DATE: August 1, 2017
TO:Honorable Mayor and City Council
FROM:Sara Somogyi, Director of Recreation and Community Services
Tom Tait, Director of Public Works Services
SUBJECT:RESOLUTION NO. 7175ADOPTING THE 2017 RECREATION AND
PARKS MASTERPLAN
Recommendation: Adopt
SUMMARY
The Recreation and Community Services Department’s last Master Plan update was
completed in 2007. Since that time, the City has enacted a Parks Development Impact
Fee, which has rapidly developed a balance due to significant residential development
in the community. In order to determine the best use of the funds, the Recreation and
Parks Master Plan has been updated.
The 2017 Recreation and Parks Master Plan is a guiding policy document that provides
recommendations for prioritizing future recommendations for growth, development, and
implementation strategies related to parks and recreation services. The development
included significant input from the community at-large as well as key existing
stakeholders and is an accurate reflection of the facility needs and recreation desires of
the evolving community.
It is recommended the City Council adopt Resolution No. 7175 adopting the 2017
Recreation and Parks Master Plan.
BACKGROUND
The City of Arcadia’s goals and policies for park acquisition, park development,and
recreation program policies are addressed in the 2010 City of Arcadia General Plan.
The Recreation and Parks Master Plan is a policy document intended to guide staff
when making recommendations for specific future growth and implementation strategies
related to parks and recreation services.The current Recreation and Parks Master Plan
was adopted in 2007and many of the key programs have been implemented.In
addition, that document was developer prior to the City establishing a Parks
Development Impact Fee, which is applied to all new residential development. Due to
Resolution No. 7175 adopting the 2017Recreation
and Parks Master Plan
August 1, 2017
Page 2of 2
the pace of development in recent years, the balance of the fund has grown to over $8
million.
On April 7, 2015, the City Council awarded acontract to ICG, Inc. for acomprehensive
update of theRecreation and Parks Master Plan.ICG, Inc. and staff worked with the
community over two yearsto createthe proposed 2017 Recreation and Parks Master
Plan, which is to serve as a reference and guidefor the City’s planning and
implementation strategies for recreation services and parks for the next 20 years, as
called for by the City’s General Plan.
Pursuant to the California Government Code, the Recreation and Parks Master Plan is
being updatedto beconsistent with the City’s adopted General Plan.
DISCUSSION
The proposed 2017 Recreation and Parks Master Plan addresses all of the goals,
policies, and implementation measures of the Parks, Recreation, and Community
Resources Element of the General Plan that are identified as being the responsibility of
the Recreation and Community Services Department. The Recreation and Parks Master
Plan team gathered input from the community through a variety of methods including:
meetings with community stakeholders, andfocus groups with the Leadership
Academy, sport user groups, senior citizen groups and the Arcadia Chinese
Association.There were also a number of public workshops, a citywide phone survey,
staff surveys, website and written surveys, plus meetings with the Recreation and Parks
and Senior Citizen Commissions.In all, over 1,000people provided input into the
document.
The 2017 Recreation and Parks Master Plan is a guiding policy document that provides
recommendations for prioritizing future recommendations for growth, development, and
implementation strategies related to parks and recreation services. This is
accomplished through a detailed assessment of community demographics, needs of the
community, existing conditions of recreation and parks facilities, and effectiveness of
the various recreation and community services programs.
The Recreation and Parks Master Plan includes recommendations forparks, facilities,
and programsona four tier prioritized basis.Tier One is the highest priorityandTier
Four is the lowest priority. Examples of higher priority items included in the Recreation
and Parks Master Plan are shade over play structures, perimeter walking trails,
synthetic turf fields, pickle ball courts, and other park improvements.
On May 10, 2017, the Recreation and Parks Commission approved a motion to
recommend the City Council approve the 2017 Recreation and Parks Master Plan.
Resolution No. 7175 adopting the 2017Recreation
and Parks Master Plan
August 1, 2017
Page 3of 2
On May 23, 2017,the Planning Commission approved a motion finding the 2017
Recreation and Parks Master Plan is consistent with the 2010 City of Arcadia’s General
Plan.
The 2017 Recreation and Parks Master Plan is a guiding policy document that provides
recommendations for prioritizing future recommendations for growth, development, and
implementation strategies related to parks and recreation services. This living
document will shape the future of Arcadia and create the community that residents
desire. Through these tangible improvements to the City, Arcadia will continue to
provide the highest qualityof parks, programs, and services.
It is recommended the City Council adopt Resolution No. 7175 adopting the 2017
Recreation and Parks Master Plan.
FISCAL IMPACT
There is no fiscal impact directly related to theadoption of the 2017 Recreation and
Parks Master Plan; however, the Plan identifies over $60millionin potential
improvements to parks throughout the City. The total cost of the Recreation and Parks
Master Plan projected projects is $51.5 millionon City propertyand an additional $9
million dollars for projects at Los Angeles County Park.Projects will be included in
future budget proposals based on priorities and available funding. Key sources of
funding would be County, State, and Federal grants, the Parks Development Fund, and
the City’s Capital Projects Fund.
RECOMMENDATION
It is recommended that theCity Council adopt Resolution No. 7175adopting the 2017
Recreation and Parks Master Plan.
Attachment:Resolution No. 7175
Exhibit "A"
kûșʑ ƕÌ !Ǩl"|û"
!Ǩl"|û" ǧlǨ"șûƕŵ "ŵ| ǘ"ǨŅȀ
Ū"ȀșǨ ǘœ"ŵ ˾˼˽̃
TABLE OF CONTENTS
Page
PART 1 - INTRODUCTION
1 A: Scope & Purpose ..................................................................... 1
1 B:Planning Process......................................................................2
1 C: Public Involvement .................................................................. 3
1 D:Report Organization ................................................................ 4
1 E: Master Plan Goals.................................................................... 5
1 F: CEQA Compliance .................................................................... 5
PART 2 - EXECUTIVE SUMMARY
2 A: Existing General Plan Policy Recommendations ........................ 8
2 B: Planning Context ..................................................................... 8
2 C: Regional Context ..................................................................... 9
PART 3 - DEMOGRAPHICS & NEEDS ASSESSMENT
3 A: Community Profile ................................................................... 9
3 B: Community Outreach ............................................................ 12
Stakeholder Interviews ..................................................... 12
Full and Part Time Staff Focus Group ............................... 15
Arcadia Summer Staff Survey ........................................... 20
Web and Hard Copy Community Surveys ......................... 22
Community Phone Survey................................................. 23
Senior Citizens Outreach and Surveys..............................25
Leadership AcademyFocus Group/Comments................26
Arcadia Chinese AssociationFocus Group/Comments..... 27
Arcadia Sports GroupsFocus Group/Comments .............. 28
Los Angeles County Arcadia Regional Park
Community Workshop ...................................................... 28
PART 4 - FINDINGS, PROJECTED COSTS AND RECOMMENDATIONS
4 A: Summary of Findings and Recommendations....................... 30
4 B: 4 Tier List of Recommendations ............................................ 30
4 C: Cost Summary of Tier Recommendations ............................. 40
APPENDIX “A” Program Inventory
Evaluation & Fee Comparison
Title IX & AB 2404 Compliance
APPENDIX “B”Community Wide Phone Survey
APPENDIX “C” Community Web and Hard Copy Survey
APPENDIX “D” Projected Cost Estimates
PART 1 - INTRODUCTION
1 A: Scope and Purpose
The Community Services Department of the City of Arcadia retained
Integrated Consulting Group (ICG), for professional consulting services to
complete the work necessary to update the City’s Comprehensive
Recreation and Parks Master Plan. The previous Master Plan document was
adopted by the City Council in 2007.
The Recreation and Parks Master Plan will be the guide staff will reference
when making recommendations for future growth and implementation
strategies. The consultants worked closely with the Recreation and
Community Services Department, Development Services Department, Public Works Services Department, the
Recreation and Parks Commission, the Senior Citizens Commission, and the Master Plan Project Team consisting
of staff from Recreation and Community Services and Public Works Services Department.
The Consultants utilized several public input tools as the process to evaluate and determine the elements in need
of updating in the previous Master Plan and, along with the Project Team, developed the priorities to recommend
to the City Council for the updated Master Plan.
The Recreation and Community Services Department of the City of Arcadia operates recreation and parks
facilities which provide the opportunity for leisure activities for approximately 60,000 residents. The City of
Arcadia recognizes that properly planned development and appropriate maintenance of these facilities enhance
the quality of life of the citizens of Arcadia. The updated Recreation and Parks Master Plan provides direction to
continue the orderly and consistent planning, acquisition, development and administration of the recreation and
parks programming in the City.
The Recreation and Community Services Department of the City of Arcadia plays an important role in creating a
healthy community through diverse and innovative programming. The Department’s goal is to enhance the
quality of life in the community by providing positive recreation and leisure opportunities for people of all ages.
The Department strives to achieve this goal by encouraging citizen involvement and developing cultural harmony
which is supported by a commitment to building and maintaining community partnerships and by responding to
community needs. The Department has a nine-part mission to:
Provide recreational experiences
Foster human development
Promote health and wellness
Protect environmental resources
Facilitate community problem solving
Support economic development
Strengthen safety and security
Strengthen community image and sense of place
Increase cultural unity
EXECUTIVE SUMMARY & NEEDS ANALYSIS –City of Arcadia Recreation & Parks Master Plan 1
The City of Arcadia General Plan, which outlines the goals and objectives for parks and recreation in the Parks,
Recreation, and Community Resources Element, calls for the update of the Master Plan every 20 years.
Consequently, this Master Plan is intended to guide the City through the year 2037.
However, the document has been prepared in digital format so that it can be updated by the Recreation and
Community Services Department if necessary. As park and facility improvements are accomplished through the
City’s Capital Improvement Program (CIP); new local, state, and federal regulations are adopted; and trends in
recreation change, the document can be easily revised to reflect current conditions and new priorities.
Consequently, the Master Plan is not a one-time snapshot of the recreation and parks system, but rather a living
document to be edited and referred to in future years when planning and determining the allocation of resources
for parks, facilities, and programs.
1 B: Planning Process
The first phase of the process to update the Comprehensive Recreation and Parks Master Plan was the
assessment of needs based upon the review of existing parks and recreation related documents and the
collection of new data utilizing the following methods:
1. A thorough review of the previous Recreation and
Parks Master Plan adopted in 2007, the 2006
Recreation and Community Services Strategic Plan,
and the goals and objectives for parks and recreation
listed in the 2010 Parks, Recreation, and Community
Resources Element of the General Plan.
2. The hosting of special focus groups, such as the
seniors group “Arcadia Travelers” to start the public
input process for updating the Master Plan.
3. A review and update of the existing inventory and an analysis of parks, recreational facilities, and
trails. Each individual site plan was then updated. Aerial photographs of sites were added.
4. The identification of potential deficiencies in existing recreation and parks facilities with respect to
amenities and recreation programming needs.
5. The completion of a demand analysis for recreation and parks facilities, and recreation programs
which considered demographic trends and projections as well as an analysis of present programs.
The demand analysis included a random citywide telephone survey that consisted of 200 residents;
and a community survey responded to by 380 residents that are current users of City parks and
facilities; a senior citizen survey completed by seniors who use or are involved in senior
programming at the senior center; a survey of youth sports groups who use City fields; stakeholder
interviews with agencies, community groups and individuals with knowledge of the City’s recreation
and park facilities and programs; and surveys of full time and part time City recreation staff.
6. An analysis of the potential for improvement to existing City parks; Arcadia Regional Park operated
by Los Angeles County; Arcadia Par 3 Golf Course improvements; and various school site
improvements.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 2
7. A determination of the need for special activity facilities (i.e. youth sports facilities, teen recreation
center/gymnasium, and pickle ball courts) along with a recommendation of potential improvements
to children’s play areas in all neighborhood parks.
8. Development of a conceptual Master Plan for Arcadia Regional Park that
outlines joint City/County opportunities for the development of future
facilities within the park.
9. The development and/or update of plot plans/schematics of all existing
City parks and recreational facilities.
10. The review of the City's plan to meet the Americans with Disabilities Act (ADA) requirements and the
identification of deficiencies and a long range plan for meeting ADA requirements.
11. The review of operational and maintenance policies and standards for the park system (including
building facilities) to determine if updates are needed to maintain a safe, clean and quality parks
system.
12. A review of existing state regulations that may impact park facilities, i.e. water regulations to ensure
park improvements comply with the City’s Enhanced Watershed Management Plan (EWMP), and a
review and recommended compliance procedures for Title IX and AB 2404 regarding non-
discrimination in sports programs based on gender.
13. An analysis of the California Environmental Quality Act (CEQA) as it pertains to the adoption of the
Master Plan.
1 C: Public Involvement
The Consultant Team, working with the City, utilized a number of input tools to conduct public outreach to solicit
the public’s opinions and requests about recreation program needs and facility desires, as well as their special
insights into the operation of Recreation and Community Services programs and services.
The public outreach tools used by the Consultant Team included:
o General Public Input workshops and Surveys
o Focus Workshop with Leadership Academy
o Focus Workshop and Surveys with Sports Groups
o Focus Workshop and Survey for Senior Citizen Groups
o Citywide Community Phone Survey
o Web and Community Written Survey
o Community Services Staff Survey
o Joint LA County Master Plan Workshop
o Meeting with Arcadia Chinese Association
o Recreation and Parks Commission
o Senior Citizens Commission
The consultants and City staff talked to people utilizing City facilities while conducting park and facility inventories
and assessing conditions, in an effort to gain insight into how current park users perceive the City’s park and
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 3
recreation programs and services and what ideas they may have for possible improvements, additions, or
changes that would better serve their needs.
The survey firm Research Network Ltd. was retained to conduct the “Community Phone Survey.” The purpose of
the survey was to obtain statistically valid, community-wide input on a variety of issues related to Arcadia
residents’ use of parks, facilities and programs and their preferences for future improvements to Arcadia’s parks.
The information gained from the input tools was analyzed, then summarized and finally incorporated into the
Demand & Needs Analysis.
1 D: Report Organization
The updated comprehensive Recreation and Parks Master Plan contains five
sections. This format was chosen to make the Master Plan easy to work
with and understand. Given the tremendous amount of data, graphics,
number of facilities and analysis, separating the documents so they can be
accessed and used individually makes it easier for the reader to find the
areas or portions of the Master Plan they are interested in. The following is
a list of each section contained in the Master Plan:
Section 1 – Executive Summary and Needs Analysis
Section 2 – Arcadia Park Facilities
Section 3 – Los Angeles County Park Facilities
Section 4 – Joint Use Parks and Facilities
Section 5 – Park and Facility Standard Specifications
Section 1 is the Introduction and Executive Summary, which includes a summary of park and facility
recommendations with estimated costs, which were developed from the results of the community outreach tools
and the demand analysis for facilities and programs. It provides an overview of the documents contained in the
Master Plan. It also gives an overview of the planning context and Master Plan goals.
Section 2 is a complete inventory of existing Arcadia park facilities displayed in aerial format showing existing
amenities and the conceptual plans for future improvements. Also included is a summary of the
recommendations proposed for each site.
Section 3 is a complete inventory of existing Los Angeles County park facilities displayed in aerial format showing
existing amenities and the conceptual plans for future improvements. Also included is a summary of the
recommendations proposed for each site.
Section 4 is a complete inventory of existing schools serving Arcadia displayed in aerial format showing existing
amenities.
Section 5 is a listing of park amenity, playground, trail, building and restroom, and irrigation standards.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 4
1 E: Master Plan Goals
The Arcadia City Staff Project Team developed several Master Plan goals to guide the consultant team in the
Master Plan process. It was agreed that the Master Plan needed to do the following in order to be a document
the Recreation and Community Services Department could use to guide its facility and program development in
the future:
1. Describe current and future demographic projections and regional context;
2. Examine the current conditions of parks, trails and facilities;
3. Study and analyze current public demand and needs for parks, recreation and cultural facilities,
programs and special events;
4. Recommend improvements to existing parks, facilities, and opportunities for joint use;
5. Examine and analyze current policy documents;
6. Recommend future uses and proposed amenities at Wilderness Park;
7. Describe costs and priority actions to enable the City to implement the recommendations.
1 F: California Environmental Quality Act (CEQA) Compliance
`
The Recreation and Parks Master Plan is one of the implementation measures in the Parks, Recreation, and
Community Resources Element of the City’s General Plan. Specifically, Chapter 7-30 Goal PR-4 “A network of
City, school, and private community facilities that provides spaces for recreation, education, enrichment,
and social service programs.”
The proposed Master Plan is in line with CEQA Guideline 15262 in that it is a type of feasibility and planning
study that does not legally bind the City to act on any of the projects discussed in the document, and does
not provide funding for those projects. The proposed Recreation and Parks Master Plan should be Statutorily
Exempt from CEQA under Article 18, Section 15262 of the CEQA Guidelines. This approach is widely used for
master planning documents of this type. The justification for this finding is best explained as follows:
“The adoption of this Plan is exempt from the California
Environmental Quality Act (CEQA), Public Resources Code Section
21000, et seq. under CEQA Guideline 15262. That Guideline exempts
planning studies for possible future action, since the possible future
action (e.g. parkland acquisition and development) is not being
approved as part of the action to adopt this Plan. This Plan is not
intended to be legally binding on the future actions of the Planning
Commission (or Parks and Recreation Commission) or the City
Council, but rather as a guide to formulate potential future actions
which will be assessed pursuant to the City’s normal processing
requirements, including CEQA review. The adoption of this Plan is not intended to commit the City to any definite
course of action in regards to the acquisition or development of parkland and recreational amenities.”
The City will need to file a Notice of Exemption (NOE) with the County of Los Angeles and pay the applicable filing
fee immediately following the adoption of the Recreation and Parks Master Plan.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 5
Since the Recreation and Parks Master Plan also includes some detailed park and facility specification standards,
and specific recommendations for repair and replacement of existing facilities, it is also suggested the City add two
Categorical Exemptions to the NOE: Section 15301 exempts repairs/rehab to existing facilities; Section 15302
covers replacement or reconstruction of existing structures and facilities.
15301. EXISTING FACILITIES Class 1 consists of the operation, repair, maintenance, permitting, leasing, licensing, or
minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features,
involving negligible or no expansion of use beyond that existing at the time of the lead agency‘s determination. The
types of existing facilities itemized below are not intended to be all inclusive of the types of projects which might fall
within Class 1. The key consideration is whether the project involves negligible or no expansion of an existing use.
Examples include but are not limited to: (a) Interior or exterior alterations involving such things as interior
partitions, plumbing, and electrical conveyances; (b) Existing facilities of both investor and publicly owned utilities
used to provide electric power, natural gas, sewerage, or other public utility services; (c) Existing highways and
streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities
(this includes road grading for the purpose of public safety). (d) Restoration
or rehabilitation of deteriorated or damaged structures, facilities, or
mechanical equipment to meet current standards of public health and safety,
unless it is determined that the damage was substantial and resulted from an
environmental hazard such as earthquake, landslide, or flood; (e) Additions to
existing structures provided that the addition will not result in an increase of
more than:
Association of Environmental Professionals 2016 CEQA Guidelines 247
(1) 50 percent of the floor area of the structures before the addition, or 2,500 square feet, whichever is less; or (2)
10,000 square feet if: (A) The project is in an area where all public services and facilities are available to allow for
maximum development permissible in the General Plan and (B) The area in which the project is located is not
environmentally sensitive. (f) Addition of safety or health protection devices for use during construction of or in
conjunction with existing structures, facilities, or mechanical equipment, or topographical features including
navigational devices; (g) New copy on existing on and off-premise signs; (h) Maintenance of existing landscaping,
native growth, and water supply reservoirs (excluding the use of pesticides, as defined in Section 12753, Division 7,
Chapter 2, Food and Agricultural Code); (i) Maintenance of fish screens, fish ladders, wildlife habitat areas, artificial
wildlife waterway devices, stream flows, springs and waterholes, and stream channels (clearing of debris) to
protect fish and wildlife resources; (j) Fish stocking by the California Department of Fish and Game; (k) Division of
existing multiple family or single-family residences into common-interest ownership and subdivision of existing
commercial or industrial buildings, where no physical changes occur which are not otherwise exempt; (l) Demolition
and removal of individual small structures listed in this subdivision: (1) One single-family residence. In urbanized
areas, up to three single-family residences may be demolished under this exemption. (2) A duplex or similar
multifamily residential structure. In urbanized areas, this exemption applies to duplexes and similar structures
where not more than six dwelling units will be demolished. (3) A store, motel, office, restaurant, or similar small
commercial structure if designed for an occupant load of 30 persons or less. In urbanized areas, the exemption also
applies to the demolition of up to three such commercial buildings on sites zoned for such use. (4) Accessory
(appurtenant) structures including garages, carports, patios, swimming pools, and fences. (m) Minor repairs and
alterations to existing dams and appurtenant structures under the supervision of the Department of Water
Resources. (n) Conversion of a single family residence to office use. (o) Installation, in an existing facility occupied by
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 6
a medical waste generator, of a steam sterilization unit for the treatment of medical waste generated by that
facility provided that the unit is installed and operated in accordance with the Medical Waste Management Act
(Section 117600, et seq., of the Health and Safety Code) and accepts no offsite waste. (p) Use of a single-family
residence as a small family day care home, as defined in Section 1596.78 of the Health and Safety Code. Note:
Authority cited: Section 21083, Public Resources Code; References: Sections 21084, Public Resources Code; Bloom v.
McGurk (1994) 26 Cal.App.4th 1307.
Association of Environmental Professionals 2016 CEQA Guidelines 248”
“15302. REPLACEMENT OR RECONSTRUCTION Class 2 consists of
replacement or reconstruction of existing structures and facilities
where the new structure will be located on the same site as the
structure replaced and will have substantially the same purpose and
capacity as the structure replaced, including but not limited to: (a)
Replacement or reconstruction of existing schools and hospitals to
provide earthquake resistant structures which do not increase
capacity more than 50 percent. (b) Replacement of a commercial
structure with a new structure of substantially the same size,
purpose, and capacity. (c) Replacement or reconstruction of existing utility systems and/or facilities involving
negligible or no expansion of capacity. (d) Conversion of overhead electric utility distribution system facilities to
underground including connection to existing overhead electric utility distribution lines where the surface is
restored to the condition existing prior to the undergrounding. Note: Authority cited: Section 21083, Public
Resources Code; Reference: Section 21084, Public Resources Code. 15303. NEW CONSTRUCTION OR CONVERSION
OF SMALL STRUCTURES Class 3 consists of construction and location of limited numbers of new, small facilities or
structures; installation of small new equipment and facilities in small structures; and the conversion of existing
small structures from one use to another where only minor modifications are made in the exterior of the structure.
The numbers of structures described in this section are the maximum allowable on any legal parcel. Examples of
this exemption include, but are not limited to: (a) One single-family residence, or a second dwelling unit in a
residential zone. In urbanized areas, up to three single-family residences may be constructed or converted under
this exemption. (b) A duplex or similar multi-family residential structure, totaling no more than four dwelling units.
In urbanized areas, this exemption applies to apartments, duplexes and similar structures designed for not more
than six dwelling units. (c) A store, motel, office, restaurant or similar structure not involving the use of significant
amounts of hazardous substances, and not exceeding 2500 square feet in floor area. In urbanized areas, the
exemption also applies to up to four such commercial buildings not exceeding 10,000 square feet in floor area on
sites zoned for such use if not involving the use of significant amounts of hazardous substances where all necessary
public services and facilities are available and the surrounding area is not environmentally sensitive. (d) Water
main, sewage, electrical, gas, and other utility extensions, including street improvements, of reasonable length to
serve such construction. (e) Accessory (appurtenant) structures including garages, carports, patios, swimming
pools, and fences. (f) An accessory steam sterilization unit for the treatment of medical waste at a facility occupied
by a medical waste generator, provided that the unit is installed and operated in accordance with the Medical
Waste Management Act (Section 117600, et seq., of the Health and Safety Code) and accepts no offsite waste.
