DATE: May 16, 2017
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director
Philip A. Wray, Deputy Director of Development Services/City Engineer
SUBJECT: AUTHORIZE THE EXPENDITURE OF $54,400 FOR THE REPAVING OF
A PORTION OF FOOTHILL BOULEVARD IN THE CITY LIMITS AS A
SCOPE CHANGE ON THE COUNTY OF LOS ANGELES PROJECT FOR
PAVEMENT REHABILITATION AND TRAFFIC SIGNAL UPGRADES ON
FOOTHILL BOULEVARD BETWEEN ROSEMEAD BOULEVARD AND
MICHILLINDA AVENUE
Recommendation: Approve
SUMMARY
Several years ago, the County of Los Angeles began the planning for their Foothill
Boulevard Pavement Rehabilitation project between Rosemead Boulevard and
Michillinda Avenue. As they developed their scope of work, they proposed extending
their project limits into the City of Arcadia, to include the entire intersection of Michillinda
Avenue. As a result, the County and the City entered into a cost-sharing agreement for
the City to be responsible for its share of the project.
Concurrent with the County’s planning, the City made plans to rehabilitate the concrete
pavement on Foothill Boulevard from Michillinda Avenue to Santa Anita Avenue. The
City’s project proceeded ahead of the County’s project, and was completed in
September of 2016. There is a short segment of asphalt pavement on Foothill
Boulevard in the City of Arcadia, just east of Michillinda Avenue that was not included in
the City’s concrete pavement repair project.
The County awarded the construction contract for their project in October of 2016 and it
is now under construction. The City recently approached the County with a request for
the County to extend the limits of their asphalt pavement repairs easterly from
Michillinda Avenue, into Arcadia, to include the City’s previously unrepaired segment.
The County agreed to facilitate the extra work for a total cost of $54,400. It is
recommended that the City Council authorize the expenditure of $54,400 for the re-
Authorize Expenditure
May 16, 2017
Page 2 of 4
pavement of a portion of Foothill Boulevard in the City Limits as a scope change on the
County of Los Angeles project for the pavement rehabilitation and traffic signal
upgrades on Foothill Boulevard between Rosemead Boulevard and Michillinda Avenue.
BACKGROUND
In October of 2013, the City entered into a Cost-Sharing Agreement with the County of
Los Angeles for the County’s Foothill Boulevard Pavement Rehabilitation and Traffic
Signal Upgrades Project, from Rosemead Boulevard to Michillinda Avenue. The project
includes rehabilitation of the pavement, repairs to the curbs, gutters, sidewalks, and
ADA ramps, and upgrades to the traffic signal equipment. Arcadia has jurisdiction over
the easterly portion of the Foothill Boulevard and Michillinda Avenue intersection, and
the Agreement covered this portion of the work, at a net cost to the City of $10,000.
In the summer of 2016, the City administered its Foothill Boulevard Concrete
Rehabilitation project from Michillinda Avenue to Santa Anita Avenue. There is a short
segment of asphalt pavement on Foothill Boulevard directly east of Michillinda Avenue,
approximately 400-feet in length that was not included in the project. Although this
segment is in need of repair, it was not included in the concrete repairs project because
the project had no component for asphalt repair, and the unit costs for this small portion
of asphalt work would have been disproportionately high. The City’s project was
completed in September of 2016.
In the fall of 2016, the County of Los Angeles competitively bid their Foothill Boulevard
project and, upon opening bids, received the following results:
COMPANY AMOUNT
Sequel Contractors, Inc. $1,387,297.90
Sully Miller Contracting $1,568,164.80
All American Asphalt $1,593,000.00
Shawnan Corporation $1,619,006.40
Excel Paving $1,621,203.70
Los Angeles Engineering Inc. $1,687,737.50
Vido Samarzich $1,812,961.35
They proceeded to enter into a construction contract with Sequel Contractors, Inc. The
project began in March, and is currently under construction.
DISCUSSION
The County’s Foothill Boulevard project will repair the pavement from Rosemead
Boulevard to Michillinda Avenue. The City recently approached the County with a
request to extend the limits of the asphalt pavement repair easterly from Michillinda
Avenue into Arcadia to the beginning of the concrete pavement, and to provide an
Authorize Expenditure
May 16, 2017
Page 3 of 4
estimate for the work. The County agreed to facilitate the extra work, and the contractor
agreed to perform the work at the unit prices in their contract, for a total cost of $54,400.
The expenditure for this project is a benefit to the City for several reasons. The cost is
reasonable and competitive because it is based on the unit prices from the County’s
lowest bidder in a competitive bidding process. The City will not have to administer a
separate project or add this portion of Foothill Boulevard to another project, thus saving
time and effort. Any project administered by the City for this segment would more than
likely include an additional cost to the City for mobilization. Also, paving all of Foothill
Boulevard at one time is the most pragmatic solution, and will minimize disruption and
inconvenience to the public.
If approved by the City, the County will authorize the additional work through a service
request with the City, and will invoice the City upon completion of the work. The County
will coordinate the work with the contractor, and the City will be responsible for the
inspection.
ENVIRONMENTAL IMPACT
For the County’s current Foothill Boulevard Project, they filed a Class 1 exemption as
defined in Section 15301(c) of the California Environmental Quality Act (“CEQA”), since
the project consists of a minor alteration to an existing public facility. The proposed
additional work will fall under this exemption.
FISCAL IMPACT
The City’s Foothill Boulevard Concrete Repairs project was originally budgeted at $1.3
Million. The project was completed in September of 2016 at a cost of just over $1
million. Deducting all project expenses from the total budget, there is a balance of
approximately $200,000 in Proposition C funds remaining, that has not been closed out
yet. The cost for the proposed work is $54,400, which is less than the anticipated cost
of this work if the project needed to be bid separately. There is sufficient funding
remaining in the City’s project budget to cover this additional cost, and this is an eligible
expenditure of Proposition C funds.
RECOMMENDATION
It is recommended that the City Council approve and authorize the expenditure of
$54,400 for the repaving of a portion of Foothill Boulevard in the City Limits as a scope
change on the County of Los Angeles project for the pavement rehabilitation and traffic
signal upgrades on Foothill Boulevard between Rosemead Boulevard and Michillinda
Avenue.
Authorize Expenditure
May 16, 2017
Page 4 of 4