GB - STATE & LOCAL (505/507/660) (7/24/00)
(PROJECT NO. 41854309)
3.9 Notices.
All notices hereunder and communications regarding interpretation of the terms of the
Agreement or changes thereto shall be provided by the mailing thereof by registered or certified
mail, return receipt requested, postage prepaid and addressed as follows:
Contractor Surety
GMC Engineering, Inc.
1401 Warner Ave., Ste. B
Tustin, CA. 92780
Attn: Gennady Chizhik Attn:
President
Owner With Copies To:
City of Arcadia
240 West Huntington Drive
Arcadia CA 91007
Attn: Philip A. Wray
City Engineer
Any notice so given shall be considered received by the other party three (3) days after
deposit in the U.S. Mail, first class postage prepaid, addressed to the party at the above address.
Actual notice shall be deemed adequate notice on the date actual notice occurred, regardless of the
method of service.
CONTRACTOR CITY OF ARCADIA
Name
Title
By:
Name
Title
Tax 1. D. Number.
Number
Approved as to Form:
By:
Stephen P. Deitsch, City Attorney
Dominic Lazzaretto, City Manager
Date
Attest:
By:
City Clerk
Contractor's License:
Number
Class
RVPUWDRD\570015 CONTRACT-4 GB - STATE & LOCAL (505/507/660) (7/24/00)
(PROJECT NO. 41854309)
EXHIBIT "A"
CERTIFICATION
LABOR CODE - SECTION 1861
I, the undersigned Contractor, am aware of the provisions of Section 3700 et seg. of
the California Labor Code which require every employer to be insured against liability for
Worker's Compensation orto undertake self- insurance in accordance with the provisions of
the Code. I agree to and will comply with such provisions before commencing the Work
governed by this Contract.
CONTRACTOR:
Name of Contractor: GMC ENGINEERING, INC.
By:
Signature:
Name:
Title:
Date:
RVPUWDRD\570015 CONTRACT (EXHIBIT A) GB - STATE & LOCAL (505/507/660) (7/24/00)