Note: Authority cited: Section 21083, Public Resources Code; Reference: Sections 21084, Public Resources Code.
15304. MINOR ALTERATIONS TO LAND Class 4 consists of minor public or private alterations in the condition of
land, water, and/or vegetation which do not involve removal of healthy, mature, scenic trees except for forestry or
agricultural purposes. Examples include, but are not limited to:
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 7
Association of Environmental Professionals 2016 CEQA Guidelines 249
(a) Grading on land with a slope of less than 10 percent, except that grading shall
not be exempt in a waterway, in any wetland, in an officially designated (by federal,
state, or local government action) scenic area, or in officially mapped areas of
severe geologic hazard such as an Alquist Priolo Earthquake Fault Zone or within an
official Seismic Hazard Zone, as delineated by the State Geologist. (b) New
gardening or landscaping, including the replacement of existing conventional
landscaping with water efficient or fire resistant landscaping. (c) Filling of earth into
previously excavated land with material compatible with the natural features of the
site; (d) Minor alterations in land, water, and vegetation on existing officially
designated wildlife management areas or fish production facilities which result in
improvement of habitat for fish and wildlife resources or greater fish production; (e)
Minor temporary use of land having negligible or no permanent effects on the environment, including carnivals,
sales of Christmas trees, etc.; (f) Minor trenching and backfilling where the surface is restored; (g) Maintenance
dredging where the spoil is deposited in a spoil area authorized by all applicable state and federal regulatory
agencies; (h) The creation of bicycle lanes on existing rights-of-way. (i) Fuel management activities within 30 feet of
structures to reduce the volume of flammable vegetation, provided that the activities will not result in the taking of
endangered, rare, or threatened plant or animal species or significant erosion and sedimentation of surface waters.
This exemption shall apply to fuel management activities within 100 feet of a structure if the public agency having
fire protection responsibility for the area has determined that 100 feet of fuel clearance is required due to extra
hazardous fire conditions. Note: Authority cited: Section 21083, Public Resources Code; Reference: Section 21084,
Public Resources Code. 15305. MINOR ALTERATIONS IN LAND USE LIMITATIONS Class 5 consists of minor
alterations in land use limitations in areas with an average slope of less than 20%, which do not result in any
changes in land use or density, including but not limited to: (a) Minor lot line adjustments, side yard, and set back
variances not resulting in the creation of any new parcel; (b) Issuance of minor encroachment permits; (c) Reversion
to acreage in accordance with the Subdivision Map Act. Note: Authority cited: Section 21083, Public Resources
Code; Reference: Section 21084, Public Resources Code.”
PART 2 - EXECUTIVE SUMMARY
2 A: Existing General Plan Policy Recommendations
The City of Arcadia has a set of park acquisition, park development, and program policies it has developed over the
years which are contained in the City of Arcadia General Plan. The policies contained in Chapter 7: Parks,
Recreation, and Community Resources Element of the General Plan (Policy PR 1.1 through PR 1.20 and Policy PR
2.1 through PR 2.5) are current and up to date and should continue to be the operating policies to guide the City in
developing and maintaining its recreation and parks system.
2 B: Planning Context
This section provides an overview of the planning context for which the Master Plan was prepared. Arcadia serves
local and regional residents, so knowing the service area for the Recreation and Community Services Department is
important to understand. The City’s population, income and age demographics, and ethnic composition affect
what programs, facilities and services will be needed within the community.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 8
2 C: Regional Context
Arcadia is located about 13 miles (21 km) northeast of downtown Los
Angeles in the San Gabriel Valley and at the base of the San Gabriel
Mountains.
It is the site of the Santa Anita ParkRacetrack and home to the Los
Angeles County Arboretum and Botanic Garden. The city is named
after Arcadia, Greece.
In 2012, Arcadia was ranked 7th in the nation on CNN Money
magazine's list of towns with highest median home costs.
Arcadia is the second best city in all of Los Angeles County for raising a family and #1 in San Gabriel Valley,
comes five
according to lifestyle rating service Niche.com. The recognition in the 2015 Niche Best Places Rankings
years after Business Week Magazine declared Arcadia the best city in the entire state of California to raise kids for
two years in a row in 2009 and 2010.
Arcadia's Upper Rancho neighborhood was ranked the 23rd richest neighborhood in Southern California by
Business Insider in 2014; out ranking Orange County's Newport Beach with a median household income of
$310,779.
Cities that border Arcadia include Monrovia, Sierra Madre, Pasadena, San Marino, Temple City, and El Monte as
shown in the map below.
San Marino
Temple City
PART 3 - DEMOGRAPHICS & NEEDS ASSESSMENT
3 A: Community Profile
The City of Arcadia is an established community with a diverse population. Per City-Data.Com the community
demographic profile for Arcadia is as follows:
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 9
Population in 2013: 57,639 (100% urban, 0% rural)
Population change since 2000: +8.6%
Males 47.1% - Females 52.9%
Median resident age 43.9 years (California average is 35.7 years)
Estimated median house or condo value in 2013: $802,400
2013 cost of living index in Arcadia: 140.3 (very high, U.S. average is 100)
Unemployment in June 2014 was 4.6% (California average is 7.3%)
Population by age (2014)
Under 17 17.2%
18 to 55 44.1%
55 & Over 38.7%
Demographic Summary:
Population density in Arcadia is 2,155% higher than California average
Median age in Arcadia is 21% higher than California average
Cost of living is 39.6% higher than US average
58.90% of the population is Asian
26.30% of the population is Caucasian
11.30 % Hispanic
Remaining population is African American or other races
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 10
Consequently, higher than average density, older population, changing cultural heritages, and higher than
average cost of living are all factors that need to be taken into consideration when planning for delivery of
recreation and community services and designing community facilities.
Demographic Projection and Correlation to Recreation:
There has been an upward trend in the Asian population over the past
decade and that trend is projected to continue. Because of the median
home prices and relatively high cost of living the minority populations are
projected to remain constant. The median age is projected to continue to
increase over the next 20 years as post World War II “Baby Boomers”
reach retirement age. Density is also expected to increase as older
properties are recycled to meet the housing demand created by the
increase in population generated by Arcadia being a desirable place to live
and the excellent reputation of the schools in Arcadia. These projections correlate to the demand for recreation
programs and facilities that meet the cultural diversity of Arcadia, address increasing density, take into account
the mature population, and meet the needs of young families that may struggle with the high cost of living in
Arcadia.
NRPA Current Recreation Trends That Could Affect Local Program Demand:
The following list of national trends in recreation was developed by the National Recreation and Parks
Association. These trends can be used as a guide for the Department in the future for programming.
1. Health and Fitness - Energizing fitness classes, studio space for Yoga, Zumba, Pilates and Dance.
Active lifestyles are a trend in all age, ethnic, and income demographics.
2. Education Classes - Technology and software classes for computers, tablets and smart phone
devices, web-based continuing education, new career training, volunteer placement services, guest
speakers, homework/tutoring programs for teens are all trends in higher median income
communities.
3. Walking and Hiking Trails - Lighted pathways in parks, connecting bike trails, outdoor adventures,
wilderness activities, and nature programs are trends in communities where green and natural
lifestyles are important to residents.
4. Active Community Centers - Social lounge areas, serving individual and
family needs, the needs of clubs and organizations within the service
area, multipurpose spaces, game rooms and classrooms, and
community event space trend big in diverse communities with high
percentage of senior population.
5. Outdoor Performance Facilities - Concerts, movies in the park, and
community events are trends in communities with extended families
and are culturally diverse.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 11
6. Dog Parks - Growing demand nationally and locally, provides for community social interaction in age
of social media.
7. Golf Courses - Regulation and Par 3 and practice facilities, along with foot golf capabilities. Per the
National Golf Foundation, Asians account for the fastest growing segment of the population playing
golf.
8. Multi-Purpose Gymnasium - Basketball, volleyball, badminton,
group exercise classes. The trend in successful communities is for
gymnasiums that have a full basketball court with two cross courts,
which can also accommodate four volleyball courts, futsal, and
large group exercise classes. These multi-purpose gyms are usually
built with a second level walking track around the perimeter of the
inside of the gym.
3 B: Community Outreach
ICG, the consultant team working with the City, utilized a number of methods to conduct public outreach to
solicit the public’s opinions and requests about recreation program needs and facility desires, as well as their
special insights into the operation of Recreation and Community Services Department programs and services.
The following is the summary of the information gathered:
Stakeholder Interviews
ICG conducted 21 interviews with selected community leaders, civic
organizations, and representatives of agencies the City partners with to
deliver community services to residents in Arcadia as part of the outreach
process for the Recreation and Community Services Master Plan. Getting
feedback and insight from community stakeholders is an important tool in the
overall determination of what the priorities should be for park and facility
improvements and the direction recreation and community services
programming should take in the future.
The interviews were confidential to encourage open dialogue and honest opinions of the state of facilities and
recreation programs in Arcadia. Below is the list of people interviewed and a summary of their comments,
opinions, and suggestions divided into what they said collectively about (1) Park and Facility Improvements; (2)
Programs and Services; and (3) Future Needs.
Those interviewed included:
1.Jim Leahy, Executive Director Facilities & Operational Services, Arcadia Unified School District
2.Christina Aragon, Assistant Superintendent Business Services, Arcadia Unified School District
3.Jason Cho, Arcadia Riptides Swim Club
4.Gail Marshal, former Mayor, Republican Woman’s Federation
5.Matt McSweeney, owner Matt Denney’s Restaurant, Arcadia Downtown Business Association
6.Glynna Harper, Senior Citizens Commissioner, Senior Friendship Club, Senior Traveler’s Club
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 12
7.Scott Hettrick, Arcadia Chamber of Commerce, Arcadia’s Best Website, Downtown Business
Association
8.Dominic Lazzaretto, Arcadia City Manager
9.Kay Kinsler, Arcadia Assistance League
10.Carl Kissel, Retired Teacher, Arcadia Resident
11.Pete Siberell, Santa Anita Race Track
12.Jesse Sanford, Manager Arcadia Par 3 Golf Course
13.Mark Budde, Arcadia Resident
14.Cung Nguyen, AYSO Region 2 Board Member, Arcadia Unified School District Board Member
15.Carter Spruill, representing “Hope Can Cure Cancer Club”, Bark for Life
16.Roberta White, Retired Arcadia Recreation & Community Services Director
17.Sherry Tay – Arcadia Chinese Association
18.Jason King – Choicess
19.Steve Phillippi – Former Recreation & Parks Commissioner
20.Lori Phillippi – Former Recreation & Parks Commissioner and School Board Member
21.Clifford Daniels – Methodist Hospital
The following is a compilation of suggestions by the stakeholders for what they believe should be
improvements to include in the Recreation and Parks Master Plan:
1. Park Facility Improvements
Lighted walking trails with distance markers
Remodel or rebuild clubhouse to expand meeting/
classrooms, youth classes, concessions and driving range
at Arcadia Par 3 Golf Course
Upgrade and offer more diversity of play in the tot lots in
neighborhood parks
Lighted sports fields that are multi-purpose for soccer,
football and lacrosse.
Upgrade and reopen restrooms in the parks
Replace natural turf with artificial turf to reduce water consumption and extend playability
Make improvements at Wilderness Park including kitchen, play area, classrooms, and hiking trails
Address the problem of after-hours unauthorized use of parks and schools with better security and
possibly a community service officer program
Find ways to install bike trails both on and off highways to connect parks, schools, and points of
interest in Arcadia
Develop a dedicated teen center
Use the trails along the flood control channels to develop multi-purpose for walking, jogging, and
biking
Look into the possibility of developing a municipal pool for swim lessons, open swimming and
competitive swim programs
Look for ways to develop another gym to relieve the impacts on the current Dana Gym
Install a band shell or stage at City Hall Lawn with electricity for concerts and movies in the park
Install a concrete plaza area at City Hall Lawn so that people can dance at concerts in the park
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 13
Develop an information kiosk at the Gold Line Train Station to give information on recreation and
community services
Install new blinds, replace table and chairs, fix flooring and expand the kitchen in the
community/senior center
Consider developing a walking trail around the perimeter of the City Hall Lawn
Provide sail shade structures at all tot lot areas in neighborhood and community parks
Change out tennis court lights from sodium vapor (yellow light) to light-emitting diode (LED/white
light)
Expand the community/senior center to include a computer lab
Improve Americans with Disabilities Act (ADA) access throughout all City facilities
Develop lighted outdoor basketball courts throughout the park system
Improve the archery range, fire pits and barbeques at Wilderness Park
Add a second dog park in Arcadia in the Southwest portion of the City
Add more tennis courts and pickle ball courts
2. Programs and Services
Expand programs for pre-school and tiny tots
Look for ways to grow the Foot Golf program at Arcadia Par 3 Golf Course
Expand activities and programs for science and technology
Initiate a street fair/nationality day in Arcadia
Expand the joint-use agreements with the schools to make them more
accessible and add more programming for residents
Continue to expand the concerts and movies in the park
Add a shuttle system from the Gold Line Train Plaza to Santa Anita Park,
Community/Senior Center, Arboretum and Arcadia County Regional Park
Give Arcadia residents priority for participation in programs
Initiate a program where residents can dispose of old flags
Expand citywide events to attract more people downtown such as a Chalk
Art event
Increase “Mommy and Me” programs
Work with local organizations that serve the disabled to increase their access and participation in
programs
Expand the summer youth camp programs to include more specialty camps for sports, science and
technology
3. Future Needs
Increase local transportation opportunities for youth and seniors
Upgrade signage and banners to include both English and Chinese
Try to address the problem of the homeless population using parks and schools
Address the issues of overcrowding, scheduling and maintenance of sports fields in Arcadia
Address the need for water conservation throughout the park system
Try to market active programs as “healthy lifestyle” activities
Address the issue of older adults wanting more active programs
Look for ways the City can co-promote programs with local organizations
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 14
Prepare for the opening of the Gold Line Train Station and the change of demographics it will bring
to the City
Address ways in which parks and facilities can be more environmentally friendly
Try to improve Arcadia’s aging park facilities
Explore ways to provide Wi-Fi in all parks and facilities
The stakeholder comments as well as the input received in the other outreach methods used in the Master Plan
process were used to determine recommendations and priorities for facility improvements and future programs
listed in Section 4 of the Executive Summary.
Full and Part Time Staff Focus Group
As part of the ICG outreach process for the Recreation and Park Master Plan, two staff focus group meetings were
held to gain insight into both full time and part time staff opinions as to program and facility needs. The following
is the summary and analysis of those focus groups.It is important to know a few things about the staff that
responded and gave their input in order to assess the facilities they work in, the age groups they work with, how
they feel about their working conditions, and if they believe they are receiving enough training to make them
comfortable doing their jobs. A total of 54 staff of the Recreation and Community Services Department
participated in the Staff Focus Groups and completed the staff questionnaire.
65% work or have worked in the Arcadia Community/Senior Center
59% work or have worked at the Wilderness Park
52% work or have worked at all the school district facilities the City runs programs
28% work or have worked programs at the City Hall Lawn
22% work or have worked at Bonita Park and Eisenhower Park
Less than 10% work or have worked at remaining City facilities
Summary: The Staff Focus Group responses represent a good cross section of opinions from those individuals who
have worked in the City’s most popular facilities and have a working knowledge of the facility needs.
The age groups the Staff Focus Groups work with include:
Under 5 19%
5 to 9 69%
10 to 14 68%
15 to 19 28%
20 to 24 22%
25 to 34 22%
35 to 44 22%
45 to 54 35%
55 to 64 39%
Ages 65+ 40%
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 15
Summary: While most of the group worked with youth and teens, there was a good representation of opinions
expressed in the questionnaire from staff that have worked with all age groups. These staff are familiar with
activity and program needs of all age groups. Most of the staff has worked with youth, so there will be a slight
bias toward opinions related to youth needs, but there were a sufficient number of responses from staff who have
worked with seniors to make the overall responses representative of all ages.
With regards to how they felt about the maintenance and physical conditions they work in the responses were as
follows:
20% were “Very Satisfied”
55% were “Somewhat Satisfied”
25% were “Somewhat Dissatisfied”
No one was “Very Dissatisfied”
Summary: Those that worked in City facilities were more satisfied with conditions than those that worked at
School District facilities. Those that worked at Wilderness Park were also less satisfied with their working
conditions. A major factor for this response is from working outdoors all day long in the summer heat.
Training is directly related to the delivery of successful programs and services to the public. Below is the Staff
Focus Group summary of how satisfied they are with the training they receive.
22% thought their training was excellent
30% thought their training was very good and they received what they needed
41% said their training was good, but would like more
5% thought the training was only fair and really would like more
2% thought their training was poor and had to figure things out on their own
Summary: A little over half of the staff feel their training is adequate and what they need for their job; however, a
little under half of the staff responded they would like more training. As a group, part time staff rated their
training higher than the full time staff did.
Front line staff attitudes are often conveyed to the public and public attitudes
conveyed to staff, either directly or indirectly through conversations and
comments, and an important factor in weighing public attitudes about
recreation facilities is to see what attitudes staff has about facilities. The staff
opinions of how Arcadia facilities compare to other cities staff has worked in
or visited are as follows:
28% believe Arcadia has better facilities than other cities they have worked in or visited
24% believe they are the same
48% feel other cities have better park facilities than Arcadia
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 16
Summary: The responses show there are a significant number of opinions Arcadia needs to upgrade their facilities
or add new facilities to offer the same quality of life opportunities as other cities staff has worked in or visited.
Staff is constantly getting feedback from program participants and is therefore a good indicator of how the public
perceives the quality of programs offered in Arcadia. The following is how staff responded to how they feel the
public rates the quality of recreation programs and services in Arcadia.
37% responded they think the public they work with feels the quality of programs is excellent
56% responded they think the public thinks the quality of programs is good
7% responded they think the public thinks the quality of programs is just fair
Summary: A very high 93% of staff believes the public thinks the quality of programs offered in Arcadia are good
to excellent. This indicates a high rate of positive feedback from the public to staff and an indication the public is
very satisfied with program quality.
Staff may also be in a position to receive feedback from participants and the
public on why people drop out of programs or don’t take advantage of the
program opportunities available to them. Consequently, staff’s opinion of why
people don’t participate, or are unable to participate, in programs is a valuable
tool to assess how the City might address any barriers to participation. The staff
opinions on the reasons people may not participate in programs in Arcadia were
as follows:
72% believe people are unaware of program offerings
46% believe it is because classes are full
41% believe it is because people are too busy and have no time
37% believe it is due to programs being held at inconvenient times
33% believe it is because they need childcare to participate
18% believe it is because there is not enough variety of programs
18% believe programs are too expensive and people can’t afford them
12% believe it is because they need transportation to participate
Summary: The staff responses show there is probably a wide variety of reasons for lack of
participation by some in the community. Being unaware, classes being full, and people not
having time were the main reasons staff thought people did not participate. About a third of the
Staff Focus Group thought it is because of logistical reasons, such as, programs are at
inconvenient times for them, they need childcare, or they could not afford them. Only a few felt
it was because of transportation issues.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 17
Finding out what benefits people want from spending their leisure time recreating is important to plan programs
and space for the future to ensure those desires are met in the delivery of recreation and community services.
Since Recreation and Community Services staff receives comments and have personal contact with the public
they serve, finding out what staff thinks the benefits people want from leisure services is an important tool in
assessing public needs for facilities and programs. The following were the staff responses to that question.
79% said their constituents are looking for opportunities to enjoy nature and
the outdoors
56% said they believe people are looking for programs that promote youth
mental and physical health
56% also said people are looking to improve physical fitness, health, and
wellness
48% said people want places and opportunities for the community to come
together
47% said people want cultural opportunities
45% said people are looking for lifelong learning opportunities
29% felt people were looking to help seniors stay active and healthy
28% felt people want to help people with disabilities feel included and remain socially active
Summary: These responses were compared with the answers received in the community and phone surveys and
then used to develop priorities for park improvements.
In order to prioritize staff and facility resources for the future in the Master Plan, it is important to try to
determine what the Recreation and Community Services Department’s focus should be for the next 20 years.
Staff was asked what they thought the Department’s focus should be and responded as follows:
56% said the focus should be on upgrading existing parks
46% said the Department should focus on providing new sports fields and facilities
41% said the Department should focus on providing more recreation programs and activities
29% said the focus should be on maintaining existing facilities
22% thought the focus should be on preserving open space
21% thought the focus should be adding to the trail system
10% felt acquiring land for future parks should be the focus
Summary: Staff responses definitely lean toward upgrading existing facilities, providing new sports fields and
increasing recreation programs as the focus for the Department in the future. Although, there was staff support
for the Department to focus on all areas. These responses were analyzed and combined with the public response
in the community and phone surveys, and then used to determine park improvement priorities.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 18
By increasing cultural unity, it can strengthen the community image and sense of place. Determining cultural
priorities so resources can be allocated according to needs addressed in the Master Plan. Staff responses as to
what they think the cultural priorities are in the community were as follows:
37% felt “Entertainment Events” are the most important to the community
22% thought “Trips and Tours” most important
20% thought “Cultural Festivals” most important
19% thought “Dance and Music” the most important
11% thought Arts and Crafts programs most important
Summary: There was a fairly even distribution of opinions about what cultural opportunities are important to the
community. There was no one type of cultural activity staff thought was significantly more important than all the
others. These answers were analyzed and compared to answers in the community phone survey, and then used to
determine recommendations in the Master Plan.
Staff was asked in three different questions what park and facility improvements they thought the City most
needed to address in the Master Plan. The answers to the three questions were tallied and compared and then
merged into the top 10 priority outcomes below:
1. Improvements to Wilderness Park 6. Space for teen activities
2. Lighted walking paths 7. More classroom space
3. A multipurpose gym 8. City Hall Lawn improvements for concerts and movies
4. Outdoor basketball courts 9. Park restroom improvements
5. More lighted sports fields 10. Improvements to children’s play equipment in parks
Summary: The staff responses on priorities for park and facility improvements reflect
their answers to the question about what they think the benefits the public is looking
for in their leisure time. For example, the number one answer for the benefits the
public is looking for was “constituents are looking for opportunities to enjoy nature
and the outdoors,” and the highest rated improvements they think the City needs to
address are at Wilderness Park and more lighted walking trails. The priorities for a
new gym, lighted basketball courts and more lighted fields correspond to their
answers that “people are looking for programs that promote youth mental and
physical health.” These answers were consistent with the answers from the community surveys and workshops
and used to determine the Master Plan recommendations for facility improvements.
Finally, staff was asked “What one improvement do you think would most benefit the community?” Staff
responses are usually a good gauge of community desires as they are the ones who receive the front line
comments/complaints and requests for facilities and programs. Their responses included the following (not in
priority order):
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 19
Lighted walking trails
Shade structures over neighborhood park playgrounds
Lighted outdoor basketball courts
A teen center
Nature Center improvements at Wilderness Park with directional signage
Kitchen improvements at Wilderness Park
Remodel community center kitchen
A child-care center
Wi-Fi connection at Wilderness Park
Play equipment at Wilderness Park
A new multi-purpose sports complex
Classroom/meeting room at Wilderness Park
A new gym and fitness center
Arcadia Summer Staff Survey
ICG conducted a focus group exercise as part of the orientation and training
for the Recreation and Community Services Department’s summer staff. After
being given a presentation of the Master Plan process, the group was divided
into four sections and spent 30 minutes focusing on what improvements are
needed at Wilderness Park to address functionality, safety, access, and
program expansion.
