Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutItem 2j - Accept Work for the Duarte Road Rehabilitation Project
DATE: June 6, 2017
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director
Philip A. Wray, Deputy Director of Development Services/City Engineer
Prepared by: Tim Kelleher, Assistant Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY SULLY-MILLER CONTRACTING
CO. FOR THE DUARTE ROAD REHABILITATION FROM SANTA ANITA
AVENUE TO FIFTH AVENUE AND THE MISCELLANEOUS ARTERIAL
IMPROVEMENTS PROJECT AS COMPLETE
Recommendation: Approve
SUMMARY
On December 6, 2016, the City Council awarded a contract to Sully-Miller Contracting
Co., in the amount of $560,022, plus a 10% contingency, for the Duarte Road
Rehabilitation from Santa Anita Avenue to Fifth Avenue and the Miscellaneous Arterial
Improvements Project. There were five (5) change orders on the project in the amount
of $5,798.39, and a final adjustment for actual measured quantities that deducted
$33,811.24, bringing the net total change to the contract a deduction of $28,012.85.
The final contract amount is $532,009.15.
The terms and conditions of this project have been complied with, and the required work
has been performed to staff’s satisfaction for a final cost of $532,009.15. It is
recommended that the City Council accept the project as complete and authorize the
final payment in accordance with the contract documents.
BACKGROUND
The City annually appropriates Proposition “C” funding for arterial street pavement
projects. For the Fiscal Year 2015-16 Capital Improvement Program, the City Council
appropriated funding for two projects: The Duarte Road Rehabilitation from Santa Anita
Avenue to Fifth Avenue, and the Arterial Streets Miscellaneous Minor Repairs projects.
The Duarte Road Rehabilitation project was planned for the segment from Santa Anita
Avenue to Fifth Avenue. The Miscellaneous Arterial Minor Repairs Project covered
small pavement repairs at four important intersections, as follows:
Accept Work Sully-Miller Contracting Co.
for the Duarte Road Rehabilitation Project
June 6, 2017
Page 2 of 3
W/B Huntington Drive at Fifth Avenue
S/B Holly Avenue at Duarte Road
N/B Second Avenue at California Street
E/B Foothill Boulevard at Baldwin Avenue South
These two Capital Improvement Projects were combined into one construction project
for administrative purposes and advertised for bids in October 2016. On October 27,
2016, six bids were opened, with Sully-Miller Contracting Co. being the low bidder in the
amount of $560,022. On December 6, 2016, the City Council awarded the contract to
Sully-Miller in this amount, and authorized a 10% contingency.
Before work began, it became clear that two private development projects on Duarte
Road between Santa Anita Avenue and First Avenue, would have construction impacts
on Duarte Road after the pavement rehabilitation project was completed, and would
potentially damage the new pavement. It was decided to remove this segment from the
project and wait until the two development projects are complete before paving this
segment.
DISCUSSION
Work began on the project on February 21, 2017, and was substantially complete by
March 17, 2017. There were five (5) change orders on the project totaling $5,798.39,
and a final adjustment for actual measured quantities as a deduction of $33,811.24,
bringing the net total change to the contract as a deduction of $28,012.85. The change
orders and costs are listed in the table below.
CO# DESCRIPTION AMOUNT
1 Pavement deduction & additional concrete work ($7,066.89)
2 Additional ADA corner ramp $4,519.49
3 Replace damaged pull boxes $2,491.44
4 Replace concrete sewer rings $742.35
5 Additional curb and gutter replacement $5,112.00
Subtotal $5,798.39
Final Adjustment for actual Measured Quantities ($33,811.24)
TOTAL ($28,012.85)
Change Order No. 1 was for various items including the initial deduction for eliminating
paving Duarte Road between Santa Anita Avenue and First Avenue, but also included
additional items such as sidewalk, curb, gutter, and ADA ramps. Change Order No. 2
was for an additional ADA curb ramp. Change Order No. 3 was to replace broken traffic
signal pull boxes that were not discovered until the adjacent concrete was removed.
Accept Work Sully-Miller Contracting Co.
for the Duarte Road Rehabilitation Project
June 6, 2017
Page 3 of 3
Change Order No. 4 was for replacing deteriorated concrete sewer manhole rings that
were not discovered until the asphalt grinding phase. Change Order No. 5 was for
removing and replacing additional curb and gutter.
The net total of all change orders and adjustments is a deduction of $28,012.85. This
changed the contract from the initial bid of $560,022 to the final amount of $532,009.15.
With regard to the segment of Duarte Road removed from this project, it is anticipated
that it will be added to the pavement rehabilitation project projected for the FY 2018-19
year, to allow enough time for the two development projects to be fully completed. The
status of the projects and the scheduling of the paving will be re-evaluated at the time of
the FY 2018-19 Capital Improvement Program preparations.
FISCAL IMPACT
Proposition “C” funds were budgeted in the amount of $800,000 for the Duarte Road
Rehabilitation Project and $150,000 for the Miscellaneous Arterial Minor Repairs Project
in the Fiscal Year 2015-16 Capital Improvement Program. The budget for the Duarte
Road project includes both the pavement rehabilitation and traffic signal work at First
Avenue and Duarte Road, and Second Avenue and Duarte Road. The traffic signal
work is being administered under a separate contract. There is sufficient funding in the
budget to cover this final construction contract amount for this project of $532,009.15,
and the traffic signal work. Upon completion of the traffic signal project, any remaining
budget will be returned to the Proposition C fund balance. The segment of Duarte Road
removed from this project, will be re-budgeted in a future year, depending on the
completion of the two private developments. The funding for this work will also be from
Proposition C.
RECOMMENDATION
It is recommended that the City Council accept all work performed by Sully-Miller
Contracting Co. for the Duarte Road Rehabilitation from Santa Anita Avenue to Fifth
Avenue and the Miscellaneous Arterial Improvements Project as complete, and
authorize the final payment to be made in accordance with the contract documents.