The following is a summary of each section’s comments and opinions:
Summer Staff Section I Comments:
A small amphitheater for events and presentations
Cabins so that overnight and extended stay camps can be accommodated
Improved hiking trails
Shaded picnic area with barbeques
Vehicle access bridge at Wilderness Park
Vending machines
Larger space for kids outdoor games
Game room for indoor games
Remodel and expand the kitchen
Parking lot improvements
Safe house for kids to protect against bears
Outdoor basketball court
Interpretive nature trail
Waterfall and swim area
Wi-Fi access and cell service
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 20
Fire outlook station
Trail map
Summer Staff Section II Comments:
Improved trails with handrails
Add a classroom for indoor activities
Add an arts and crafts room
Provide live animal exhibits
Add an outdoor basketball and volleyball court
Add a zip line activity
Improve signage
Put in a full kitchen with air conditioning
Add storage space for supplies
Install fans near the lunch tables
Add a swimming feature
Remodel the archery range and make it bigger
Provide shade and improved picnic and barbeque facilities
Address the drainage and put in a catch basin
Summer Staff Section III Comments:
Improve existing trails and add more trails with signage
Make more accessible parking
Add an academic center with computers and place for music and other classes
Add a toddler and preschool camp program
Improve and add water fountains
Build a designated classroom
Provide a lighted basketball court
Update and expand the archery range
Provide a themed nature playground
Redo the fire pit and add a stage or amphitheater
Provide more storage space for day camp supplies
Fix the bridge into Wilderness Park and provide vehicle access
Add live animal exhibits and displays
Improve and expand the kitchen
Summer Staff Section IV Comments:
Add an outdoor basketball court
Add an obstacle course
Upgrade and expand the archery course
Operate a camp for adults at Wilderness Park to promote awareness of the park
Upgrade and expand the kitchen
Create an area for tents for overnight and extended camp programs
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 21
Make Wi-Fi and cell service available
Add a classroom and arts and crafts center
The most common suggestions for improvements among the four summer staff sections were:
Wilderness Park kitchen improvements
Upgrading the Archery course
Improving the parking
Adding Wi-Fi and cell service
Improve and add trails
Address the need for classroom space
Adding an outdoor basketball court
Web and Hard Copy Community Surveys
ICG conducted a community survey aimed at getting input from recreation program participants and facility users
whereby residents could access the survey and respond to it through the City’s website, or pick up a hard copy at
park and recreation facilities, fill it out and return it to the City.
The community survey was a comprehensive questionnaire covering resident use patterns, demographics, and
opinions on what park users would like in the way of park improvements and programs.
The following is a summary of the community survey results (the entire results are contained in Appendix C –
Community Web & Hard Copy Survey):
A total of 380 responses were received, 72% from Arcadia
residents and 28% from residents in surrounding cities. This
very closely matches the average non-resident participant rate
that attend Arcadia programs, which is about 25%. Residents
from surrounding cities are drawn to Arcadia because of the Los
Angeles County Arcadia Regional Park and the City of Arcadia
Par 3 Golf Course, as well as the Los Angeles County Arboretum
and the Santa Anita Race Track. Consequently, the survey statistically represents the percentage
distribution of participants who actually use Arcadia programs and facilities and can be considered a
valid indication of the opinions of users of Arcadia programs and facilities.
The benefits people wanted most from participating in recreation programs are:
o Opportunities to enjoy events and activities with other people
o Improve fitness, health and wellness, and
o Help seniors maintain socially active lifestyles
Cultural programs were important to people, especially art, music, and dance.
The most used facilities are the Arcadia Community/Senior Center, neighborhood parks, and sports
fields with 75% of the responders saying they use those facilities.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 22
88% responded that they attend the special events put on by the Recreation and Community
Services Department.
There was a 90% satisfaction rate among the users with the quality of
maintenance for City of Arcadia parks and facilities.
75% responded that they have participated in programs offered by the
Recreation and Community Services Department with most participation
in youth and senior programs and 88% saying the quality of programs is
good to excellent.
Of those people who said they have not participated in recreation programs in Arcadia, the main
reasons were that they are too busy, were not aware of the programs, or the programs were held at
inconvenient times.
The responses to the community survey came from a wide range of ethnic categories including
White, Chinese, Korean, Vietnamese, Asian Pacific, Hispanic, and Black. The survey results are a valid
representation of different cultural needs.
When asked what is the one program most needed by your household, the majority of responses
were for youth, teen and senior programs.
All age groups from 5 to 65+ were represented in the responses.
Community Phone Survey
ICG and Research Network Ltd. conducted a community-wide phone survey aimed at
including the opinions, use characteristics, and preferences of a representative cross-
section of the City's residents. The community-wide survey is a critical public planning
tool due to its ability to provide a statistically valid representation of all the households
in Arcadia as a whole rather than only those stakeholders or interested citizens who
choose to participate in outreach tools such as on-line questionnaires or public
workshops. The goal of such a representative survey is to generate unbiased, detailed
and accurate data regarding the true current demand from a statistically valid representation of all households in
Arcadia for recreation facilities and programs specific to the City.
The ability of the community-wide survey to provide a basis of information used to estimate current recreation
needs of the City's residents is the result of the design of a custom survey questionnaire for the City. The subject
areas of this survey were developed through conversations with Staff and the Master Plan Project
Team. Questionnaire topics included selected demography and attitudes regarding recreation, current usage
patterns of community/neighborhood parks and recreation facilities and programs, and desires for service
improvements. Profiles of users and non-users were also developed and specific reasons for non-use explored.
Research Network Ltd. completed 200 questionnaires among a random sample of City resident households
representing all geographic areas of the city, yielding an error margin of ± 7.1% at a 95% confidence level City-
wide.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 23
The scope assumed a questionnaire length of eight minutes with a maximum of five questions containing open
end/other specific opportunities. A total of 85% of completed interviews were completedin English while the
remainder were conducted in Mandarin Chinese. Eighty percent of the interviews were conducted via land-line
telephones and the remaining 20% were conducted via cell.
The following is a summary of the phone survey results. The written summary of the entire findings of the
survey is contained in Appendix B.
More than half (52%) of residents identified web-based sources including
“Internet/Website” and "City Website" as their primary information source.
"Mailed Information" was identified by more than one in ten residents (12%) as
their primary information source.
More than half of residents (56%) chose "Physical Fitness, Health and Well-
Being" as the most important benefit when seeking recreation.
More than eight of every ten Arcadia households (83%) reported having used
recreation facilities in the past year, comparable to the 86% average of other
communities surveyed. Of these recreation facility users, 88% reported most often using facilities
located in the City of Arcadia.
The six facilities most often identified as most often used included (1) Arcadia County Park, (2)
Arcadia Community Center, (3) Santa Anita Golf Course, (4) Santa Anita Race Track, (5) Tierra Verde
Park, and (6) parks outside Arcadia.
When asked from a list of recreation activities (which included Walking/Jogging/Running/Hiking on
Public Trails, Streets or Sidewalks for Recreation or Fitness; Bicycling on Public Trails or Paths for
Golf Activities; Indoor Activities for
Active Recreation or Fitness; Organized Sports Leagues for Youth;
Adults such as Basketball, Volleyball, Badminton, Martial Arts, Fitness, Yoga, Dance, the greatest
participation by residents (in order) included (1)“Walking/Jogging/Running/Hiking on Public Trails,
Streets or Sidewalks for Recreation or Fitness,” (2)“Indoor Activities for Adults,” (3)“Bicycling on
Public Trails or Paths for Active Recreation or Fitness,” (4)“Organized Youth Sports Leagues,” and
(5)“Golf Activities.”
Activities reportedly conducted most often outside the City of Arcadia included (1) “Bicycling” at 24%
of users, (2) “Golf” at 23% of users, (3) “Indoor Activities” at 21% and (4) “Organized Youth Sports”at
20%.
Nearly six in ten Arcadia households (59%) reported using recreation programs, classes or lessons in
the past year, somewhat higher than the 53% average of other communities surveyed. Of these
users, 76% reported using such programs at facilities located within the City of Arcadia.
Three in ten Arcadia households with a member 50 years or older
(30%) reported using senior recreation programs, classes or
lessons. Of these users, 83% reported participating in these
programs at a location within the City of Arcadia.
Eight in ten households polled (80%) with members aged 13 to 17
years stated these teens used teen recreation programs in the past
year. Of these teen program users, 84% reported most often
participating at a location in the City of Arcadia.
More than half of Arcadia households polled (56%) stated they had attended one or more special
events in the City of Arcadia in the past year. Most of these attendees (75%) reported such
attendance more than once during the past year.
Fully 93% of the residents polled stated they are Very or Somewhat Satisfied with existing park and
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 24
recreation programs in the City of Arcadia.
Nearly one-third of City of Arcadia households (32%) identified a preference for Active Recreation
Facilities and Programs while the next largest share of households (28%) preferred Fine Arts or
Performing Arts Facilities and Programs. Remaining households were evenly split between
preference for Classes, Lessons and Community Events or Open Space Preservation and
Enjoyment.
More than three in four (77%) City of Arcadia households identified
a desired recreation facility. One in five (23%) stated they desired
no new recreation facilities. The facilities most often mentioned
were, in aggregate, Swimming Pools (19%), Trails (12%), Fitness
Center (4%), and Gymnasium (4%).
Nearly two-thirds of households polled (64%) identified a desired new recreation program. The
remaining 36% of households stated they desired no new programs. The recreation programs most
often mentioned as desired, included Dance (8%), Fitness (6%), Personal Development (5%), and
Instruction Classes (5%).
Nearly two-thirds of households with teens present (64%) stated they would be somewhat or very
likely to participate in new teen programs if offered in Arcadia.
Eight in ten residents polled (81%) stated they were “Somewhat” or “Very likely” to attend new
community events if offered in Arcadia.
The recreation events most often mentioned as desired included Farmers Market (26%), Concerts
(22%), Cultural/Diversity Events (12%), Fireworks (5%), Seasonal Events (5%), Bike Rides (3%), and
Street Fair (3%).
Senior Citizens Outreach and Surveys
ICG conducted a separate senior citizens survey aimed at getting input
from seniors using the senior center as to the recreation programs and
social services they use at the community/senior center and their
opinions on what they would like in the way of community/senior
center improvements and programs. ICG and staff attended an Arcadia
Travelers meeting to discuss the Recreation and Parks Master Plan and
speak with the seniors about their needs moving forward in the future.
The Senior Citizen Survey was different from the Community Phone
Survey and Web Based Public Survey, in that, it surveyed how seniors use the senior center and what specific
senior services they take advantage of at the center. The Phone Survey and Web/Hard Copy Survey focused on
the entire park system and what facility improvements are needed to serve programs for the entire community.
The Phone Survey and Web/Hard Copy Survey did contain responses from seniors; however, the responses
pertained to how they use all the parks and facilities in the City, not just the senior center facility.
ICG received 161 responses from the seniors group and the following is a summary of their opinions:
88% were aware of all the services available to them at the community/senior center.
The most popular programs and services that the seniors desired included:
o Carefree Café daily senior lunch program
o Tech Talk
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 25
o Special events
o Health and wellness programs
o Support groups
o Reading rooms
o Outdoor plaza/quiet places
o Internet access
o Exercise and fitness classes
o Craft classes
o Dance classes
o Art classes
o Counseling services
o Arcadia travelers
When asked if they would be willing to pay for senior activities, the majority said yes to travel (trips
and tours), fee based hobby and lifestyle classes, dances, and special events at lunch or dinner. A
majority were opposed to paying for personal services, game room space and activities, and health
and wellness programs.
92% responded they did not have any deterrents to participating, 8% responded that they have
physical or health deterrents that keep them from participating.
75% responded they participate in senior activities with their friends or family, while 25% said they
come alone.
Only 12% responded that they volunteer at the community/senior center.
55% said they own and know how to use a computer, while 45% said they did not own a computer.
85% responded they live independently while 15% said they live with family or in an assisted living
facility.
The age of the responders were as follows:
o 50 to 59 4%
o 60 to 69 36%
o 70 to 79 37%
o 80 to 89 16%
o 90 and over 7%
74% of the responders were Caucasian, 21% Chinese, and 5% were other ethnicities. 79% were
female and 21% were male.
All 100% of the responders said they use the Arcadia Community/Senior Center at least weekly.
40% also said they use the Arcadia Public Library.
Leadership Academy Focus Group/Comments
As part of the outreach process for the Recreation and Parks Master Plan, ICG and the Recreation and Community
Services Department made a special presentation to the Arcadia Leadership Academy. After presenting a
PowerPoint outlining the purpose and goals of the Master Plan to the group, an exercise was conducted where
each participant had the chance to provide comments, ideas, and suggestions for future programs and facilities
they thought were needed in Arcadia.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 26
The following is the summary of the comments:
Block parties at neighborhood parks to give neighbors the chance to
meet each other and build a sense of community
Police and other Department “Meet & Greet” activities to make more
people aware of what the City does
Lighted bike paths so people can ride safely at night
City should coordinate a “Grand Bike Tour of Arcadia” event
Walking paths within parks to encourage people to get out and walk
Wi-Fi in the parks to attract people
Volunteer program with youth helping seniors with computer and other electronic devices
Music, Stamp and other programs at the Community Center
Making programs for parents and children at concurrent times
Better publication to residents of City offered programs
Public art in the parks—dedicate space
Provide an “Arcadia Day” to promote programs, maybe at the City Hall Lawn
Improve quality and quantity of programs that attract more diversity
Exercise equipment in the parks (along walking paths or in play areas)
More shade canopies over play structures and picnic areas
Better security lighting in parks
Signage for littering—more trash cans throughout the ity commercial areas
Arcadia Chinese Association Focus Group/Comments
ICG and staff met with the Arcadia Chinese Association in an effort to gain insight
and opinions of Arcadia’s substantial Chinese population with regards to park,
facility, and program needs within the Chinese community. The Arcadia Chinese
Association Board meets monthly at the Chamber of Commerce to coordinate
community activities, discuss community issues, and to plan community events.
Twenty people attended the meeting and all were very excited about the City
undertaking the task of developing a master plan. After the presentation of the Master Plan process and goals,
the group had the following comments:
Participants were all supportive of addressing facility improvements in neighborhood parks
Improve children’s play equipment areas with shade
Improve the amenities at the community center
Request for more lighted walking trails
More programs for teens
The Arcadia Par 3 Golf Course could use improvements
Additional afterschool education programs for youth
Commented how wonderful all the community events the City puts on are for the residents
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 27
Arcadia Sports Groups Focus Group/Comments
The Recreation and Community Services Department holds biannual
meetings with all of the youth and adult organized sports groups in the
City for purposes of allocating field space and coordinating field
improvements and maintenance. ICG, along with staff, attended the fall
2015 allocation meeting and presented the Master Plan process and
goals and received input as to the different needs and suggested
improvements for fields and sports facilities in Arcadia.
Twelve organizations attended representing youth soccer, girls’ softball, baseball, football, basketball, and adult
softball. The following is a summary of their input on what improvements are suggested to the athleticfacilities in
Arcadia.
Restroom/concession improvements or replacement
Improved or additional field lighting
Replacement of natural turf with artificial turf to handle the demand for field space on a year round
basis
Backstop, fencing, dugout improvements
More access to gymnasiums for indoor sports (basketball, volleyball, badminton, table tennis)
New scoreboards
Additional picnic areas
Improved parking lots
Security lighting
Los AngelesCounty Arcadia Regional Park Community Workshop
Los Angeles County conducted a County wide needs assessment process at the same time the City of Arcadia is
preparing its Recreation and Parks Master Plan. The County process is an effort to learn about what park assets
and needs there are in the County. Each City within Los Angeles County is a study area. Each City was expected
to conduct a public workshop to get resident input on the assets and needs within its study area. The results of
the community workshop input into what the priorities should be for the County to include for Arcadia in its
Master Plan were as follows:
Arcadia County Park (Los Angeles County Park)
Lighted walking path
Inclusive playground
Joint use gym
Teen center
Lighted basketball courts (outdoor)
Extreme sports exercise course/climbing wall
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 28
Arcadia City Parks
Bicentennial Park Improvements:
Playground
Shade structure
Bonita Park Improvements:
Baseball field restroom
Baseball field backstop/dugout fencing
Synthetic turf field
Fairview Avenue Park Improvements:
General park infrastructure
Dog park
Playground 5-12 Yr.
Forest Avenue Park Improvements:
General park infrastructure
Open lawn/turf area
Newcastle Park Improvements:
General park infrastructure
Playground
Sand volleyball courts
Pickle ball courts
Tierra Verde Park Improvements:
General park infrastructure
Playground
Restroom
Tripolis Friendship Park Improvements:
General park infrastructure
Playground
These priorities have been passed on to the County, and the City will work with the County in possibly finding
future Los Angeles County funding to implement these recommendations.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 29
PART 4 - FINDINGS, PROJECTED COSTS AND RECOMMENDATIONS
4 A: Summary of Findings and Recommendations
The following is a summary of findings from the community outreach and needs assessment, and
recommendations for each park facility in Arcadia that were developed from the community input process and
demand analysis presented in the next sections. The facility recommendations can also be found in each park
graphic contained in Section 2. The projected total cost (rounded to the nearest thousand) for each facility
recommendation is included in the summary of recommendations and the breakout of projected specific costs are
contained in Appendix D.
The key findings of the Master Plan process regarding what park and facility improvements are needed for the park
system as identified in the community outreach are as follows (not prioritized):
Upgrade existing and provide new children’s play areas
Upgrade or replacement of older park restrooms/concessions
Installation of new lighted walking paths
Replace natural turf with synthetic turf for year round use of sports fields
Replace or upgrade ball field lighting
New dog parks and facilities
Additional shade over play structures
Picnic and barbeque improvements
Americans with Disabilities Act (ADA) compliant access improvements
New teen facilities and programs
New facilities for community events
Upgrade of landscape areas with drought tolerant plant materials
Enhanced Watershed Management Plan (EWMP) state regulations compliant
Consistent park structures theme to identify City of Arcadia parks (new enhanced paving, brick
pilasters and park signage)
Improvements for sports fields such as new bleachers, dugouts, batting cages, team benches and
fencing
Parking lot upgrades and improvements
Each park site has been inventoried and analyzed as to the specific improvements needed at each location to
address the findings above. The following is the list of individual park improvements recommended from public
input for each site along with a summary of projected costs. The breakdown of projected costs for each park site is
contained in Appendix D.
4 B: 4 Tier List of Recommendations
The total projected cost to implement the recommended park and facility improvements is $51,398,077.
Obviously, the City does not have the financial resources or administrative capacity to implement all the
recommendations at once. The Master Plan is designed to allow the City to construct the park and facility
recommendations in phases over a period of years.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 30
Consequently, the recommendations have been divided into four tiers depending on their degree of need.
Tier 1 Recommendations are the greatest current need projects for existing program operation, or replacement,
or for safety reasons that the City will want to concentrate funding efforts on and try to implement as soon as
possible.
Tier 2 Recommendations are the next level of need and are projects the City can allocate resources to as Tier 1
projects are completed and funding becomes available.
Tier 3 Recommendations are needed for program expansion or will be needed in the future as current facilities
age and should be considered for future projects when Tier 1 and 2 recommendations are completed, or the City
is able to find a dedicated funding source, such as a specific grant, or community partner who wishes to provide
funding for the specific project.
Tier 4 Recommendations are desired improvements, but not critical in the near future and will be addressed over
time as higher tier recommendations are completed and future funding becomes available.
Staff will use this list each year during the City’s budget process to update its Capital Improvement Program (CIP)
for park and facility improvements.
There are several funding sources available to the City for implementing the
recommendations, including park impact fees, state and federal grant
programs, private foundation grants, enterprise funds, community
sponsorships, joint-funding agreements and general fund. Some funding
sources can only be used for certain types of improvements. For example,
Trail Grants can only be used for development and installing trails within the
park system. While City staff will generally prioritize annual budgets based
on Tier 1 recommendations, Tier 2, 3, or 4 recommendations may get funded ahead of Tier 1 recommendations if
specific grants or joint funding opportunities present themselves. The Tier List of Recommendations is meant to
be used as a guide by staff during the annual budget allocation process as a way to address the most important
priorities identified by the public outreach and needs analysis.
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 31
4B.1: City of Arcadia – Community/Senior Center
The Community/Senior Center is the City’s most used facility as most of the youth, adult, and senior classes,
activities and programs take place there. The recommendations for improvements address current program
needs as well as future needs to keep the Community/Senior Center up to date and functioning efficiently.
Tier 1 Tier 2 Tier 3Tier 4
Kitchen Equipment (Replace LED walkway Parking lotFlooring/carpet,
warming ovens and install lighting improvements, upgraded lobby
walk-in refrigerator/ freezer, fencing, pilasters, and furniture, new chairs,
dishwasher and ice maker), audio visual upgrades new tables, and solar
and drought tolerant panels
landscaping
$270,750 $20,000$1,394,200 $713,427
Total Projected Cost $2,398,377
4B.2: City of Arcadia - Recreation and Community Services Administrative Building
The Recreation and Community Services building houses the administration functions for the Recreation and
Community Services Department and hosts public class and activity registration, meetings, and training
functions. Recommendations address future needs for efficiency and operational capacity.
Tier 1Tier 2 Tier 3Tier 4
Bike rack Benches and trash LED lights within Back parking lot
receptacles facility, sola-tube improvements and work
fixtures room/break room
addition
$1,500$23,000 $47,000 $301,675
Total Projected Cost $373,175
4B.3: City of Arcadia -Bicentennial Park
Bicentennial Park is a mini park containing two children’s play areas and two very popular tennis courts, in
addition to family picnic facilities. Recommendations address enhancing the park’s appearance and
operational efficiency.
Tier 1 Tier 2 Tier 3 Tier 4
Resurface tennis Replace the wood rail fencing with aluminum picket fence,
courts new LED walkway lighting, add ADA compliant drinking
fountain, install enhanced paving in plaza areas, new park
identification sign, new park benches and bike racks, add
new LED tennis court lights, replacement of children’s play
equipment, and new picnic facilities
$17,000 $738,712
Total Projected Cost $755,712
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 32
4B.4: City of Arcadia -Bonita Park
Bonita Park is a specialty facility for residents as it contains a sports field, a skate park, and children’s play
equipment. Recommendations address improving the park’s appearance, upgrading the sports field to
improve play and decrease maintenance costs, and to capture runoff on site.
Tier 1 Tier 2 Tier 3 Tier 4
Bleachers Baseball LED walkway lighting, install an ADA compliant Resurface skate
with shade, backstop, drinking fountain, new park identification sign, park
dugouts dugouts, install new park bench and bike rack, install new LED
with shade enhanced paving sports field lighting, new 10’ high fencing with 30’
in plaza areas, high netting at the baseball diamond, new
scoreboard, and pitcher’s warm-up bullpen, new storage bin, add
replace new batting cages, replace children’s play
restroom/ equipment w/ADA surfacing, new picnic and
concession
barbeque amenities, replace landscape planter
beds with drought tolerant plant materials and
natural turf areas with no water synthetic turf,
add new flag pole, install a retention basin, and
add soccer field striping to outfield.
$79,500 $509,573 $3,879,468 $65,838
Total Projected Cost $4,534,379
4B.5: City of Arcadia -Camino Grove Park
Camino Grove Park is a joint use facility with the Arcadia Unified School District. The facility has sports fields,
tennis courts, basketball courts, handball courts, and two large tot lots. Recommendations address short
term and long term needs to upgrade play equipment. A joint use project would be necessary to upgrade
the sports amenities to increase playability, safety and operational efficiency.
Tier 1 Tier 2 Tier 3 Tier 4
Resurface Enhanced paving in plaza areas, Install an ADA compliant New 10’ high
tennis courts replace tot lot children’s play drinking fountain, enhanced fencing with 30’
equipment, ADA surfacing, new paving in plaza areas, a new high netting on
steel shade structure, picnic park identification sign, park softball field, new
tables, ADA drinking fountain,benches and bike rack, new players dugout
new barbeque and picnic
LED tennis court lighting, with bench, and
amenities, new park new LED basketball lights, new bleachers
identification, LED walkway landscape planter beds with with shade, LED
lighting, landscape planter beds drought tolerant plant walkway, new
with drought tolerant plant materials, install infiltration picnic amenities,
materials, install infiltration basin to capture runoff, new new score board
access gate and parking lot and new flag pole
basin to capture runoff,and new
enhancements
access gate
$17,000 $376,226 $1,218,997$192,290
Total Projected Cost $1,804,513
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 33
4B.6a:CityofArcadiaCivicCenterSoccerFieldandParkingLot
RecommendedimprovementsforCivicCenterSoccerFieldaredesignedtoimprovethesoccerfield.
Tier1Tier2Tier3Tier4
CivicCentersoccerfieldimprovements,
syntheticturffieldreplacementwith
naturalinfillandBrockshockpad,andadd
paverstoparkinglot
$2,033,751
TotalProjectedCost$2,033,751
4B.6b:CityofArcadiaCityHallLawn
RecommendedimprovementsforCityHallLawnaredesignedtoenhancethespecialeventsthattakeplace
andbeautifythepublicspace.ThesiteplanencompassesthefutureplannedexpansionoftheCityHall
facility.
Tier1Tier2Tier3Tier4
ConcretepadInstallstageLEDwalkwaylighting,ADAcompliant
withelectrical(plazaareas,ЋЍͼseatdrinkingfountain,handicapaccessramp,
conduitwall,concreteriser)newflagpole,bikerack,trash/recycle
receptacles,parkbenchandarborshade
structure
$15,000$85,350$202,400
TotalProjectedCost$302,750
4B.7a:CityofArcadiaEisenhowerMemorialPark
Therecommendationsforthisneighborhoodparkwillenhancethecommunityandservelocalresidents.
Theimprovementswilladdresstheneighborhoodamenities,sportsuses,andcommunitydogpark.Because
ofthemultipleusesofthepark,andcurrentconditions,itisrecommendedthattheentireparkbeimproved
inonephase.
Tier1Tier2Tier3Tier4
InstallanБhighpropertylinewalltoprotectadjacent
residents,newLEDparksecuritylightpole,ADA
compliantdrinkingfountain,parkbench,newЏhigh
aluminumfencing,LEDsportsfieldlighting,
installationofanewParCoursestation,addЊЉhigh
chainlinkfencingatthebaseballfield,replacenatural
turfareaswithsyntheticturf,newbattingcages,new
bleachers,storagebin,newrestroom/concession
facility,newbarbequeandpicnicfacilities,replacethe
ĭŷźƌķƩĻƓƭplayequipment,andaddaperimeter
walkingtrailaroundfacilityandparcoursestations
$5,911,076
TotalProjectedCost$5,911,076
EXECUTIVESUMMARY&NEEDSANALYSISΑCityofArcadiaRecreation&ParksMasterPlan34
4B.7 b: City of Arcadia - Eisenhower Memorial Park Dog Park
The community outreach showed a high demand for improvements to the Dog Park and because it is
adjacent to the very popular sports and neighborhood facilities that are recommended to be done in one
phase, it is recommended that all of the Dog Park improvements be done in one phase also.
Tier 1 Tier 2 Tier 3 Tier 4
Install new surface material, fencing, lighting,
a new doggie drinking fountain, new dog
transition gate with new fencing, and add a
pedestrian bridge over the flood control
channel
$1,053,562
Total Projected Cost $1,053,562
4B.8: City of Arcadia -Fairview Avenue Park
Fairview Avenue Park improvement recommendations address beautifying the park with new landscaping,
adding new children’s play equipment, and new Dog Park amenities.
Tier 1 Tier 2 Tier 3 Tier 4
Landscape planter beds with drought tolerant
plant materials and subsurface irrigation, park
benches, barbeque and picnic amenities, shade
structures, LED walkway lighting, enhanced
paving, new play equipment, and an ADA
compliant drinking fountain. The Dog Park
recommendations include adding a 4’ doggie
gate, new doggie drinking fountain, dog bag
dispensers, adding decomposed granite
surface, 6’ high doggie gate, perimeter fencing,
and an infiltration swale
$1,137,433
Total Projected Cost $1,137,433
4B.9: City of Arcadia -Forest Avenue Park
Forest Avenue Park is a mini park and recommendations address making maintenance more efficient and
providing barbeque and picnic amenities.
Tier 1Tier 2 Tier 3Tier 4
Add landscape planter beds with drought tolerant
plant materials and subsurface irrigation, ADA
compliant drinking fountain, enhanced paving in
plaza areas, a new park identification sign, new
park bench and bike rack, new trash/recycle
receptacles, new barbeque unit, new barbeque
ash receptacle, new picnic table, and new 8’ high
aluminum fencing
$300,990
Total Projected Cost $300,990
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 35
4B.10: City of Arcadia -Hugo Reid Park
Recommendations for Hugo Reid Park address the need for park upgrades, baseball field and tennis court
improvements. Upgrading the sports field lighting and restroom/concession is a priority. This is a joint use
facility with the Arcadia Unified School District. When implementing new playground equipment, school
district personnel should be notified to collaborate on this project.
Tier 1 Tier 2Tier 3 Tier 4
Bleachers with Sports field lights, Play equipment, new park signage, an 8’ high
shade, dugouts upgrade of restroom and aluminum entry gate, barbeque unit,
with shade, concession, barbeque ash receptacle, picnic shade
resurface tennis new scoreboard, new 10’ shelter, picnic table, trash/recycled
courts high chain link fence receptacles, new flagpole, enhanced paving,
with 30’ high netting, a handicap curb ramp, park bench, ADA
new batting cage tunnel, compliant drinking fountain, new Par Course
and team benches station, install pervious pavers in the parking
lot, new parking lot lights, 8’ property line
wall, new tennis court lights, and new tennis
court gate entrance
$96,500 $932,300 $2,744,255
Total Projected Cost $3,773,055
4B.11: City of Arcadia -Longden Avenue Park
Longden Avenue Park is a baseball facility. There is a need for field lights and replacement of
restroom/concession. Future recommendations address improving playability, access, operational efficiency,
and spectator comfort.
Tier 1 Tier 2Tier 3 Tier 4
Bleachers with New sports field New 8’ high aluminum fence, Synthetic turf (organic)
shade, dugouts lights, replace the install 8’ high aluminum vehicular w/shock pad, pervious
with shade restroom and gate, 8’ high aluminum pavers in parking stalls,
concession, new pedestrian gate, picnic table, create a driveway
scoreboard enhanced paving, 10’ high chain apron, new park
link fence with 30’ high netting, signage, and ADA curb
new pitcher’s bull-pen, new ramp
parking lot lights, new park
bench, batting cage, storage bin,
ADA compliant drinking fountain,
and new flagpole
$98,000 $405,325$1,331,287 $1,475,799
Total Projected Cost $3,310,411
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 36
4B.12: City of Arcadia -Newcastle Park
Recommendations for Newcastle Park address the growing need for pickle ball courts, improvements for the
tennis courts and sand volleyball facilities, and upgrades to the neighborhood park amenities. Because of
the growing demand and extreme popularity, it is recommended that all the improvements be done in one
phase.
Tier 1 Tier 2 Tier 3 Tier 4
6 new pickle ball courts, a new Par Course
station, new children’s play equipment,
new lighted sand volleyball courts with
bleachers, new concrete walkway,
barbeque and picnic amenities, LED
walkway lighting, shade structure,
resurface tennis courts, new tennis court
fencing, tennis court lighting, and tennis
court gates, parking lot improvements,
installation of an 8’ split face block wall
between the adjacent residents and the
park, and a new restroom/storage facility
$3,023,860
Total Projected Cost $3,023,860
4B.13 City of Arcadia - Orange Grove Park
Orange Grove Park is a neighborhood park/tennis facility. The tennis facility sits upon a City water tank and
pumping station. Recommendations address upgrading the tennis facility, creating a perimeter
walking/exercise track and par course stations, improving the water tank maintenance access, and providing
new restrooms.
Tier 1 Tier 2 Tier 3Tier 4
Resurface tennis New restroom, tennis Add landscape planter beds with drought
courts court lights, replace tolerant plant materials and subsurface
tennis court fence irrigation, new vehicular access gate, new
and gate park sign, enhanced paving, new parking lot
curbs, a new 8’ high split face boundary wall
with 8’ brick pilasters, new bleachers, LED
walkway lighting, a Par Course exercise
station, create a perimeter walking/exercise
track, ADA compliant drinking fountain,
pedestrian access gate, and parking lot
improvements
$35,000$740,192 $1,283,164
Total Projected Cost $2,058,356
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 37
4B.14: City of Arcadia -Par 3 Golf Course
The Arcadia Par 3 Golf Course is a specialty park managed by the City’s contractor. Section 2 contains the
site plans and recommendations for the entire site, some of which will be implemented by the City and
some by the contractor.
Tier 1Tier 2 Tier 3 Tier 4
Additional shade Replace landscape planter beds with drought tolerant
for driving range plant materials and subsurface irrigation, a new park
sign, a new 8’ high split face boundary wall with 8’ brick
pilasters, parking lot improvements, new 8’ high
vehicular access gate, new flagpole, bicycle route kiosk,
bike racks, ADA compliant drinking fountain, and a new
art feature. Golf course improvements include
remodeling and expanding the clubhouse, new tables
and chairs, solar panel shade structures, and a new two-
story driving range with lights
$75,000 $10,640,081
Total Projected Cost $10,715,081
4B.15: City of Arcadia -Tierra Verde Park
Tierra Verde Park is a popular neighborhood park and recommendations address the need for replacing and
improving park amenities, capturing water run off, and improving park appearance.
Tier 1 Tier 2Tier 3 Tier 4
Resurface New picnic tables on concrete slab, Replace tennis court
tennis courts new LED walkway lighting, enhanced lighting, and add a new
paving, new shade structure, park restroom facility
bench, bike rack, trash/recycle
receptacle, ADA compliant drinking
fountain, park bench, and new
children’s play equipment
$17,000 $1,618,995 $155,140
Total Projected Cost $1,791,135
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 38
4B.16: City of Arcadia -Tripolis Friendship Park
Tripolis Friendship Park is a mini park catering to children and family play. Recommendations address
improving park amenities, appearance and maintenance efficiency.
Tier 1Tier 2 Tier 3Tier 4
Install ADA compliant drinking fountain, enhanced
paving in plaza areas, new park identification sign,
park bench, bike rack, trash/recycle receptacles,
new 4’ high aluminum fencing, barbeque and picnic
amenities, new steel shade structure, landscape
planter beds with drought tolerant plant materials
and subsurface irrigation, an infiltration basin, and
replace children’s play equipment
$634,322
Total Projected Cost $634,322
4B.17: City of Arcadia -Wilderness Park
Wilderness Park is a classified as a community park and the recommendations for improvements address
the need to improve and add nature trails and nature enrichment amenities that enhance the wilderness
experience and make operations more efficient.
Tier 1Tier 2 Tier 3 Tier 4
Construct new water barrier, Resurface asphalt parking lot, Upgrade nature Install 8’ high
upgrade trail system to 6’ additional picnic tables, center and aluminum
wide with river rock lining, upgrade trash enclosure, concession/storage fencing with 8’
install a river rock infiltration vehicular barrier gate, upgrade facility and shade high river rock
basin, add pressure treated the archery range, improve fire structure pilasters and
wood fencing, upgrade access road, add vehicular native
concrete steps with 18” high barrier posts, new barbeque landscaping
rock wall retaining walls, units, barbeque ash receptacle
ADA handicap ramp, units, upgrade tot lot
enhanced paving, upgrade equipment, upgrade concrete
fire pit ring with metal amphitheater, replace flag pole,
screen, providing interactive bike racks
trail signage
$432,440 $3,263,485 $1,470,600 $484,134
Total Projected Cost $5,650,659
EXECUTIVE SUMMARY & NEEDS ANALYSIS – City of Arcadia Recreation & Parks Master Plan 39
4B.18:LosAngelesCountyArcadiaRegionalPark(NotCityOwnedorOperated)
Thecommunityinputprocessandneedsassessmentindicatethedesiredimprovementsthatwouldbest
benefittheusersoftheCountyRegionalParkinArcadiaincludeanewgymnasium/teencenterwitharock
climbingarea,newoutdoorlightedbasketballcourts,inclusiveplaygroundequipment,andnewlighted
walkingtrails.TheCountyRegionalParkistheonlyparkspaceinArcadiathathastheroomforthese
improvementswhichwillservebothArcadiaresidentsandLosAngelesCountyresidentswithinthe
surroundingareasofArcadia.
Tier1Tier2Tier3Tier4
NewlightedwalkingNewgymnasium/teencenterwitharock
trailclimbingareaandADAplayground,newlighted
basketballcourtcomplex,andinclusivetotlot
playgroundequipment
$350,000$8,715,618
TotalProjectedCost$9,065,618
4C:CostSummaryofTierRecommendations
CITYOFARCADIAPARKSTIER1TIER2TIER3TIER4Totals
Community/SeniorCenter$270,750$20,000$1,394,200$713,427$2,398,377
Recreation/CommunityServices$1,500$23,000$47,000$301,675$373,175
Building
BicentennialPark$17,000$738,712$755,712
BonitaPark$79,500$509,573$3,879,468$65,838$4,534,379
CaminoGrovePark$17,000$376,226$1,218,997$192,290$1,804,513
CivicCenterAthleticFieldand$2,033,751$2,033,751
ParkingLot
CityHallLawn$15,000$85,350$202,400$302,750
EisenhowerMemorialPark$5,911,075$6,183,051
EisenhowerMemorialDogPark$1,053,562$1,053,562
FairviewAvenuePark$1,137,433$1,137,433
ForestAvenuePark$300,990$300,990
HugoReidPark$96,500$932,300$2,744,255$3,773,055
LongdenAvenuePark$98,000$405,325$1,331,287$1,475,799$3,310,411
NewcastlePark$3,023,860$3,023,860
OrangeGrovePark$35,000$740,192$1,283,164$2,058,356
Par3GolfCourse$75,000$10,640,081$10,715,081
TierraVerdePark$17,000$1,618,995$155,1401,791,135
TripolisFriendshipPark$634,322$634,322
WildernessPark$432,440$3,263,485$1,470,600$484,134$5,650,659
TOTALARCADIAPARKS$10,014,626$9,308,141$12,103,016$20,136,814$51,562,597
LOSANGELESCOUNTYREGIONALPARK
TIER1TIER2TIER3TIER4Totals
ArcadiaRegionalPark$350,000$8,715,618$9,065,618
TOTALCOUNTYREGIONALPARK$350,000$8,715,618$9,065,618
EXECUTIVESUMMARY&NEEDSANALYSISΑCityofArcadiaRecreation&ParksMasterPlan40
Appendix A
Program Inventory
Evaluation & Fee Comparison
Title IX & AB 2404 Compliance
Program Inventory
Evaluation & Fee Comparison
Title IX & AB 2404 Compliance
1PROGRAMINVENTORYCOMPARISON
The Recreation and Community Services Department offers a variety of programs which benefit the
Arcadia community. This report addresses the recreation program inventory and evaluates Arcadia
program offerings as compared to programs offered by surrounding cities to gauge the level of
programs and activities in Arcadia and identify any gaps in programming that would cause Arcadia
residents to seek services outside the City.
The following table provides an inventory of recreation programs and core services offered by Arcadia as
compared to San Marino, South Pasadena, San Gabriel, and Duarte. These cities were chosen for
comparison based on feedback from the community outreach surveys pertaining to where Arcadia
residents said they participated in recreation programs outside Arcadia.
There can be several reasons Arcadia residents attend recreation programs and activities in cities
outside Arcadia, including more convenient location, participating with friends and family, programs or
times not available in Arcadia, or lower program costs in other cities. To analyze if program offerings is a
factor, the report provides an analysis between Arcadia and the selected cities and compares Arcadia’s
program and activity inventory to their program offerings.
Programs or activities designated with an asterisk (*) are provided by an outside agency or community
partner.
San
Activity Arcadia San Marino South Pasadena Gabriel Duarte
Preschool Programs
Tiny Tots/Toddlers Pre-School Yes (*) Yes Yes Yes No
Parent/Child Classes YesYes Yes Yes No
Tiny Tot Ballet YesYes Yes Yes No
Tiny Tot Soccer YesYes Yes Yes No
Tiny Tot Karate YesYes (*) Yes (*) Yes No
Tiny Tot/Toddler Swim LessonsYesYes Yes Yes Yes
Kids Music & Motion YesYes Yes Yes No
San
Activity Arcadia San Marino South Pasadena Gabriel Duarte
Piano for Preschoolers YesYes Yes Yes No
Tiny Tot Gymnastics YesYes Yes (*) Yes Yes
Pee Wee Tennis YesYes Yes (*) Yes No
Youth/Teen Programs
Youth SwimYes(*)Yes (*)Yes (*)Yes (*)Yes
Outdoor Adventure Programs YesNo No No No
Outdoor Youth Sports Leagues YesNo Yes Yes Yes
Free Afterschool Programs YesNo No No Yes
Indoor Youth Sports YesNo (*) No (*) Yes Yes
Kids Night Out YesNo Yes Yes Yes
Arts & Crafts Classes YesYes Yes Yes Yes
1
Teen Camps YesYes Yes No No
Music ClassesYesYes Yes YesYes
Youth Special Events YesYes Yes YesYes
Summer Day CampsYesYes Yes YesYes
Teen Programs YesNo Yes No Yes
Junior Golf YesNo Yes No Yes
Computer Classes YesYes Yes YesYes
Youth TennisYesYesYesYesYes
Youth Baton/Cheer YesYes Yes YesYes
Youth Cooking Classes YesYes Yes YesYes
Youth Gymnastics YesYes Yes YesYes
Year-Round Extended Day CareNo Yes No No No
Summer Extended Day Care YesYes Yes No Yes
Adult Programs
Adult Basketball YesNo No No No
Adult Softball Yes(*) No No No Yes
Adult Indoor SportsYesNo No No No
Wilderness Park Adventures YesNo No No No
Fitness Classes YesYes Yes YesYes
Adult Ballroom Dance YesYes Yes YesYes
Adult Zumba YesYes Yes YesYes
Adult Yoga YesYes Yes YesYes
Adult Special Interest ClassesYesYes Yes YesYes
Adult Music Classes YesYes Yes YesYes
Dog Obedience YesYes Yes YesYes
Adult Computer Classes YesNo Yes YesYes
Family EventsYesYes Yes YesYes
Life Long Learning/Career Classes YesNo Yes YesYes
Adult Tennis YesYes Yes YesYes
Adult Golf YesNo Yes No Yes
Health Support Services YesNo Yes No No
Social Programs YesYes Yes No No
Performing Arts Theater Yes (*) Yes (*) Yes (*) Yes (*) Yes (*)
Performing Arts Classes/Excursions YesYes Yes YesYes
Senior Programs
Senior Health ServicesYesNo Yes YesYes
Senior Exercise YesNo Yes YesYes
Senior Fitness Activities YesNo Yes YesYes
Senior Line Dance YesYes Yes YesYes
San
Activity Arcadia San Marino South Pasadena GabrielDuarte
Senior Tai-Chi YesYes Yes YesYes
Senior Arts & Crafts YesNo Yes YesYes
Social Programs YesNo Yes YesYes
Lunch Program YesYes Yes YesYes
Senior Expo YesYes Yes YesYes
Tax HelpYesYes Yes YesYes
Special EventsYesYes Yes YesYes
Travel Activities YesYes Yes YesYes
Holiday Events YesYes Yes YesYes
2
San
Facilities Arcadia San Marino South Pasadena GabrielDuarte
Community Center YesYes No YesYes
Senior Center YesNo Yes No Yes
Teen Center No No Yes No Yes
Lighted Ball FieldsYesNo Yes YesYes
Neighborhood Parks YesNo Yes YesYes
Children’s Play Areas YesNo Yes YesYes
Municipal Pool No No No No Yes
Wilderness ParkYesNo No No No
Gymnasium YesNo No No No
Amphitheater No No Yes YesNo
Fitness Center No No No No Yes
The comparison analysis shows Arcadia programs and services exceed the offerings in surrounding cities,
thus lack of program offerings does not appear to be a reason Arcadia residents would participate in
programs outside Arcadia. Program offerings in Arcadia and recreation facilities available for
programming appear to be equally distributed between age groups and highly comparable to the types
of programs and facilities offered in surrounding cities. During the community outreach, people were
very complimentary of the programs in Arcadia and indicated a high degree of satisfaction with both
quantity and quality of programs. No new program offerings were suggested, as there are no gaps in
programming offered.
2PROGRAMFEECOMPARISON
One of the factors to consider for establishing fees is “Market Rate.” It is important to know what
surrounding cities are charging for similar programs to make sure Arcadia fees are consistent with the
market. If Arcadia sets its fees too high then Arcadia residents will seek recreation activities in
surrounding cities and not in Arcadia; consequently, if fees are too low then residents in other cities will
fill the lower priced classes and activities in Arcadia, thus impacting opportunities for Arcadia residents.
The following comparison chart shows what the surrounding cities of San Marino, South Pasadena, San
Gabriel, and Duarte are charging for similar programs.
SAMPLE FEE COMPARISONS (fees adjusted to compare equal number of weeks)
San
Activity Arcadia San Marino South Pasadena GabrielDuarte
Swim LessonsNA$50 NA $35$30
Adult Basketball League$500 NA NA NA $530**
Intramural Youth Sports $38 $42 $40 $35$30
Group Picnic Shelter RentalNANA $55/$65* $50/$75*$50/$75*
Youth Day Camps (1 Week) $125 $107$148 $110 $160
Teen Nights $20 NA $10 NA $5
Synthetic Turf Field Rental$28.90 Hr. NA NA NA $30 Hr.
Large Banquet Room (6 Hrs.) $550 Avg.$575 Avg. $600 Avg. $450 Avg. $400 Avg.
Tiny Tot Ballet (8 weeks)$69 $106$95 $69$30
Tiny Tot Soccer (8 weeks)$98 $106$82 $95NA
Tiny Tot Karate (11 weeks) $189 $164$60 $66$76
Youth Baton/Cheer (10 weeks) $72 $93 NA $52$46
Youth Cooking Classes (5 weeks) $52 $138$100 NA $40
Youth Gymnastics (5 weeks)$50 $80 $110 $127 $35
3
Youth Tennis (4 weeks)$75 $132$50 $109 $58
Adult Ballroom Dance (8 weeks) $58 $70 $96 $54$40
Adult Zumba (10 weeks) $62 $65 $52 $73NA
Adult Yoga (10 weeks) $70 $47 $80 $67$50
Senior Exercise (11 weeks)$35 $40 $58 $53$20
Senior Line Dance (10 weeks)$44 $52 $50 $45$40
Senior Tai-Chi (8 weeks) $52 $47 $30 NA $40
Dog Obedience$62$106NANANA
* Non-resident fee
** Compared to adult softball, as no adult basketball leagues are available
It appears that the fees Arcadia charges for sample programs are fairly consistent with what surrounding
cities charge for similar programs. Day camps, tot classes, youth classes, adult and senior activities are
within the range that does not incentivize Arcadia residents to seek programs outside the City, nor non-
Arcadia residents to prefer Arcadia to their own city because of costs. Some of the large differences in
tennis program fees are contributed to class size and court availability. The large difference in tiny tot
karate is attributed to Arcadia and San Marino’s program being offered through a commercial
establishment, while the other cities operate the classes within their recreation center. The same is true
of youth cooking classes in San Marino and South Pasadena, where they are offered in a commercial
business.
Arcadia can probably expect to get a higher percentage of non-residents in its dog obedience classes, as
most other cities do not offer them and the fee in San Marino is substantially higher than Arcadia.
As part of the scope of services for the Master Plan, the City requested ICG to do a comparison of the
rental rate for the Museum Education Center in Arcadia to see if it is within market rates for other like
facilities in the San Gabriel Valley and throughout Southern California in cities with like economic and
cultural demographics. The Museum Education Center contains restrooms, a refrigerator, stove, round
tables, rectangular tables, chairs, a projector and a wall divider to separate the room into two rooms.
A search for comparable facilities yielded the following data showing a rental fee comparison based on
the rental rate for “Non-Commercial Resident and Community Group” rentals. The facilities chosen for
comparison have similar amenities and capacity. They include cities surrounding Arcadia and cities in
Southern California with similar economic and cultural demographics.
MARKET RENTAL RATE COMPARISON MUSEUM EDUCATION CENTER
Rental Rate
Assembly (All require 2 Hr. Min.)
City Facility Capacity Non-Commercial Resident
and Community GroupRate
Arcadia Museum Education Center142 $25 Hr.
Arcadia Community Center Activity Room50$30 Hr.
San Marino Fireside Room 112 $50 Hr.
San Gabriel North Room 100 $45 Hr.
South Pasadena Library Community Room 130 $60 Hr.
Duarte Royal Oaks Room125 $60 Hr.
Rosemead Rosemead Center Room 115 $50 Hr.
ClaremontPadua Room 105 $75 Hr.
Irvine Deerfield Room 135 $75 Hr.
Orange Grijalva Activity Center 90$40 Hr.
Newport Beach Newport Ridge Activity Room 150 $79 Hr.
4
3ESTABLISHINGFEES
The Department’s goal in pricing programs, services, and facilities is to set prices in a manner that
balances user fees with taxpayer investment. Pricing takes into consideration the following:
Program benefit to the City’s residents
The financial ability of the City to support the program or special activity with public funds
Users’ ability to pay
The Department also recognizes not all programs and facilities are the same, there is no “one fee fits all,”
but if possible, a full or partial cost recovery model will be utilized when establishing fees.
Each year, the department will evaluate the programs, services and fees and determine if adjustments
are necessary. The City of Arcadia typically does this with all departments on an annual basis. Each fee
and/or adjustment is justified and approved by the City Council.
4TITLEIXANDAB2404REVIEWANDANALYSIS
The following provides a review and analysis of the 1972 Title IX Federal Anti-Discrimination Law and
State of California Assembly Bill AB 2404. Assembly Bill 2404 pertains to gender discrimination in sports
programs and is specifically aimed at ensuring girls and women have equal access to sports and
recreation facilities and programs under the direct operation or control of city, county, and state
agencies. It requires that girls be accorded “opportunities for participation in community youth athletic
programs equal, both in quality and scope, to those accorded to boys.”
The “Coaching Corps and Fair Play for Girls in Sports Association,” a project of the Legal Aid Society-
Employment Law Center, has developed the following implementation guidelines for recreation and
parks departments to follow in order to comply with Title IX and AB 2404. They recommend that:
a)Departments should keep records of gender participation in sports programs operated both
directly by the department and by sports organizations the department allocates fields and
sports facilities space to.
b)Departments should use the collected participation data when determining allocation of fields
and facilities to ensure girls’ sports programs have equal access to safe and well maintained
fields (to ensure boys’ programs do not have better fields to play on than girls programs); equal
access to storage units for equipment; equal practice times at facilities; equal support amenities,
such as scoreboards, dugouts, batting cages, bleachers, restrooms, locker rooms, etc.
c)Departments operating direct sports programs should ensure girls’ sports programs have equally
trained and qualified coaches and officials as those of boys’ programs and are assigned to
programs in an equal manner.
d)Departments should ensure that facility development and improvements are gender neutral and
afford equal gender access.
e) Departments should ensure that girls’ sports programs have equal access to advertising for
participants, i.e. in recreation brochures, City websites, distribution of flyers, posting of banners,
etc.
f)Departments should develop policy and criteria for regularly notifying youth athletic
organizations and involved personnel that they cannot discriminate on the basis of gender in the
programs and activities they operate.
5
In addition to the above operational guidelines both Title IX and AB 2404 require the City to have in
place a “Gender Equity Grievance Procedure,” to publish a “Title IX-AB 2404 Grievance Form,” and to
appoint a staff member as a “Title IX-AB 2404 Coordinator.”
In reviewing the Recreation and Community Services Department’s operations as it pertains to
compliance with Title IX and AB 2404, the Master Plan study found that the Department does do a good
job of notifying youth athletic organizations and involved personnel that they cannot discriminate on the
basis of gender in the programs and activities they operate. The Department conducts regularly
scheduled meetings with all the sports organizations it allocates field space and facilities to and at these
meetings City staff informs the groups of the anti-discrimination laws. Staff is also diligent in making
sure athletic field allocations and facility allocations do not result in any unequal access for girls’ sports
programs.
The design of all park and facility improvements in the Master Plan has been developed to ensure equal
gender access.
It is the policy of the Recreation and Community Services Department to achieve gender equity in youth
sports programs that are operated on City-owned land and within City facilities. It is the Department’s
goal that all youth may aspire to and have the opportunity to participate in City sports programs that
meet their interests and capabilities.
As part of the Recreation and Parks Master Plan process, the Department will implement a “Title IX-AB
2404 Notification Procedure Policy,” as shown in Exhibit 1; the “Gender Equity Grievance Procedures,”
as shown in Exhibit 2; and the “Title IX-AB 2404 Grievance Form,” as shown in Exhibit 3. Finally, the
Department will appoint a staff member as the “Title IX-AB 2404 Coordinator” for the Department and
make sure that person understands the Department’s Gender Equity Plan and their responsibility for
communicating it to youth sports groups and in processing a gender or sexual harassment complaint.
By implementing the guidelines and policies outlined above, the Department can ensure that it is in
compliance with both Title IX and AB 2404.
6
Exhibit 1 – City of Arcadia
“Title IX – AB 2404 Notification Procedure Policy”
PURPOSE: Policy and criteria for regularly notifying youth athletic organizations, employees and
involved personnel that they cannot discriminate on the basis of gender in the activities or programs
they operate
In an effort to regularly communicate to employees, volunteers and sports organization personnel the
importance of non-discrimination practices on the basis of gender regarding youth athletic and
recreational programming, the following measures shall be implemented:
1.The Department will provide the appropriate annual training for Recreation and
Community Services Department staff, contractors, and Youth Sports Community
Organization Volunteers to attend for information and compliance regarding federal and
state anti-discrimination law as it relates to youth athletic and recreational programming.
2.In the event that the representative who received training chooses to resign or is no
longer part of the organization, such organization would need to send a new
representative to complete the anti-discrimination training. Failure to do so would place
the organization in non-compliance position with City regulations.
Non-compliance will be defined as: Failure to maintain at least one active representative
that is currently trained (by the City) to prevent discrimination in youth athletics. Any
league that falls into non-compliance regarding this issue will suffer suspension of field
access rights, as granted under the Facility Use Agreement between the City and Said
Organization/League.
7
Exhibit 2 – City of Arcadia
“Gender Equity Grievance Procedures”
PURPOSE: Resolving youth athletic complaints alleging discrimination on the basis of gender
The City will maintain gender equitable opportunities for youth who participate in sports programs. In
the event that an inequitable situation is discovered or believed to be happening, the City provides four
methods to file a grievance regarding discrimination of youth athletes or youth athletic program on the
basis of sex, sexual orientation, race, nationality, ethnic origin, color, religion or disability.
1.Contact the City’s Title IX–AB 2404 Anti-Discrimination Coordinator (Ryan Wright) at
626.821.4398, and communicate any concerns and to obtain an AB 2404 Grievance Form.
Upon completion of the City’s AB 2404 Grievance Form, the issue(s) will be investigated and
reviewed for further action, which may include the Director of Recreation and Community
Services, and Recreation and Parks Commission. The Recreation and Community Services
office is located at 375 Campus Drive, P.O. Box 60021, Arcadia, CA 91066-6021.
2.Attend a Recreation and Parks Commission meeting, and voice any concerns during oral
communications.
After doing so:
The Recreation and Parks Commission may put the item on the agenda at an upcoming
meeting for further discussion.
During the upcoming meeting the item will be discussed, and if it requires action, the
Recreation and Parks Commission may ask staff to investigate the item further, or make a
recommendation that will be forwarded to the City Council for final approval.
3.Attend a City Council meeting, and voice any concerns during oral communications.
After doing so:
The City Council may ask staff to put the item on the agenda at an upcoming meeting for
further discussion.
During the upcoming meeting the item will be discussed and if it requires action, the City
Council may ask staff to investigate the item further, or make a decision for final action.
The grievance procedure does not restrict the right to file a complaint with any state or federal agency
responsible for the enforcements of anti-discrimination legislation.
It is the commitment of the City to confront and eliminate discrimination, providing gender equitable
opportunities for all youth involved in sports programs. The meaning of gender equitable opportunities
in this City is defined as: The absence of discrimination and unfavorable treatment of citizens; the
promotion of gender equitable sports programs; and the commitment to ensure equitable support of
facilities, fields, and promotion of girls’ and boys’ athletics programs.
8
Exhibit 3 - City of Arcadia
Title IX – AB 2404 Grievance Form
The purpose of this form is to assist you in filing a Gender Equity complaint. You are not required to
use this form; a letter with the same information is sufficient. However, the information requested in
the items marked with a star (*) must be provided, whether or not the form is used.
NOTE: Item #11 must be signed before form is submitted.
1. * State your name and address.
Name: ______________________________________________________________________
Address: ________________________________ City: ___________________ Zip: _________
Phone Number: Home: ( _____ ) _________________ Alternate: ( _____ ) ________________
E-mail: ______________________________________________________________________
2. * Person(s) discriminated against, if different from above:
Name: _______________________________________________________________________
Address: _________________________________ City: ___________________ Zip: _________
Phone Number: Home: ( _____ ) _________________ Alternate: ( _____ )_________________
E-mail: _______________________________________________________________________
Please explain your relationship to this person(s): ____________________________________
If person discriminated against is a minor (under 18 years old), please provide the following
information:
Parent/Guardian Name: ________________________________________________________
Address: ________________________________ City: ___________________ Zip: _________
Phone Number: Home: ( _____ ) _________________ Alternate: ( _____ ) ________________
E-mail: ______________________________________________________________________
3. * Agency and Department or program that discriminated:
Name: _______________________________________________________________________
Address: _________________________________ City: ___________________ Zip: _________
Phone Number: Home: ( _____ ) _________________ Alternate: ( _____ ) _________________
E-mail: _______________________________________________________________________
4. * AB 2404 Complaint: Please indicate below the basis on which you believe these discriminatory
actions were taken.
Race/Ethnicity: _______ National Origin: _______ Sex: _______ Religion: _______ Age: _______
Disability: _______ Sexual Orientation: _______ Other: _________________________________
9
AB 2404 Grievance Form Page 2 of 4
5. * To the best of your recollection, on what date(s) did the alleged discrimination take place?
Earliest Date of Discrimination: __________ Most Recent Date of Discrimination: ___________
6.* Please explain as clearly as possible what happened, why you believe it happened, and how you
were discriminated against. Indicate who was involved. Be sure to include how other persons were
treated differently from you. Please use additional sheets if necessary and attach a copy of written
materials pertaining to your case.
Please list below any persons (witnesses, fellow employees, supervisors, or others) if known, whom we
may contact for additional information to support or clarify your complaint.
Name ______________________________________________________________________________
Address: ________________________________ City: ________________ State: _____ ZIP: _________
Area Code/Telephone: ( _____ )____________________Alternate: ( _____ ) _______________________
Email: _______________________________________________________________________________
7. Do you have any other information that you think is relevant to our investigation of your allegations?
8. What remedy are you seeking for the alleged discrimination?
9. What are the most convenient times and place for us to contact you about this complaint?
10. If you have an attorney representing you concerning the matters raised in this complaint, please
provide the following:
Attorney’s Name/Firm: _________________________________________________________________
Address: _______________________________ City: ___________________ State: ____ Zip: _________
Phone Number: Home: ( _____ ) ______________________ Alternate: ( _____ ) ___________________
E-mail: _______________________________________________________________________________
11. * We cannot accept a complaint if it has not been signed. Please sign and date below.
__________________________________________________________________
Name - Print
__________________________________________________________________ ______________
Name - Signature Date
Please submit completed form to City of Arcadia Title IX-AB 2404 Compliance Coordinator:
Ryan Wright, 626.821.4398, Recreation and Community Services Office, 375 Campus Drive,
PO Box 60021, Arcadia, CA 91066-6021
10
Appendix B
Community Wide Phone Survey
Research Network Ltd.
Research Network Ltd.
Appendix B
Community-wide Survey
Arcadia Recreation & Parks Master Plan
November, 2015
City of Arcadia Community-wide Survey November, 2015
CONTENTS
1 Project Overview 2
1.1 Project Goals 2
1.2 Project Methodology 2
2 Key Findings 3
3 Recreation Information Sources 6
3.1 Parks, Recreation Facilities, Programs Info Sources 6
4 Recreation Benefits and Behavior 8
4.1 Most Important Recreation Benefit 8
4.2 Recreation Facility Usage 10
4.3 Recreation Facility Most Often Used 11
4.4 Recreation Activities Participation 12
4.5 Recreation Programs and Events Usage 15
4.6 Senior Recreation Programs Usage 16
4.7 Teen Recreation Programs Usage 17
4.8 Special Events Attendance 18
5 Recreation Programs Satisfaction 19
5.1 Recreation Programs Satisfaction 19
6 Improvements Desired 20
6.1 Preferred Community Improvements 20
6.2 One Recreation Facility Improvement Desired 21
6.3 One New Recreation Program Desired 23
6.4 Interest in New Teen Programs 24
6.5 Interest in New Events 25
6.6 One Special Event Desired 26
7 Respondent Demography 27
APPENDIX
Questionnaire
Response Tabulations
Page | 1
City of Arcadia Community-wide Survey November, 2015
1 PROJECT OVERVIEW
1.1 PROJECT GOALS
The Community-wide Survey was part of the preparation of the City of Arcadia
Recreation & Parks Master Plan. The purpose of the survey was to obtain
statistically valid, community-wide input on a variety of issues relevant to parks
and recreation planning in the City.
The Community-wide Survey is one of several methods being undertaken to
involve the community in the Recreation & Parks Master Plan process. The
purpose of gathering community input through a variety of methods is to ensure
that the Master Plan is as inclusive as possible and that it reflects the views,
preferences, and recreating patterns of City of Arcadia residents.
Subjects explored in the context of the resident survey included:
Parks, Recreation Facilities/Programs Info Sources
Recreation Benefits Desired
Recreation Facility and Programs Usage
Park or Recreation Facility Most Often Used in Last Year
Recreation Activities Participation
Senior Recreation Programs Participation
Teen Recreation Programs Participation
Arcadia Special Events Attendance
Satisfaction with Recreation Programs
Preferred Improvements in the City of Arcadia
One New Recreation Facility Desired
One New Recreation Program, Class or Lesson Desired
Propensity to Attend New Events in Arcadia
One New Event Desired in Arcadia
Propensity to Participate in New Teen Recreation Programs
Selected Demographic Characteristics
1.2 PROJECT METHODOLOGY
Telephone Survey of 200 City of Arcadia households, selected at random,
representing approximately 570 residents.
Interviews were conducted in English and Mandarin Chinese languages.
Interviews were conducted via land line and cellular telephones.
Overall margin of error of + 7.1% at the 95% Confidence Level.
Interviewing took place between October 13 and October 27, 2015.
Page | 2
City of Arcadia Community-wide Survey November, 2015
2 KEY FINDINGS
More than half (52%) of residents identified web-based
Information
sources including and "City Website"
responses. "Mailed Information" was identified by more than
Sources
one in ten residents (12%) as their primary information source.
.
.More than half of residents (56%) chose "Physical Fitness,
Health and Well-being" as the most important benefit when
seeking recreation.
.
More than eight of every ten Arcadia households (83%)
reported having used recreation facilities in the past year,
comparable to the 86% average of other communities
surveyed. Of these recreation facility users, 88% reported
most often using facilities located in the City of Arcadia.
Recreation
Benefits and
The six recreation facilities most often identified as most used
included Arcadia Park, Arcadia Community Center, Santa
Behavior
Anita Golf Course, Parks Outside Arcadia, Santa Anita
Racetrack and Tierra Verde Park.
Of the five recreation activities tested, the greatest
participation by residents (in order) included
Running/Hiking on Public Trails, Streets or Sidewalks for
Recreation or Fitness, Activities for
on Public Trails or Paths for Active Recreation or
Sports Leagues for and
Activities reportedly conducted most often outside the City of
Arcadia included at 24% of users, at 23% of
at 21% and Youth
at 20%.
Page | 3
City of Arcadia Community-wide Survey November, 2015
Nearly six in ten Arcadia households (59%) reported using
recreation programs, classes or lessons in the past year,
somewhat higher than the 53% average of other communities
surveyed. Of these users, 76% reported using such programs
at facilities located within the City of Arcadia.
Recreation
Three in ten Arcadia households with a member 50 years or
older (30%) reported using senior recreation programs,
Programs
classes or lessons. Of these users, 83% reported participating
and Events
in these programs at a location within the City of Arcadia.
Use
Eight in ten households polled (80%) with members aged 13 to
17 years stated these teens used teen recreation programs in
the past year. Of these teen program users, 84% reported
most often participating at a location in the City of Arcadia.
More than half of Arcadia households polled (56%) stated they
had attended one or more special events in the City of Arcadia
in the past year. Most of these attendees (75%) reported such
attendance more than once during the past year.
Recreation
Fully 93% of the residents polled stated they are Very or
Programs
Somewhat Satisfied with existing park and recreation
programs in the City of Arcadia.
Satisfaction
Page | 4
City of Arcadia Community-wide Survey November, 2015
Nearly one-third of City of Arcadia households (32%) identified
a preference for Active Recreation Facilities and Programs
while the next largest share of households (28%) preferred
Fine Arts or Performing Arts Facilities and Programs.
Remaining households were evenly split between preference
for Classes, Lessons and Community Events or Open Space
Preservation and Enjoyment.
More than three in four (77%) City of Arcadia households
identified a desired recreation facility. One in five (23%) stated
they desired no new recreation facilities. The facilities most
often mentioned were, in aggregate, Swimming Pools (19%),
Trails (12%), Fitness Center (4%), and Gymnasium (4%).
Changes
Nearly two-thirds of households polled (64%) identified a
desired new recreation program. The remaining 36% of
Desired
households stated they desired no new programs. The
recreation programs most often mentioned as desired included
Dance (8%), Fitness (6%), or Personal Development (5%)
instruction or classes.
Nearly two-thirds of households with teens present (64%)
stated they would be somewhat or very likely to participate in
new teen programs if offered in Arcadia.
Eight in ten residents polled (81%) stated they were
Somewhat or Very likely to attend new community events if
offered in Arcadia.
The recreation events most often mentioned as desired
included Farmers Market (26%), Concerts (22%), Cultural
Events (7%), Ethnic Diversity Events (5%), Fireworks (5%),
Seasonal Events (5%), Bike Rides (3%), and Street Fair (3%).
Page | 5
City of Arcadia Community-wide Survey November, 2015
3 RECREATION INFORMATION SOURCES
3.1 PARKS, RECREATION FACILITIES/PROGRAMS INFO SOURCES
Question Analyzed: Q.5
If you need information about parks and recreation facilities or programs, where do you usually
get that information?
Finding
More than half (52%) of residents identified web-based sources including
and "City Website" responses. "Mailed Information" was
identified by more than one in ten residents (12%) as their primary information
source.
The eight response categories with the largest share of responses are presented in Figure 1.
Remaining categories received less than 2% of the responses.
Figure 1
Parks, Recreation Facilities, Programs Info Sources
City of Arcadia Residents
Internet
27%
City Website
25%
Mailed Info
12%
Don't Need
8%
Peacock Buzz
7%
Newspaper
6%
City Office
5%
Rec Sites
5%
0% 10% 20% 30%
Page | 6
City of Arcadia Community-wide Survey November, 2015
Subgroup Responses
Examining the total sample of responses by selected subgroups of residents, the
following significant differences in response patterns were noted:
Residents most likely to report usually using the City website included respondents
reporting household incomes of $75,000 to $150,000 (39% vs. 25% overall) and
households with a head 45 to 64 years of age (39%).
Residents least likely to report usually using the City website included respondents
with a household head 65 years or older (4%) and those reporting household
incomes of less than $75,000 (14%).
Page | 7
City of Arcadia Community-wide Survey November, 2015
4 RECREATION BENEFITS AND BEHAVIOR
4.1 MOST IMPORTANT RECREATION BENEFIT
Question Analyzed: Q.6
Reflecting upon the recreation patterns of those in your household, which one of the following benefits
do you feel is most important when you seek recreation or leisure opportunities? Would it
Physical Fitness, Health and Well-being
Opportunities to Gather and Socialize with Others
Learning Opportunities for Hobby, Self-Improvement or Career Development
Opportunities to Give Back to the Community Through Volunteer Work
Finding
More than half of residents (56%) chose "Physical Fitness, Health and Well-being" as
the most important benefit when seeking recreation.
The benefits tested and the share of responses each received is presented in Figure 2.
Figure 2
Most Important Recreation Benefit
City of Arcadia Residents
Fitness
56%
Learning
21%
Social
17%
Volunteer
6%
0% 20% 40% 60%
Page | 8
City of Arcadia Community-wide Survey November, 2015
Communities Compared
Table 1 below compares these recreation benefit responses from City of Arcadia residents to
statistics derived from twenty-seven other California municipalities where similar work has been
conducted. Because each survey questionnaire is custom-designed for each agency, the
number of comparison surveys varies by question.
The residents of the City of Arcadia reported a higher level of interest in Physical Fitness, Health
and Well-Being benefits than all communities previously surveyed. The share of residents
choosing Learning Opportunities for Hobby, self-improvement or Career Development as most
important was above the average posted historically. Conversely, the two remaining benefit
categories received a lower than average response from City of Arcadia residents polled.
Table 1
Most Important Recreation Benefits
City of Arcadia vs. Twenty-seven Selected California Municipalities
Twenty-seven Selected California Municipalities
Lowest
City of Arcadia
Highest Response Median
Response
Health/Fitness 56% 31% 54% 47%
Learning 21% 12% 28% 16%
Gather/Socialize 17% 19% 36% 28%
Volunteer 6% 6% 16% 9%
Page | 9
City of Arcadia Community-wide Survey November, 2015
4.2 RECREATION FACILITY USAGE
Question Analyzed: Q.7
Thinking about the past year, what best describes how you or other members of your household use
indoor or outdoor parks and recreation facilities in or outside of the City of Arcadia?
Most often used facilities located in Arcadia Most
often used facilities located outside Arcadia Did
not use parks and recreation facilities
Finding
More than eight of every ten Arcadia households (83%) reported having used parks in
and outside Arcadia. Of these recreation facility users, 88% reported most often using
facilities located in the City of Arcadia.
The facility use categories tested and the share of responses each received is presented
in Figure 3.
Figure 3
Recreation Facility Use
City of Arcadia Residents
Arcadia Users
88%
Non-Arcadia Users
12%
0% 20% 40% 60% 80%
Page | 10
City of Arcadia Community-wide Survey November, 2015
Subgroup Responses
An examination of reported recreation facility use among City of Arcadia residents revealed the
following statistically significant differences in the overall 83% share of facility users among
examined subgroups of the total sample. Residents most likely to have used recreation facilities
included:
Households with children less than 18 years of age (95%).
Households reporting an annual income of $75,000 to $150,000 (92%).
4.3 RECREATION FACILITY MOST OFTEN USED
Question Analyzed: Q.8
During the last year, what one park or recreation facility did you and your household most often use?
Finding
The six recreation facilities most often identified as most used included Arcadia Park,
Arcadia Community Center, Santa Anita Golf Course, Parks Outside Arcadia, Santa
Anita Racetrack and Tierra Verde Park.
The six response categories with the largest share of responses are presented in Figure 4.
Remaining categories received less than 4% of the responses.
Figure 4
Most Used Recreation Facility
City of Arcadia Residents
Arcadia Park
33%
Community Center
16%
Santa Anita GC
9%
Outside Arcadia
7%
Santa Anita RT
5%
Tierra Verde
4%
0% 5% 10% 15% 20% 25% 30% 35%
Page | 11
City of Arcadia Community-wide Survey November, 2015
4.4 RECREATION ACTIVITIES PARTICIPATION
Question Analyzed: Q.9
I am going to read a list of recreation activities to you. Please tell me what best describes how youor
other members of your household participated in each activity in the past year, NOT including school-
related activities.
Walking/Jogging/Running/Hiking on Public Trails, Streets or Sidewalks for Recreation or Fitness
Bicycling on Public Trails or Paths for Active Recreation or Fitness
Organized Sports Leagues for Youth
Golf Activities
Indoor Activities for Adults such as Basketball, Volleyball, Badminton, Martial Arts, Fitness, Yoga, Dance
Finding
Of the five recreation activities tested, the greatest participation by residents (in order)
included on Public Trails, Streets or Sidewalks for
Recreation or Activities for on Public Trails or Paths
for Active Recreation or Sports Leagues for and
Activities reportedly conducted most often outside the City of Arcadia included
at 24% of users, at 23% of Adult at 21% and
Youth at 20%.
The five recreation activities tested and the share of the households surveyed in the City of
Arcadia that reported participation in the past year are presented in Figure 5 on the following
page. Figure 6 presents the share of users who stated they most often use recreation facilities
outside of the City of Arcadia for these activities.
Page | 12
City of Arcadia Community-wide Survey November, 2015
Figure 5
Recreation Activities Participation
Share of Arcadia Households Participating
Walk/Jog/Run/Hike
74%
Indoor Adult Activities
44%
Bicycling
32%
Youth Sports
17%
Golf
16%
0% 10% 20% 30% 40% 50% 60% 70% 80%
Figure 6
Recreation Activities Participation
Households Participating Outside City
Bicycling
24%
Golf
23%
Indoor Adult Activities
21%
Youth Sports
20%
Walk/Jog/Run/Hike
15%
0% 5% 10% 15% 20% 25%
Page | 13
City of Arcadia Community-wide Survey November, 2015
Note
The data presented in Figures 5 may appear counter intuitive to representatives of organized
sports leagues for youth and to agency officials who regularly host comments or testimony
from them. To confirm the validity of the participation levels, it is important to recognize the
demography of the area population. Specifically, youth ages 5 to 14 (the prime ages for youth
sports) constituted less than 13% of the total City population as of the 2010 Census.
Page | 14
City of Arcadia Community-wide Survey November, 2015
4.5 RECREATION PROGRAMS AND EVENTS USAGE
Question Analyzed: Q.11
Thinking about the past year, what best describes how you or other members of your household
participated in recreation programs, classes or lessons in or outside of the City of Arcadia?
Most often participated at a location in Arcadia
Most often participated at a location outside Arcadia
Did not participate in recreation programs, classes or lessons
Finding
Nearly six in ten Arcadia households (59%) reported using recreation programs,
classes or lessons in the past year, somewhat higher than the 53% average of other
communities surveyed. Of these users, 76% reported using such programs at
facilities located within the City of Arcadia.
The facility use categories tested and the share of responses each received is presented in
Figure 7.
Figure 7
Recreation Programs Use
City of Arcadia Residents
Arcadia Users
76%
Non-Arcadia Users
24%
0% 20% 40% 60% 80%
Page | 15
City of Arcadia Community-wide Survey November, 2015
4.6 SENIOR RECREATION PROGRAMS USAGE
Question Analyzed: Q.12
Thinking about the past year, what best describes how the members of your household 50 years of
age or older used senior recreation programs, classes or lessons in or outside of the City of Arcadia?
Most often participated at a location in Arcadia Most
often participated at a location outside Arcadia
Did not participate in recreation programs, classes or lessons
Finding
Three in ten Arcadia households with a member 50 years or older (30%) reported
using senior recreation programs, classes or lessons. Of these users, 83% reported
participating in these programs at a location within the City of Arcadia.
The facility use categories tested and the share of responses each received is presented in
Figure 8.
Figure 8
Senior Recreation Programs Use
City of Arcadia Residents
Arcadia Users
83%
Non-Arcadia Users
17%
0% 20% 40% 60% 80% 100%
Page | 16
City of Arcadia Community-wide Survey November, 2015
4.7 TEEN RECREATION PROGRAMS USAGE
Question Analyzed: Q.13
Thinking about the past year, what best describes how the members of your household aged 13 to 17
used teen recreation programs, classes or lessons in or outside of the City of Arcadia?
Most often participated at a location in Arcadia
Most often participated at a location outside Arcadia
Did not participate in recreation programs, classes or lessons
Finding
Eight in ten households polled (80%) with members aged 13 to 17 years stated
these teens used teen recreation programs in the past year. Of these teen program
users, 84% reported most often participating at a location in the City of Arcadia.
The facility use categories tested and the share of responses each received is presented in
Figure 9.
Figure 9
Teen Recreation Programs Use
City of Arcadia Residents
Arcadia Users
84%
Non-Arcadia Users
1
6%
0% 20% 40% 60% 80% 100%
Page | 17
City of Arcadia Community-wide Survey November, 2015
4.8 SPECIAL EVENTS ATTENDANCE
Question Analyzed: Q.15
Thinking about the past year, what best describes how often you or other members of your household
attended special events in the City of Arcadia? Examples of such events include the Concerts or
Movies in the Park, Winter Snow Festival, Community Bike Ride and the Summer Dance Night.
Most often participated at a location in Arcadia
Most often participated at a location outside Arcadia
Did not participate in recreation programs, classes or lessons
Finding
More than half of Arcadia households polled (56%) stated they had attended one or
more special events in the City of Arcadia in the past year. Most of these attendees
(75%) reported such attendance more than once during the past year.
The facility use categories tested and the share of responses each received is presented in
Figure 10.
Figure 10
Special Events Attendance in Past Year
City of Arcadia Residents
Once Per Year
25%
Several Times /Yr.
62%
1-2 Times/Mo.
13%
0% 10% 20% 30% 40% 50% 60% 70%
Page | 18
City of Arcadia Community-wide Survey November, 2015
5 RECREATION PROGRAMS SATISFACTION
5.1 RECREATION PROGRAMS SATISFACTION
Question Analyzed: Q.18
How would you describe your overall satisfaction with existing park and recreation programs in the
City of Arcadia? Would you say you are:
Very Satisfied
Somewhat Satisfied
Not Very Satisfied
Not At All Satisfied
Finding
Fully 93% of the residents polled stated they are Very or Somewhat Satisfied with
existing park and recreation programs in the City of Arcadia.
The response categories and share of responses each received are charted in Figure 11.
Figure 11
Recreation Programs Satisfaction
City of Arcadia Residents
Very
46%
Satisfied
Somewhat
47%
Satisfied
Not Very
6%
Satisfied
Not At All
1%
Satisfied
0% 10% 20% 30% 40% 50%
Page | 19
City of Arcadia Community-wide Survey November, 2015
6 IMPROVEMENTS DESIRED
6.1 PREFERRED COMMUNITY IMPROVEMENTS
Question Analyzed: Q.20
Thinking about the needs of your household, which one of the following types of improvements would
you most like to see added in the City of Arcadia?
Active Sports Facilities and Programs at neighborhood or community parks
Fine Arts or Performing Arts Facilities and Programs
Classes, Lessons, and Community Events
Open Space Preservation and Enjoyment
Finding
Nearly one-third of City of Arcadia households (32%) identified a preference for
Active Recreation Facilities and Programs, equaling the largest posting of
communities previously surveyed. The next largest share of Arcadia households
(28%) preferred Fine Arts or Performing Arts Facilities and Programs. Remaining
households were evenly split between preference for Classes, Lessons and
Community Events or Open Space Preservation and Enjoyment.
Page | 20
City of Arcadia Community-wide Survey November, 2015
The program response categories and the share of responses each received are charted in
Figure 12.
Figure 12
Preferred Community Improvements
City of Arcadia Residents
Active Recreation
32%
Fine Arts
28%
Classes/Events
20%
Open Space
20%
0% 10% 20% 30% 40%
6.2 ONE NEW RECREATION FACILITY IMPROVEMENT DESIRED
Question Analyzed: Q.10
Now that we have discussed many recreation possibilities, what is the one recreation facility you
would most like to see added in the City of Arcadia to meet the needs of your household?
Finding
More than three in four (77%) City of Arcadia households identified a desired
recreation facility. One in five (23%) stated they desired no new recreation facilities.
The facilities most often mentioned were, in aggregate, Swimming Pool (19%), Trails
(12%), Community Center/Senior Facilities/Teen and Youth Club (8%), Fitness
Center (4%), and Gymnasium (4%).
Page | 21
City of Arcadia Community-wide Survey November, 2015
The recreation facility response categories garnering at least 3% of the responses and the share
of responses each received are charted in Figure 13.
Figure 13
Recreation Facilities Desired
City of Arcadia Residents
Swimming Pool
19%
Trails
12%
Community Ctr
8%
Fitness Center
4%
Gymnasium
4%
Dog Park
3%
0% 5% 10% 15% 20%
Page | 22
City of Arcadia Community-wide Survey November, 2015
6.3 ONE NEW RECREATION PROGRAM, CLASS OR LESS DESIRED
Question Analyzed: Q.19
What is the one recreation program, class or lesson you would most like to see added in the City of
Arcadia to meet the needs of your household?
Finding
Nearly two-thirds of households polled (64%) identified a desired new recreation
program. The remaining 36% of households stated they desired no new programs.
The recreation programs most often mentioned as desired included Dance (8%),
Fitness (6%), or Personal Development (5%) instruction or classes.
The recreation facility response categories garnering at least 3% of the responses and the share
of responses each received are charted in Figure 14.
Figure 14
Recreation Program Desired
City of Arcadia Residents
Dance
8%
Fitness
6%
Personal Dev
5%
Yoga
4%
Martial Arts
4%
Cooking
4%
Arts/Crafts
3%
0% 5% 10%
Page | 23
City of Arcadia Community-wide Survey November, 2015
6.4 PROPENSITY TO PARTICIPATE IN NEW TEEN PROGRAMS IN ARCADIA
Question Analyzed: Q.14
How likely would the members of your household aged 13 to 17 years be in participating in new teen
programs if offered in Arcadia?
Very likely
Somewhat likely
Not very likely
Not at all likely
Finding
Nearly two-thirds of households with teens present (64%) stated they would be
somewhat or very likely to participate in new teen programs if offered in Arcadia.
The facility use categories tested and the share of responses each received is presented in
Figure 15.
Figure 15
Propensity to Use New Teen Programs
City of Arcadia Residents
Very likely
28%
Somewhat likely
36%
Not very likely
13%
Not at all likely
23%
0% 10% 20% 30% 40%
Page | 24
City of Arcadia Community-wide Survey November, 2015
6.5 PROPENSITY TO PARTICIPATE IN NEW EVENTS IN ARCADIA
Question Analyzed: Q.16
How likely would the members of your household be in participating in new events if offered in
Arcadia?
Very likely
Somewhat likely
Not very likely
Not at all likely
Finding
Eight in ten residents polled (81%) stated they were Somewhat or Very likely to
attend new community events if offered in Arcadia.
The facility use categories tested and the share of responses each received is presented in
Figure 16.
Figure 16
Propensity to Attend New Events
City of Arcadia Residents
Very likely
34%
Somewhat likely
47%
Not very likely
11%
Not at all likely
8%
0% 10% 20% 30% 40% 50%
Page | 25
City of Arcadia Community-wide Survey November, 2015
6.6 ONE NEW EVENT DESIRED
Question Analyzed: Q.17
What one new event would the members of your household most like to see added in the City of
Arcadia?
Finding
The recreation events most often mentioned as desired included Farmers Market
(26%), Concerts (22%), Cultural Events (7%), Ethnic Diversity Events (5%), Fireworks
(5%), Seasonal Events (5%), Bike Rides (3%), and Street Fair (3%).
The recreation facility response categories garnering at least 3% of the responses and the share
of responses each received are charted in Figure 17.
Figure 17
One New Event Desired
City of Arcadia Residents
Farmers Market
26%
Concerts
22%
Cultural Events
7%
Ethnic Diversity Events
5%
Fireworks
5%
Seasonal Events
5%
Bike Rides
3%
Street Fair
3%
0% 10% 20% 30%
Page | 26
City of Arcadia Community-wide Survey November, 2015
7 RESPONDENT DEMOGRAPHY
7.1 Demographic Profile of Respondents
Questions Analyzed: Q.1, 2, 3, 4, 21, 22, 23, 24
A collection of demographic questions was included in the survey questionnaire to enable validation of
the reliability of the survey sample of respondents as well as for use in response analysis.
Home Zip Code
Age of Household Members
Number of Household Members
Tenure in the City of Arcadia
Race/Ethnicity of Respondent
Annual Household Income
Finding
A comparison of the demographic profile of respondents to the benchmark 2010
Census profile for the City of Arcadia confirmed the reliability of the survey sample.
Table 2 on the following page presents the detailed comparison of selected demographic
characteristics from the Survey and the 2010 Census.
Page | 27
City of Arcadia Community-wide Survey November, 2015
Table 2
Community-Wide Telephone Survey
Demographic Characteristics
City of Arcadia
2010 Census Survey
Percent of Householder by Age:
2% 2%
Less than 24 years
11% 10%
25 to 34 years
21% 21%
35 to 44 years
27% 26%
45 to 54 years
18% 18%
55 to 64 years
21% 23%
65 years and over
Household Description:
20% 20%
1 adult w-o children
43% 42%
2 or more adults w-o children
63% 62%
Subtotal Households w-o children
NA 2%
1 adult w/children
NA 24%
2 adults w/children
NA 12%
3 or more adults w/children
37% 38%
Subtotal Households w/children
Race/Ethnicity of Householder:
52% 52%
Non-Hispanic Asian/Pacific Islander
36% 36%
Non-Hispanic White
10% 10%
Hispanic/Latino
1% 1%
Non-Hispanic Black/African American
1% 1%
Non-Hispanic Other
Source: 2010 Census
Page | 28
Appendix C
Community Web & Hard Copy Surveys
Q1 In which community do you live? Please select one.
Answered: 380 Skipped: 0
Arcadia
Pasadena
Duarte
Temple City
Monrovia
San Marino
San Gabriel
Sierra Madre
Other
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
72.37%
275
Arcadia
3.42% 13
Pasadena
2.11%
8
Duarte
5.79% 22
Temple City
2.89%
11
Monrovia
0.53% 2
SanMarino
3.42%
13
SanGabriel
1.32% 5
Sierra Madre
8.16%
31
Other
Total380
Њ
Q2 Which of the following benefits of recreation programs and services are
most important to you? Please mark all that apply.
Answered: 374 Skipped: 6
Opportunities
to enjoy eve...
Promote youth
mental &...
Improve
fitness, hea...
Opportunities
for communit...
Opportunities
for lifelong...
Cultural
opportunitie...
Help seniors
maintain...
Connect people
together,...
Enhance
community im...
Helping
persons with...
Access to
social servi...
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
AnswerChoices Responses
72.46% 271
Opportunities to enjoy events and activities with other people
44.65%
167
Promote youth mental & physical development
67.38%
252
Improve fitness, health and wellness
28.34% 106
Opportunities for community organizations to meet
47.59%
178
Opportunities for lifelong learning by taking interesting classes
44.39% 166
Cultural opportunities (e.g., arts, music, theater & dance)
53.74% 201
Help seniors maintain socially active lifestyles
35.56% 133
Connect people together, building stronger family ties by participating in family events
35.03% 131
Enhance community image and sense of place
28.07% 105
Helping persons with disabilities feel included and remain socially active
25.13% 94
Access to social services and assistance programs
TotalRespondents: 374
Ћ
Q3 What types of cultural arts programming for all ages would you like to see offered in Arcadia
in the future? (1 BEING THE MOST DESIRED AND 10 BEING THE LEAST DESIRED ACTIVITY.)
Answered: 261 Skipped: 119
Art
Dance
Music
Singing/Acting
Theatre
Productions
Culinary/Cookin
g
Crafts
Reading
Jewelry Making
Ceramics
Classes
0 1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10 Total Score
Art 14.02% 17.76% 13.08% 15.42% 13.08% 9.35% 9.35% 2.34% 3.74% 1.87%
30 38 28 33 28 20 20 5 8 4
214 6.92
13.08% 11.68% 14.95% 10.75% 14.02% 8.88% 7.48% 6.54% 5.61% 7.01%
Dance
28 25 32 23 30 19 16 14 12 15
214 6.27
Music 22.67% 22.67% 17.33% 11.56% 7.56% 4.44% 5.78% 3.56% 2.67% 1.78%
51 51 39 26 17 10 13 8 6 4
225 7.59
4.19% 9.77% 12.56% 13.02% 9.30% 11.16% 13.95% 9.30% 6.98% 9.77%
Singing/Acting
9 21 27 28 20 24 30 20 15 21
215 5.40
Theatre Productions 17.81% 9.13% 8.68% 10.50% 10.96% 5.94% 9.59% 10.05% 9.59% 7.76%
39 20 19 23 24 13 21 22 21 17
219 5.94
13.78% 12.00% 10.67% 11.11% 13.33% 14.22% 8.44% 8.44% 4.44% 3.56%
Culinary/Cooking
31 27 24 25 30 32 19 19 10 8
225 6.32
Crafts 4.07% 10.41% 10.41% 14.03% 9.50% 14.48% 14.03% 16.74% 4.98% 1.36%
9 23 23 31 21 32 31 37 11 3
221 5.63
Reading 13.06% 7.66% 9.46% 5.41% 9.46% 12.16% 13.06% 10.81% 7.21% 11.71%
29 17 21 12 21 27 29 24 16 26
222 5.41
5.21% 3.32% 6.16% 4.74% 8.53% 5.69% 4.27% 10.43% 23.22% 28.44%
Jewelry Making
11 7 13 10 18 12 9 22 49 60
211 3.67
Ceramics Classes 6.48% 5.09% 6.02% 6.94% 5.09% 7.87% 7.87% 13.43% 22.22% 18.98%
14 11 13 15 11 17 17 29 48 41
216 4.13
Ќ
Q4 What is the ONE current recreation amenity you would MOST like to see the City
address for the future in its Parks and Recreation Master Plan to meet the needs of the
members of your household? Please select ONE choice.
Answered: 354 Skipped: 26
Community/Senior
Center
Meeting
&Cclassrooms
Bonita Skate
Park
Neighborhood
parks
Sports fields
Par 3 Golf
Course
Wilderness Park
Dog Park
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
38.98%
138
Community/Senior Center
8.19% 29
Meeting & class rooms for special interest classes and activities
1.41%
5
Bonita Skate Park
17.23% 61
Neighborhood parks
18.93%
67
Sports fields
1.98% 7
3 Par Golf Course
9.60%
34
Wilderness Park
3.67% 13
Dog Park
Total354
Ѝ
Q5 Do you attend special events in Arcadia? (Examples: Concerts & Movies
in the Park, Snow Fest, Bike Ride)
Answered: 361 Skipped: 19
Yes, they are
an important...
Sometimes,
depending on...
Yes, but only
occasionally
No, I have
never attend...
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
23.55% 85
Yes, they are an important activity to feel a part of the community for me and my family
38.50%
139
Sometimes, depending on the event
26.04% 94
Yes, but only occasionally
11.91%
43
No, I have never attended a special event in Arcadia
Total361
Ў
Q6 If you have used any of the following facilities during the last 12 months for
RECREATION purposes, please check the box that corresponds to the frequency of
your use of these facilities.
Frequently (Once a week or more) Sometimes (1-2 times a month)
Rarely (Less than 5 times a year) Never
Answered: 351 Skipped: 29
Arcadia
Community/Se...
Arcadia Par 3
Golf Course
Bicentennial
Park
Bonita Park
Џ
Camino Park
Civic Center
Athletic Park
Eisenhower
Memorial Park
Fairview
Avenue Park
Forest Avenue
Park
А
Hugo Reid Park
Longden Avenue
Park
Newcastle Park
Orange Grove
Park
Tierra Verde
Park
Tripolis
Friendship Park
Б
Wilderness Park
LA County
Arboretum
Arcadia High
School
LA County
Arcadia Park
Baldwin
Stocker Park
В
Dana Middle
School
Highland Oaks
Park
Holly Avenue
Park
Peck Road
Fishing Park
LA County
Santa Anita...
ЊЉ
Santa Anita
Race Track
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Frequently (Once a week or more) Sometimes (1-2 times a month)
Rarely (Less than 5 times a year) Never
Frequently (Once a week or Sometimes (1-2 times a Rarely (Less than 5 times a Never Total
more) month) year)
38.91% 16.08% 25.40% 19.61%
Arcadia Community/Senior
Center 121 50 79 61
311
Arcadia 3 Par Golf Course 1.23% 9.84% 19.26% 69.67%
3 24 47 170
244
2.62% 7.86% 18.34% 71.18%
Bicentennial Park
6 18 42 163
229
Bonita Park 3.03% 8.23% 20.78% 67.97%
7 19 48 157
231
6.84% 5.98% 18.38% 68.80%
Camino Park
16 14 43 161
234
Civic Center Athletic Park 8.97% 7.26% 14.96% 68.80%
21 17 35 161
234
Eisenhower Memorial Park 3.32% 14.52% 21.99% 60.17%
8 35 53 145
241
1.76% 2.64% 11.89% 83.70%
Fairview Avenue Park
4 6 27 190
227
Forest Avenue Park 0.90% 0.00% 7.24% 91.86%
2 0 16 203
221
3.48% 7.83% 10.43% 78.26%
Hugo Reid Park
8 18 24 180
230
Longden Avenue Park 2.63% 5.70% 16.23% 75.44%
6 13 37 172
228
3.46% 3.03% 14.72% 78.79%
Newcastle Park
8 7 34 182
231
Orange Grove Park 0.89% 0.89% 10.67% 87.56%
2 2 24 197
225
3.10% 2.65% 12.39% 81.86%
Tierra Verde Park
7 6 28 185
226
Tripolis Friendship Park 4.00% 1.33% 8.89% 85.78%
9 3 20 193
225
ЊЊ
5.83% 12.08% 33.75% 48.33%
Wilderness Park
14 29 81 116
240
LA County Arboretum 18.37%23.47%45.92%12.24%
54 69 135 36
294
Arcadia High School 17.93% 22.71% 26.69% 32.67%
45 57 67 82
251
20.90% 28.73% 30.22% 20.15%
LA County Arcadia Park
56 77 81 54
268
2.65% 3.10% 9.29% 84.96%
Baldwin Stocker Park
6 7 21 192
226
Dana Middle School 7.30% 12.02% 11.59% 69.10%
17 28 27 161
233
4.39% 2.63% 13.16% 79.82%
Highland Oaks Park
10 6 30 182
228
Holly Avenue Park 1.78% 4.44% 9.78% 84.00%
4 10 22 189
225
0.44% 4.87% 10.18% 84.51%
Peck Road Fishing Park
1 11 23 191
226
LA County Santa Anita Golf 4.49% 8.16% 23.67% 63.67%
Course 11 20 58 156
245
4.10% 13.81% 56.72% 25.37%
Santa Anita Race Track
11 37 152 68
268
ЊЋ
Q7 Overall, which of the following statements best describes your
satisfaction with the physical condition (maintenance, cleanliness, etc.) of
the Arcadia city parks and facilities you have visited?
Answered: 352 Skipped: 28
SATISFACTION
0 1 2 3 4 5 6 7 8 9 10
Very satisfied Somewhat satisfied Not very satisfied Not at all satisfied Total Weighted Average
46.59% 44.32% 7.10% 1.99%
Satisfaction
164 156 25 7
352 3.36
ЊЌ
Q8 Have you or others in your household participated in City recreation
programs in Arcadia?
Answered: 349 Skipped: 31
Yes
No Skip
questions 9 ...
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
74.50%
260
Yes
25.50% 89
No Skip questions 9 and 10 and go to question 11
Total349
ЊЍ
Q9 If you answered "yes" to Question #8, which age group programs did
you or your family members participate in? (check all that apply)
Answered: 265 Skipped: 115
Youth
Teen
Adult
Senior
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
45.66%
121
Youth
17.36% 46
Teen
35.85%
95
Adult
40.38% 107
Senior
Total Respondents: 265
ЊЎ
Q10 If you answered "yes" to Question #8, how
would you rate the overall quality of recreation
programs provided by the Arcadia Recreation
and Community Services Department?
Answered: 262 Skipped: 118
Excellent
Good
Fair
Poor
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
37.40% 98
Excellent
51.15%
134
Good
10.69% 28
Fair
0.76%
2
Poor
Total262
ЊЏ
Q11 If you did NOT participate in Arcadia
Recreation and Community Services programs,
classes or lessons, what are your reasons?
Answered: 133 Skipped: 247
Not aware of
programs
Poor quality
of programs
Held at
inconvenient...
Classes or
programs are...
Need child
care in orde...
Too busy; no
time
Too expensive
Need
transportati...
I participate
in other cities
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
22.56%
30
Not aware of programs
9.02% 12
Poor quality of programs
29.32%
39
Heldat inconvenient times
8.27% 11
Classes or programs are full
6.77%
9
Need child care in order to participate
40.60%
54
Too busy; no time
14.29% 19
Too expensive
4.51%
6
Need transportation to participate
11.28% 15
I participate in other cities
Total Respondents: 133
ЊА
Q12 What ethnic category would your family most
identify with?
Answered: 351 Skipped: 29
White
Chinese
Korean
Vietnamese
Other
Asian/Pacifi...
Hispanic
Black/African
American
Other (please
specify)
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
53.85%
189
White
15.38% 54
Chinese
0.57%
2
Korean
0.57% 2
Vietnamese
9.97%
35
Other Asian/Pacific Islander
10.54% 37
Hispanic
1.42%
5
Black/African American
7.69% 27
Other (please specify)
Total351
Q13 What is the ONE program category you would MOST like to address in
the future Parks and Recreation Master Plan to meet the needs of members
of your household?
Answered: 331 Skipped: 49
Programs for
tiny tots an...
Programs for
youth and teens
Programs for
adults
Programs for
seniors
Programs for
the entire...
Programs for
people to...
Programs that
provide...
Program space
for clubs an...
Community wide
special events
Park and
facility...
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
2.72% 9
Programs for tiny tots and preschoolers
12.69%
42
Programs for youth and teens
6.95% 23
Programs for adults
28.10%
93
Programs for seniors
7.85%
26
Programs for the entire family
6.95% 23
Programs for people to socialize and meet their neighbors
8.76%
29
Programs that provide entertainment for all ages
4.53% 15
Program space for clubs and organizations to meet
7.55%
25
Community wide special events
13.90% 46
Park and facility improvements
Total331
Q14 Counting yourself, circle all of the age groups living in your household:
Answered: 353 Skipped: 27
Under age 5
Ages 5-9
Ages 10-14
Ages 15-19
Ages 20-24
Ages 25-34
Ages 35-44
Ages 45-54
Ages 55-64
Ages 65+
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Answer Choices Responses
8.50% 30
Under age 5
19.83%
70
Ages 5-9
20.68% 73
Ages 10-14
18.13%
64
Ages 15-19
6.52% 23
Ages 20-24
9.63%
34
Ages 25-34
26.91%
95
Ages 35-44
28.05% 99
Ages 45-54
16.43%
58
Ages 55-64
45.33%
160
Ages 65+
Total Respondents: 353
Appendix D
Projected Cost Estimates
3/6/2017
Preliminary Opinion of Construction Costs
For
Arcadia Community Center
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$85,000.00$85,000.00
Construction Cost)
Sub-Total $85,000.00
Demolition
Miscellaneous Debris1Allow$63,000.00$63,000.00
Sub-Total $63,000.00
Earthwork
Grading & Drainage1Allow$63,000.00$63,000.00
$86,000.00
Infiltration Swale1Allow$86,000.00
Sub-Total $149,000.00
Site Hardscape
Asphalt Paving at Parking Lot36,000LF$6.00$216,000.00
Porous Pavers at Parking Stalls31,000SF$22.00$682,000.00
Sub-Total $898,000.00
Site Furnishings
Trash Receptacles9EA$1,500.00$13,500.00
Bench3EA$3,500.00$10,500.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table5EA$4,500.00$22,500.00
Site Signage1EA$5,000.00$5,000.00
Sub-Total $53,000.00
Fencing
8' High Aluminum Fence at Perimeter650LF$28.00$18,200.00
8' x 30" Sq. Pilasters at Aluminum Fence14EA$4,500.00$63,000.00
Sub-Total $81,200.00
Landscape
Landscaping (trees, shrubs & groundcover)43,000SF$5.00$215,000.00
Sub-Total $215,000.00
Irrigation System
Irrigation System43,000SF$0.75$32,250.00
Sub-Total $32,250.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Arcadia Community Center
Site Lighting
Parking Lot Lights20EA$4,500.00$90,000.00
Walkway Lights8EA$2,500.00$20,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $118,000.00
Architectural - Community Center
LED Lighting Within Facilities1Allow$98,000.00$98,000.00
Solatube Fixtures Within Facility1Allow$90,000.00$90,000.00
Audio Visual Upgrades1Allow$20,000.00$20,000.00
Kitchen Equipment - Warming Ovens1Allow$10,000.00$10,000.00
Kitchen Equipment - Walk-In Ref. / Freez.1Allow$15,000.00$15,000.00
Kitchen Equipment - Dishwasher1Allow$8,000.00$8,000.00
Kitchen Equipment - Ice Maker1Allow$3,000.00$3,000.00
Flooring/Carpet1Allow$52,000.00$52,000.00
Upgrade Lobby Funiture1Allow$4,500.00$4,500.00
Upgrade Center Chairs1Allow$50,000.00$50,000.00
Sub-Total $350,500.00
Sub Total $1,895,950.00
10% Contingency $189,595.00
Construction Total
$2,085,545.00
8% - 10% Consulting Fees208,554.50
5% City Management Fees104,277.25
Grand Total2,398,376.75
Average Cost Per Acre
Development Acreage
5
Estimated Development Cost$2,398,376.75
$479,675.35
Cost per Acre
3/6/2017
Preliminary Opinion of Construction Costs
For
Arcadia Recreation and Community Services Department
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$10,000.00$10,000.00
Construction Cost)
Sub-Total $10,000.00
Demolition
Miscellaneous Debris1Allow$5,000.00$5,000.00
Sub-Total $5,000.00
Earthwork
Grading & Drainage1Allow$5,000.00$5,000.00
Sub-Total $5,000.00
Site Hardscape
3,450LF$6.00$20,700.00
Asphalt Paving at Parking Lot
4,900SF$22.00$107,800.00
Porous Pavers at Parking Stalls
Sub-Total $128,500.00
Architectural - Recreation and Community Services
LED Lighting Within Facilities1Allow$20,000.00$20,000.00
$22,000.00
Solatube Fixtures Within Facility1Allow$22,000.00
Audio Visual Upgrades1Allow$5,000.00$5,000.00
Work Room / Break Room Addition1Allow$75,000.00$75,000.00
Sub-Total $122,000.00
Site Furnishings
Trash Receptacles2EA$1,500.00$3,000.00
Bench3EA$3,500.00$10,500.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table1EA$4,500.00$4,500.00
Site Signage1EA$5,000.00$5,000.00
Sub-Total $24,500.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Arcadia Recreation and Community Services Department
Sub Total $295,000.00
10% Contingency $29,500.00
Construction Total
$324,500.00
8% - 10% Consulting Fees32,450.00
5% City Management Fees16,225.00
Grand Total373,175.00
Average Cost Per Acre
Development Acreage
1
Estimated Development Cost$373,175.00
$373,175.00
Cost per Acre
3/6/2017
Preliminary Opinion of Construction Costs
For
Bicentennial Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$30,000.00$30,000.00
Construction Cost)
Sub-Total $30,000.00
Demolition
Miscellaneous Debris1Allow$15,750.00$15,750.00
Sub-Total $15,750.00
Earthwork
Grading & Drainage1Allow$15,750.00$15,750.00
Infiltration Swale1Allow$9,500.00$9,500.00
Sub-Total $25,250.00
Site Hardscape
4" Concrete Paving3,834SF$6.50$24,921.00
4" Enhanced Concrete Paving1,310SF$9.00$11,790.00
3" D.G. Paving1,270SF$5.50$6,985.00
Sub-Total $43,696.00
Tennis Courts
20' High C.L.F. (Paint Black)482LF$18.00$8,676.00
8' Long Players Bench2EA$1,500.00$3,000.00
Trash Receptacles2EA$1,500.00$3,000.00
Tennis Court Lights (single)4EA$3,500.00$14,000.00
Tennis Court Lights (double)2EA$4,500.00$9,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Resurface Tennis Courts2EA$7,000.00$14,000.00
Sub-Total $59,676.00
Site Furnishings
Trash Receptacles6EA$1,500.00$9,000.00
Bench6EA$3,500.00$21,000.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table2EA$4,500.00$9,000.00
B.B.Q. Units Small2EA$1,500.00$3,000.00
B.B.Q. Ash Urn1EA$3,500.00$3,500.00
Drinking Fountain and Sump1EA$6,000.00$6,000.00
Site Signage1EA$5,000.00$5,000.00
Shade Shelters (24' x 24')1EA$50,000.00$50,000.00
2-5 Year Play Equipment1Allow$60,000.00$60,000.00
5-12 Year Play Equipment1Allow$135,000.00$135,000.00
Play Area Surfacing (Rubber)3,051SF$13.50$41,188.50
Sub-Total $344,188.50
3/6/2017
Preliminary Opinion of Construction Costs
For
Bicentennial Park
Fencing
4' High Aluminum Fence at Perimeter240LF$14.00$3,360.00
4' x 30" Sq. Pilasters at Aluminum Fence22EA$2,250.00$49,500.00
Sub-Total $52,860.00
Landscape
Landscaping (trees, shrubs & groundcover)4,835SF$5.00$24,175.00
Sod 2,143SF$0.50$1,071.50
Sub-Total $25,246.50
Irrigation System
Irrigation System6,978SF$0.75$5,233.50
Sub-Total $5,233.50
Site Lighting
Walkway Lights7EA$2,500.00$17,500.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $25,500.00
Sub Total $597,400.50
10% Contingency $59,740.05
Construction Total
$657,140.55
8% - 10% Consulting Fees65,714.06
5% City Management Fees32,857.03
Grand Total755,711.63
Average Cost Per Acre
Development Acreage
0.63
Estimated Development Cost$755,711.63
Cost per Acre$1,199,542.27
3/6/2017
Preliminary Opinion of Construction Costs
For
Bonita Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$168,000.00$168,000.00
Construction Cost)
Sub-Total $168,000.00
Demolition
Miscellaneous Debris1Allow$85,000.00$85,000.00
Sub-Total $85,000.00
Earthwork
Grading & Drainage1Allow$85,000.00$85,000.00
Infiltration Swale1Allow$35,000.00$35,000.00
Sub-Total $120,000.00
Utilities
6" Sewer Line50LF$50.00$2,500.00
Sewer Cleanouts1EA$600.00$600.00
Sewer Manhole1EA$2,500.00$2,500.00
2" Domestic Water Line50LF$12.00$600.00
2" Domestic Water Backflow Preventer1EA$9,000.00$9,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $42,600.00
Site Hardscape
4" Concrete Paving5,104SF$6.50$33,176.00
4" Enhanced Concrete Paving10,229SF$9.00$92,061.00
3" D.G. Paving5,124SF$5.50$28,182.00
5,163LF$6.00$30,978.00
Asphalt Paving at Parking Lot
2,182SF$22.00$48,004.00
Porous Pavers at Parking Stalls
500LF$21.00$10,500.00
6" Parking Lot Curb
10,973SF$6.00$65,838.00
Resurface Skate Park
Sub-Total $308,739.00
Architectural
Concession / Restroom Facility at Baseball
743SF$150.00$111,450.00
Field
Storage Bin3EA$5,000.00$15,000.00
Trash Enclosures w/ Lattice Roof1EA$15,000.00$15,000.00
Sub-Total $141,450.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Bonita Park
Baseball Field
Synthetic Turf (Organic) w/ Shock Pad85,659SF$13.50$1,156,396.50
10' High C.L.F. at Field #1782LF$21.00$16,422.00
8' H. x 5' W. C.L.Gates10EA$1,500.00$15,000.00
4' High Recycled Wood Backstop60LF$100.00$6,000.00
30' High Netting at Field #1 Backstop60LF$300.00$18,000.00
4' High Removable Fence320LF$15.00$4,800.00
21' Long Player Bench2EA$2,500.00$5,000.00
Bat Rack2EA$1,200.00$2,400.00
Batting Cages2EA$35,000.00$70,000.00
7 Row x 21' Long Bleacher w/ Canopy4EA$18,000.00$72,000.00
3 Row x 21' Long Bleacher w/ Canopy1EA$7,500.00$7,500.00
Scoreboard 1EA$15,000.00$15,000.00
Musco Sports Field Lights (single)8EA$25,000.00$200,000.00
Electrical Gear and Pad1EA$15,000.00$15,000.00
Sub-Total $1,603,518.50
Site Furnishings
Trash Receptacles26EA$1,500.00$39,000.00
Bench10EA$3,500.00$35,000.00
Bike Rack3EA$1,500.00$4,500.00
Picnic Table8EA$4,500.00$36,000.00
B.B.Q. Units Small2EA$1,500.00$3,000.00
B.B.Q. Ash Urns1EA$3,500.00$3,500.00
Drinking Fountain and Sump3EA$6,000.00$18,000.00
Site Signage2EA$5,000.00$10,000.00
Shade Shelters (16' x 19')1EA$50,000.00$50,000.00
2-5 Year Play Equipment1Allow$45,000.00$45,000.00
5-12 Year Play Equipment1Allow$180,000.00$180,000.00
Play Area Surfacing (Rubber)2,621SF$13.50$35,383.50
Flag Pole1EA$6,500.00$6,500.00
Sub-Total $465,883.50
Fencing
8' High Aluminum Fence at Perimeter1,777LF$28.00$49,756.00
8' x 30" Sq. Pilasters at Aluminum Fence90EA$4,500.00$405,000.00
8' H x 5' W. Aluminum Gates6EA$2,500.00$15,000.00
Sub-Total $469,756.00
Landscape
Landscaping (trees, shrubs & groundcover)21,663SF$5.00$108,315.00
Sod 6,384SF$0.50$3,192.00
Sub-Total $111,507.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Bonita Park
Irrigation System
Irrigation System28,047SF$0.75$21,035.25
Sub-Total $21,035.25
Site Lighting
Parking Lot Lights2EA$4,500.00$9,000.00
Walkway Lights12EA$2,500.00$30,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $47,000.00
Sub Total $3,584,489.25
10% Contingency $358,448.93
Construction Total $3,942,938.18
8% - 10% Consulting Fees394,293.82
5% City Management Fees197,146.91
Grand Total4,534,378.90
Average Cost Per Acre
Development Acreage
3.38
Estimated Development Cost$4,534,378.90
Cost per Acre$1,341,532.22
3/6/2017
Preliminary Opinion of Construction Costs
For
Camino Grove Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$67,000.00$67,000.00
Construction Cost)
Sub-Total $67,000.00
Demolition
Miscellaneous Debris1Allow$45,000.00$45,000.00
Sub-Total $45,000.00
Earthwork
Grading & Drainage1Allow$45,000.00$45,000.00
Infiltration Swale1Allow$15,500.00$15,500.00
Sub-Total $60,500.00
Site Hardscape
4" Concrete Paving9,559SF$6.50$62,133.50
4" Enhanced Concrete Paving3,660SF$9.00$32,940.00
6" Concrete Mow Curb75SF$7.00$525.00
155LF$220.00$34,100.00
18" High Seat Walls
3" D.G. Paving1,416SF$5.50$7,788.00
5,493LF$6.00$32,958.00
Asphalt Paving at Parking Lot
1,934SF$22.00$42,548.00
Porous Pavers at Parking Stalls
500LF$21.00$10,500.00
6" Parking Lot Curb
12,600SF$12.00$151,200.00
6" Post Tension Conc. @ Basketball Ct.
3,660SF$12.00$43,920.00
6" Post Tension Conc. @ Handball Ct.
Sub-Total $418,612.50
Tennis Courts
20' High C.L.F. (Paint Black)585LF$18.00$10,530.00
8' Long Players Bench6EA$1,500.00$9,000.00
Trash Receptacles6EA$1,500.00$9,000.00
Tennis Court Lights (single)4EA$3,500.00$14,000.00
Tennis Court Lights (double)4EA$4,500.00$18,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $68,530.00
Softball Field
10' High C.L.F. at Field #1590LF$21.00$12,390.00
8' H. x 5' W. C.L.Gates6EA$1,500.00$9,000.00
4' High Recycled Wood Backstop130LF$100.00$13,000.00
30' High Netting at Field #1 Backstop130LF$300.00$39,000.00
21' Long Player Bench2EA$2,500.00$5,000.00
Bat Rack2EA$1,200.00$2,400.00
7 Row x 21' Long Bleacher w/ Canopy3EA$18,000.00$54,000.00
Sub-Total $134,790.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Camino Grove Park
Site Furnishings
Trash Receptacles7EA$1,500.00$10,500.00
Players Bench @ Basketball Courts11EA$3,500.00$38,500.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table2EA$4,500.00$9,000.00
B.B.Q. Units Small2EA$1,500.00$3,000.00
B.B.Q. Ash Urns1EA$3,500.00$3,500.00
Drinking Fountain and Sump4EA$6,000.00$24,000.00
Site Signage2EA$5,000.00$10,000.00
Shade Shelters (24' x 24')1EA$50,000.00$50,000.00
2-5 Year Play Equipment1Allow$80,000.00$80,000.00
5-12 Year Play Equipment1Allow$80,000.00$80,000.00
Play Area Surfacing (Rubber)2,964SF$13.50$40,014.00
Flag Pole1EA$6,500.00$6,500.00
Basketball Back Boards6EA$4,500.00$27,000.00
12' High P.I.P Concrete Handball Wall3EA$15,000.00$45,000.00
Sub-Total $428,514.00
Fencing
8' High Aluminum Fence at Perimeter300LF$28.00$8,400.00
8' x 30" Sq. Pilasters at Aluminum Fence10EA$4,500.00$45,000.00
8' H x 5' W. Aluminum Gates (Ped.)2EA$2,500.00$5,000.00
8' H x 10' W. Aluminum Gates (Veh.)2EA$5,000.00$10,000.00
Resurface Tennis Courts3EA$7,000.00$21,000.00
Sub-Total $89,400.00
Landscape
Landscaping (trees, shrubs & groundcover)12,721SF$5.00$63,605.00
Sub-Total $63,605.00
Irrigation System
Irrigation System12,721SF$0.75$9,540.75
Sub-Total $9,540.75
Site Lighting
Parking Lot Lights4EA$4,500.00$18,000.00
Walkway Lights6EA$2,500.00$15,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $41,000.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Camino Grove Park
Sub Total $1,426,492.25
10% Contingency $142,649.23
Construction Total
$1,569,141.48
8% - 10% Consulting Fees156,914.15
5% City Management Fees78,457.07
Grand Total1,804,512.70
Average Cost Per Acre
Development Acreage
1.8
Estimated Development Cost$1,804,512.70
$1,002,507.05
Cost per Acre
3/6/2017
Preliminary Opinion of Construction Costs
For
Civic Center - City Hall Lawn
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$4,000.00$4,000.00
Construction Cost)
Sub-Total $4,000.00
Demolition
Miscellaneous Debris1Allow$5,000.00$2,500.00
Sub-Total $2,500.00
Earthwork
Grading & Drainage1Allow$5,000.00$2,500.00
Sub-Total $2,500.00
Utilities
Electrical Conduit to Stage1EA$5,000.00$5,000.00
Sub-Total $5,000.00
Site Hardscape
4" Enhanced Concrete Paving2,080SF$9.00$18,720.00
90LF$220.00$19,800.00
18" High Seat Walls
280SF$12.00$3,360.00
Concrete Ramp
120LF$18.00$2,160.00
12" Riser / Step
Sub-Total $44,040.00
Site Furnishings
Arbor Structure at Stage1EA$15,000.00$15,000.00
Trash Receptacles19EA$1,500.00$28,500.00
Bike Rack1EA$1,500.00$1,500.00
Drinking Fountain and Sump1EA$6,000.00$6,000.00
Site Signage2EA$5,000.00$10,000.00
Flag Pole3EA$6,500.00$19,500.00
Bench27EA$3,500.00$94,500.00
Sub-Total $175,000.00
Fencing
42" High Guardrail / Handrail46LF$28.00$1,288.00
Sub-Total $1,288.00
Landscape
Sod - Renovation1Allow$2,500.00$2,500.00
Sub-Total $2,500.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Civic Center - City Hall Lawn
Irrigation System
Irrigation System - Renovation1Allow$2,500.00$2,500.00
Sub-Total $2,500.00
Sub Total $239,328.00
10% Contingency $23,932.80
Construction Total
$263,260.80
8% - 10% Consulting Fees26,326.08
5% City Management Fees13,163.04
Grand Total302,749.92
3/6/2017
Preliminary Opinion of Construction Costs
For
Civic Center Soccer Field - Athletic Field and Parking Lot
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$80,000.00$80,000.00
Construction Cost)
Sub-Total $80,000.00
Demolition
$100,000.00
Miscellaneous Debris1Allow$100,000.00
Sub-Total $100,000.00
Site Hardscape
39,690SF$6.00$238,140.00
Asphalt Paving at Parking Lot
28,844SF$22.00$634,568.00
Porous Pavers at Parking Stalls
Sub-Total $872,708.00
Sports Filed
Replace Rubber Infill w/ Natural Infill1EA$250,000.00$250,000.00
Sub-Total $250,000.00
Electrical
Replace Parking Lot Lights W/ LED30EA$2,500.00$75,000.00
Replace Musco Sports Field Lights W/ LED
4EA$15,000.00$60,000.00
Fixtures
$250,000.00
Solar Panels in Parking Lot5EA$50,000.00
Sub-Total $385,000.00
Sub Total $1,607,708.00
10% Contingency $160,770.80
Construction Total
$1,768,478.80
8% - 10% Consulting Fees176,847.88
5% City Management Fees88,423.94
Grand Total2,033,750.62
7/19/2017
Preliminary Opinion of Construction Costs
For
Eisenhower Memorial Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$230,000.00$230,000.00
Construction Cost)
Sub-Total $230,000.00
Demolition
Miscellaneous Debris1Allow$110,000.00$110,000.00
Sub-Total $110,000.00
Earthwork
Grading & Drainage1Allow$110,000.00$110,000.00
Infiltration Swale1Allow$15,000.00$15,000.00
Infiltration Swale Head Wall5EA$4,500.00$22,500.00
Sub-Total $147,500.00
Utilities
6" Sewer Line300LF$50.00$15,000.00
Sewer Cleanouts3EA$600.00$1,800.00
Sewer Manhole1EA$2,500.00$2,500.00
2" Domestic Water Line300LF$12.00$3,600.00
2" Domestic Water Backflow Preventer1EA$9,000.00$9,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
8" Fire Water Line300LF$95.00$28,500.00
Fire Hydrant1EA$2,500.00$2,500.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $90,300.00
Site Hardscape
4" Concrete Paving3,616SF$6.50$23,504.00
4" Enhanced Concrete Paving19,326SF$9.00$173,934.00
375LF$220.00$82,500.00
18" High Seat Walls
3" D.G. Paving17,638SF$5.50$97,009.00
15,731LF$6.00$94,386.00
Asphalt Paving at Parking Lot
3,672SF$22.00$80,784.00
Porous Pavers at Parking Stalls
1,200LF$21.00$25,200.00
6" Parking Lot Curb
Sub-Total $577,317.00
Architectural
Restroom Facility at Tot-Lot743SF$150.00$111,450.00
Concession / Restroom Facility at Baseball
653SF$150.00$97,950.00
Field
Storage Bin1EA$5,000.00$5,000.00
Trash Enclosures w/ Lattice Roof1EA$15,000.00$15,000.00
Sub-Total $229,400.00
7/19/2017
Preliminary Opinion of Construction Costs
For
Eisenhower Memorial Park
Baseball Field
Synthetic Turf (Organic) w/ Shock Pad86,983SF$13.50$1,174,270.50
10' High C.L.F. at Field #1800LF$21.00$16,800.00
10' High C.L.F. at Field #280LF$21.00$1,680.00
10' High C.L.F. at Filed #380LF$21.00$1,680.00
8' H. x 5' W. C.L.Gates10EA$1,500.00$15,000.00
4' High Recycled Wood Backstop60LF$100.00$6,000.00
30' High Netting at Field #1 Backstop150LF$300.00$45,000.00
30' High Netting at Field #1 Outfield100LF$300.00$30,000.00
4' High Removable Fence300LF$15.00$4,500.00
21' Long Player Bench6EA$2,500.00$15,000.00
Bat Rack6EA$1,200.00$7,200.00
Batting Cages2EA$35,000.00$70,000.00
7 Row x 21' Long Bleacher w/ Canopy4EA$18,000.00$72,000.00
3 Row x 21' Long Bleacher w/ Canopy4EA$7,500.00$30,000.00
Scoreboard 1EA$15,000.00$15,000.00
Musco Sports Field Lights (single)11EA$25,000.00$275,000.00
Electrical Gear and Pad1EA$15,000.00$15,000.00
Sub-Total $1,794,130.50
Site Furnishings
Trash Receptacles16EA$1,500.00$24,000.00
Bench4EA$3,500.00$14,000.00
Bike Rack2EA$1,500.00$3,000.00
Picnic Table16EA$4,500.00$72,000.00
B.B.Q. Units Small10EA$1,500.00$15,000.00
B.B.Q. Units Large10EA$3,500.00$35,000.00
Drinking Fountain and Sump3EA$6,000.00$18,000.00
Site Signage2EA$5,000.00$10,000.00
Shade Shelters (32' Octagon)3EA$64,000.00$192,000.00
2-5 Year Play Equipment1Allow$150,000.00$150,000.00
5-12 Year Play Equipment1Allow$150,000.00$150,000.00
Par Course Equipment1Allow$57,000.00$57,000.00
Play Area Surfacing (Rubber)7,792SF$13.50$105,192.00
Bridge at Wash (Pedestrian)1EA$35,000.00$35,000.00
Flag Pole1EA$6,500.00$6,500.00
Sub-Total $886,692.00
Fencing
8' High Aluminum Fence at Perimeter2,014LF$28.00$56,392.00
8' x 30" Sq. Pilasters at Aluminum Fence45EA$4,500.00$202,500.00
8' High Block Wall at Property Line360LF$30.00$10,800.00
8' x 30" Sq. Pilasters at Block Wall8EA$4,500.00$36,000.00
Sub-Total $305,692.00
Landscape
Landscaping (trees, shrubs & groundcover)22,416SF$5.00$112,080.00
Sod 26,291SF$0.50$13,145.50
Sub-Total $125,225.50
7/19/2017
Preliminary Opinion of Construction Costs
For
Eisenhower Memorial Park
Irrigation System
Irrigation System48,707SF$0.75$36,530.25
Sub-Total $36,530.25
Site Lighting
Parking Lot Lights6EA$4,500.00$27,000.00
Walkway Lights42EA$2,500.00$105,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $140,000.00
Sub Total $4,672,787.25
10% Contingency $467,278.73
Construction Total $5,140,065.98
8% - 10% Consulting Fees514,006.60
5% City Management Fees257,003.30
Grand Total5,911,075.87
Average Cost Per Acre
Development Acreage
4.39
Estimated Development Cost$5,911,075.87
Cost per Acre$1,346,486.53
3/6/2017
Preliminary Opinion of Construction Costs
For
Eisenhower Dog Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$42,000.00$42,000.00
Construction Cost)
Sub-Total $42,000.00
Demolition
Miscellaneous Debris1Allow$25,000.00$25,000.00
Sub-Total $25,000.00
Earthwork
Grading & Drainage1Allow$25,000.00$25,000.00
Sub-Total $25,000.00
Utilities
3/4" Domestic Water Line to D.F.300LF$12.00$3,600.00
3/4" Domestic Water Backflow Preventer1EA$3,500.00$3,500.00
3/4" Domestic Water Gate Valve1EA$400.00$400.00
2" Irrigation Backflow Preventer1EA$9,000.00$9,000.00
Sub-Total $16,500.00
Site Hardscape
4" Concrete Paving1,800SF$6.50$11,700.00
4" Enhanced Concrete Paving4,685SF$9.00$42,165.00
6" Concrete Mow Curb1,200SF$7.00$8,400.00
3" D.G. Paving15,273SF$5.50$84,001.50
Sub-Total $146,266.50
Site Furnishings
Trash Receptacles8EA$1,500.00$12,000.00
Bench10EA$3,500.00$35,000.00
Bike Rack2EA$1,500.00$3,000.00
Picnic Table8EA$4,500.00$36,000.00
Drinking Fountain and Sump6EA$6,000.00$36,000.00
Site Signage1EA$5,000.00$5,000.00
Shade Shelters (32' Octagon)2EA$64,000.00$128,000.00
Small Dog Park Play Equipment1Allow$12,000.00$12,000.00
Large Dog Park Play Equipment1Allow$12,000.00$12,000.00
Dog Bag Dispensers8EA$1,000.00$8,000.00
Sub-Total $287,000.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Eisenhower Dog Park
Fencing
6' High Aluminum Fence at Dog Park337LF$28.00$9,436.00
6' H x 5' W. Aluminum Gates at Dog Park4EA$2,500.00$10,000.00
6' x 30" Sq. Pilasters at Dog Park8$4,500.00$36,000.00
4' High Aluminum Fence at Dog Park264LF$14.00$3,696.00
4' H x 5' W. Aluminum Gates at Dog Park4EA$1,250.00$5,000.00
4' x 30" Sq. Pilasters at Dog Park6$2,500.00$15,000.00
8' High Aluminum Fence at Perimeter279LF$28.00$7,812.00
8' x 30" Sq. Pilasters at Aluminum Fence10EA$4,500.00$45,000.00
8' High Block Wall at Property Line385LF$30.00$11,550.00
8' x 30" Sq. Pilasters at Block Wall10EA$4,500.00$45,000.00
Sub-Total $188,494.00
Landscape
Landscaping (trees, shrubs & groundcover)11,230SF$5.00$56,150.00
Sod 15,618SF$0.50$7,809.00
Sub-Total $63,959.00
Irrigation System
Irrigation System26,848SF$0.75$20,136.00
Sub-Total $20,136.00
Site Lighting
Walkway Lights21EA$2,500.00$52,500.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $60,500.00
Sub Total $832,855.50
10% Contingency $83,285.55
Construction Total $916,141.05
8% - 10% Consulting Fees91,614.11
5% City Management Fees45,807.05
Grand Total1,053,562.21
Average Cost Per Acre
Development Acreage
1
Estimated Development Cost$1,053,562.21
$1,053,562.21
Cost per Acre
3/6/2017
Preliminary Opinion of Construction Costs
For
Fairview Avenue Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$42,000.00$42,000.00
Construction Cost)
Sub-Total $42,000.00
Demolition
Miscellaneous Debris1Allow$23,750.00$23,750.00
Sub-Total $23,750.00
Earthwork
Grading & Drainage1Allow$23,750.00$23,750.00
Infiltration Swale1Allow$13,000.00$13,000.00
Sub-Total $36,750.00
Site Hardscape
4" Concrete Paving2,358SF$6.50$15,327.00
4" Enhanced Concrete Paving3,981SF$9.00$35,829.00
6" Concrete Mow Curb465SF$7.00$3,255.00
Sub-Total $54,411.00
Site Furnishings
Trash Receptacles15EA$1,500.00$22,500.00
Bench10EA$3,500.00$35,000.00
Bike Rack3EA$1,500.00$4,500.00
Picnic Table8EA$4,500.00$36,000.00
B.B.Q. Units Small9EA$1,500.00$13,500.00
B.B.Q. Ash Urns3EA$3,500.00$10,500.00
Drinking Fountain and Sump5EA$6,000.00$30,000.00
Site Signage2EA$5,000.00$10,000.00
Shade Arbor 40' x 8'2EA$15,000.00$30,000.00
5-12 Year Play Equipment1Allow$145,000.00$145,000.00
Play Area Surfacing (Rubber)2,700Allow$13.50$36,450.00
Small Dog Park Play Equipment1Allow$12,000.00$12,000.00
Large Dog Park Play Equipment1Allow$12,000.00$12,000.00
Shade Structure At Dog Park Bench6EA$2,500.00$15,000.00
Dog Bag Dispensers4EA$1,000.00$4,000.00
Sub-Total $397,450.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Fairview Avenue Park
Fencing
8' High Aluminum Fence at Dog Park325LF$28.00$9,100.00
8' H x 5' W. Aluminum Gates at Dog Park4EA$2,500.00$10,000.00
8' x 30" Sq. Pilasters at Block Wall10EA$4,500.00$45,000.00
4' High Aluminum Fence at Dog Park275LF$14.00$3,850.00
4' H x 5' W. Aluminum Gates at Dog Park4EA$1,250.00$5,000.00
4' x 30" Sq. Pilasters at Block Wall9EA$2,250.00$20,250.00
8' High Block Wall at Property Line800LF$30.00$24,000.00
8' x 30" Sq. Pilasters at Block Wall20EA$4,500.00$90,000.00
Sub-Total $207,200.00
Landscape
Landscaping (trees, shrubs & groundcover)12,856SF$5.00$64,280.00
Sod 15,339SF$0.50$7,669.50
Sub-Total $71,949.50
Irrigation System
Irrigation System28,195SF$0.75$21,146.25
Sub-Total $21,146.25
Site Lighting
Walkway Lights7EA$2,500.00$17,500.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $25,500.00
Sub Total $880,156.75
10% Contingency $88,015.68
Construction Total $968,172.43
8% - 10% Consulting Fees96,817.24
5% City Management Fees48,408.62
Grand Total1,113,398.29
Average Cost Per Acre
Development Acreage
0.95
Estimated Development Cost$1,113,398.29
$1,171,998.20
Cost per Acre
3/6/2017
Preliminary Opinion of Construction Costs
For
Forest Avenue Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$12,000.00$12,000.00
Construction Cost)
Sub-Total $12,000.00
Demolition
Miscellaneous Debris1Allow$6,500.00$6,500.00
Sub-Total $6,500.00
Earthwork
Grading & Drainage1Allow$6,500.00$6,500.00
Infiltration Swale1Allow$7,500.00
Sub-Total $6,500.00
Site Hardscape
4" Enhanced Concrete Paving2,403SF$9.00$21,627.00
6" Concrete Mow Curb226SF$7.00$1,582.00
Sub-Total $23,209.00
Site Furnishings
Trash Receptacles3EA$1,500.00$4,500.00
Bench3EA$3,500.00$10,500.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table6EA$4,500.00$27,000.00
B.B.Q. Units Small2EA$1,500.00$3,000.00
B.B.Q. Ash Urns2EA$3,500.00$7,000.00
Drinking Fountain and Sump1EA$6,000.00$6,000.00
Site Signage1EA$5,000.00$5,000.00
Sub-Total $64,500.00
Fencing
8' High Aluminum Fence at Perimeter345LF$28.00$9,660.00
8' x 30" Sq. Pilasters at Aluminum Fence9EA$4,500.00$40,500.00
Sub-Total $50,160.00
Landscape
Landscaping (trees, shrubs & groundcover)9,582SF$5.00$47,910.00
Sod 3,577SF$0.50$1,788.50
Sub-Total $49,698.50
3/6/2017
Preliminary Opinion of Construction Costs
For
Forest Avenue Park
Irrigation System
Irrigation System13,159SF$0.75$9,869.25
Sub-Total $9,869.25
Site Lighting
Walkway Lights3EA$2,500.00$7,500.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $15,500.00
Sub Total $237,936.75
10% Contingency $23,793.68
Construction Total
$261,730.43
8% - 10% Consulting Fees26,173.04
5% City Management Fees13,086.52
Grand Total300,989.99
Average Cost Per Acre
Development Acreage
0.63
Estimated Development Cost$300,989.99
Cost per Acre$477,761.89
3/6/2017
Preliminary Opinion of Construction Costs
For
Hugo Reid Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$141,000.00$141,000.00
Construction Cost)
Sub-Total $141,000.00
Demolition
Miscellaneous Debris1Allow$110,000.00$110,000.00
Sub-Total $110,000.00
Earthwork
Grading & Drainage1Allow$110,000.00$110,000.00
Infiltration Swale1Allow$22,000.00$22,000.00
Sub-Total $132,000.00
Utilities
6" Sewer Line100LF$50.00$5,000.00
Sewer Cleanouts2EA$600.00$1,200.00
Sewer Manhole1EA$2,500.00$2,500.00
2" Domestic Water Line100LF$12.00$1,200.00
2" Domestic Water Backflow Preventer1EA$9,000.00$9,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $46,300.00
Site Hardscape
4" Concrete Paving10,329SF$6.50$67,138.50
4" Enhanced Concrete Paving8,726SF$9.00$78,534.00
6" Concrete Mow Curb362SF$7.00$2,534.00
320LF$220.00$70,400.00
18" High Seat Walls
10,618LF$6.00$63,708.00
Asphalt Paving at Parking Lot
8,629SF$22.00$189,838.00
Porous Pavers at Parking Stalls
1,134LF$21.00$23,814.00
6" Parking Lot Curb
Sub-Total $495,966.50
Architectural
Concession / Restroom Facility at Baseball
743SF$150.00$111,450.00
Field
Sub-Total $111,450.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Hugo Reid Park
Tennis Courts
20' High C.L.F. (Paint Black)751LF$18.00$13,518.00
4SF$1,500.00$6,000.00
8' H. x 5' W. C.L. Gates
8' Long Players Bench6EA$1,500.00$9,000.00
Tennis Court Net3EA$3,500.00$10,500.00
Trash Receptacles3EA$1,500.00$4,500.00
Tennis Court Lights (single)8EA$3,500.00$28,000.00
Tennis Court Lights (double)2EA$4,500.00$9,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Resurface Tennis Courts3EA$7,000.00$21,000.00
Sub-Total $109,518.00
Baseball Field
Synthetic Turf (Organic) w/ Shock Pad40,000SF$13.50$540,000.00
10' High C.L.F. at Field #1900LF$21.00$18,900.00
8' H. x 5' W. C.L.Gates14EA$1,500.00$21,000.00
4' High Recycled Wood Backstop60LF$100.00$6,000.00
30' High Netting at Field #1 Backstop60LF$300.00$18,000.00
20' High Netting at Field #1 Outfield355LF$200.00$71,000.00
21' Long Player Bench2EA$2,500.00$5,000.00
Bat Rack2EA$1,200.00$2,400.00
Batting Cage2EA$35,000.00$70,000.00
7 Row x 21' Long Bleacher w/ Canopy4EA$18,000.00$72,000.00
3 Row x 21' Long Bleacher w/ Canopy1EA$7,500.00$7,500.00
Scoreboard 1EA$15,000.00$15,000.00
Musco Sports Field Lights (single)6EA$25,000.00$150,000.00
Electrical Gear and Pad1EA$15,000.00$15,000.00
Sub-Total $1,011,800.00
Site Furnishings
Trash Receptacles8EA$1,500.00$12,000.00
Bench5EA$3,500.00$17,500.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table6EA$4,500.00$27,000.00
B.B.Q. Units Small4EA$1,500.00$6,000.00
B.B.Q. Ash Urns4EA$3,500.00$14,000.00
Drinking Fountain and Sump4EA$6,000.00$24,000.00
Site Signage2EA$5,000.00$10,000.00
Shade Shelters (32' Octagon)1EA$64,000.00$64,000.00
2-5 Year Play Equipment1Allow$35,000.00$35,000.00
5-12 Year Play Equipment1Allow$108,000.00$108,000.00
Play Area Surfacing (Rubber)5,078Allow$13.50$68,553.00
Flag Pole1EA$6,500.00$6,500.00
Sub-Total $394,053.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Hugo Reid Park
Fencing
4' High Aluminum Fence at Tot-Lot85LF$14.00$1,190.00
4' x 30" Sq. Pilasters at Aluminum Fence4EA$2,250.00$9,000.00
8' High Aluminum Fence at Perimeter250LF$28.00$7,000.00
8' x 30" Sq. Pilasters at Aluminum Fence12EA$4,500.00$54,000.00
8' H x 5' W. Aluminum Gates4EA$2,500.00$10,000.00
8' High Block Wall at Property Line750LF$30.00$22,500.00
8' x 30" Sq. Pilasters at Block Wall18EA$4,500.00$81,000.00
Sub-Total $184,690.00
Landscape
Landscaping (trees, shrubs & groundcover)28,000SF$5.00$140,000.00
Sod 17,500SF$0.50$8,750.00
Sub-Total $148,750.00
Irrigation System
Irrigation System45,500SF$0.75$34,125.00
Sub-Total $34,125.00
Site Lighting
Parking Lot Lights5EA$4,500.00$22,500.00
Walkway Lights13EA$2,500.00$32,500.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $63,000.00
Sub Total $2,982,652.50
10% Contingency $298,265.25
Construction Total
$3,280,917.75
8% - 10% Consulting Fees328,091.78
5% City Management Fees164,045.89
Grand Total3,773,055.41
Average Cost Per Acre
Development Acreage
4.67
Estimated Development Cost$3,773,055.41
$807,934.78
Cost per Acre
3/6/2017
Preliminary Opinion of Construction Costs
For
Longden Avenue Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$125,000.00$125,000.00
Construction Cost)
Sub-Total $125,000.00
Demolition
Miscellaneous Debris1Allow$72,500.00$72,500.00
Sub-Total $72,500.00
Earthwork
Grading & Drainage1Allow$72,500.00$72,500.00
Infiltration Swale1Allow$17,644.00$17,644.00
Sub-Total $72,500.00
Utilities
6" Sewer Line275LF$50.00$13,750.00
Sewer Cleanouts3EA$600.00$1,800.00
Sewer Manhole2EA$2,500.00$5,000.00
2" Domestic Water Line275LF$12.00$3,300.00
2" Domestic Water Backflow Preventer1EA$9,000.00$9,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
8" Fire Water Line275LF$95.00$26,125.00
Fire Hydrant1EA$2,500.00$2,500.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $88,875.00
Site Hardscape
4" Concrete Paving3,992SF$6.50$25,948.00
4" Enhanced Concrete Paving14,676SF$9.00$132,084.00
18,384LF$6.00$110,304.00
Asphalt Paving at Parking Lot
8,890SF$22.00$195,580.00
Porous Pavers at Parking Stalls
1,063LF$21.00$22,323.00
6" Parking Lot Curb
Sub-Total $486,239.00
Architectural
Concession / Restroom Facility at Baseball
743SF$150.00$111,450.00
Field
Storage Bin2EA$5,000.00$10,000.00
Trash Enclosures w/ Lattice Roof1EA$15,000.00$15,000.00
Sub-Total $136,450.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Longden Avenue Park
Baseball Field
Synthetic Turf (Organic) w/ Shock Pad47,753SF$13.50$644,665.50
10' High C.L.F. at Field910LF$21.00$19,110.00
8' H. x 5' W. C.L.Gates17EA$1,500.00$25,500.00
4' High Recycled Wood Backstop120LF$100.00$12,000.00
30' High Netting at Field Backstop120LF$300.00$36,000.00
30' High Netting at Field Outfield240LF$300.00$72,000.00
21' Long Player Bench2EA$2,500.00$5,000.00
Bat Rack2EA$1,200.00$2,400.00
Batting Cages2EA$35,000.00$70,000.00
5 Row x 21' Long Bleacher w/ Canopy5EA$13,000.00$65,000.00
4 Row x 21' Long Bleacher w/ Canopy1EA$10,500.00$10,500.00
3 Row x 21' Long Bleacher w/ Canopy3EA$7,500.00$22,500.00
Scoreboard 1EA$15,000.00$15,000.00
Musco Sports Field Lights (single)6EA$25,000.00$150,000.00
Electrical Gear and Pad1EA$15,000.00$15,000.00
Sub-Total $1,164,675.50
Site Furnishings
Trash Receptacles9EA$1,500.00$13,500.00
Bench5EA$3,500.00$17,500.00
Bike Rack2EA$1,500.00$3,000.00
Picnic Table5EA$4,500.00$22,500.00
Drinking Fountain and Sump3EA$6,000.00$18,000.00
Site Signage2EA$5,000.00$10,000.00
Flag Pole1EA$6,500.00$6,500.00
Sub-Total $91,000.00
Fencing
8' High Aluminum Fence at Perimeter1,320LF$28.00$36,960.00
8' x 30" Sq. Pilasters at Aluminum Fence28EA$4,500.00$126,000.00
8' H x 5' W. Aluminum Gates5EA$2,500.00$12,500.00
8' High Block Wall at Property Line700LF$30.00$21,000.00
8' x 30" Sq. Pilasters at Block Wall15EA$4,500.00$67,500.00
Sub-Total $263,960.00
Landscape
Landscaping (trees, shrubs & groundcover)8,822SF$5.00$44,110.00
Sub-Total $44,110.00
Irrigation System
Irrigation System8,822SF$0.75$6,616.50
Sub-Total $6,616.50
3/6/2017
Preliminary Opinion of Construction Costs
For
Longden Avenue Park
Site Lighting
Parking Lot Lights6EA$4,500.00$27,000.00
Walkway Lights12EA$2,500.00$30,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $65,000.00
Sub Total $2,616,926.00
10% Contingency $261,692.60
Construction Total
$2,878,618.60
8% - 10% Consulting Fees287,861.86
5% City Management Fees143,930.93
Grand Total3,310,411.39
Average Cost Per Acre
Development Acreage
2.9
Estimated Development Cost$3,310,411.39
Cost per Acre$1,141,521.17
3/6/2017
Preliminary Opinion of Construction Costs
For
Newcastle Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$108,000.00$108,000.00
Construction Cost)
Sub-Total $108,000.00
Demolition
Miscellaneous Debris1Allow$65,000.00$65,000.00
Sub-Total $65,000.00
Earthwork
Grading & Drainage1Allow$65,000.00$65,000.00
Infiltration Swale1Allow$33,366.00$33,366.00
Infiltration Headwall4EA$4,500.00$18,000.00
Sub-Total $116,366.00
Utilities
6" Sewer Line100LF$50.00$5,000.00
Sewer Cleanouts2EA$600.00$1,200.00
Sewer Manhole1EA$2,500.00$2,500.00
2" Domestic Water Line100LF$12.00$1,200.00
2" Domestic Water Backflow Preventer1EA$9,000.00$9,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
8" Fire Water Line100LF$95.00$9,500.00
Fire Hydrant1EA$2,500.00$2,500.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $58,300.00
Site Hardscape
4" Concrete Paving10,705SF$6.50$69,582.50
4" Enhanced Concrete Paving8,418SF$9.00$75,762.00
6" Concrete Mow Curb180SF$7.00$1,260.00
13,238LF$6.00$79,428.00
Asphalt Paving at Parking Lot
3,060SF$22.00$67,320.00
Porous Pavers at Parking Stalls
922LF$21.00$19,362.00
6" Parking Lot Curb
450LF$260.00$117,000.00
Retaining Wall @ Colorado Blvd
2,250SF$6.50$14,625.00
4" Concrete Paving @ Colorado Blvd
Sub-Total $444,339.50
3/6/2017
Preliminary Opinion of Construction Costs
For
Newcastle Park
Architectural
Restroom Facility at Tot-Lot653SF$150.00$97,950.00
Trash Enclosures w/ Lattice Roof1EA$15,000.00$15,000.00
Sub-Total $112,950.00
Tennis Courts / Pickel Ball Courts
20' High C.L.F. (Paint Exist. Black)518LF$18.00$9,324.00
$14,812.00
20' High C.L.F. (at Pickel Ball Courts)529LF$28.00
$129,012.00
Post Tension Pickel Ball Courts10,751SF$12.00
5SF$1,500.00$7,500.00
8' H. x 5' W. C.L. Gates
8' Long Players Bench4EA$1,500.00$6,000.00
Pickel Ball Court Net6EA$3,500.00$21,000.00
Trash Receptacles2EA$1,500.00$3,000.00
Tennis / Pickel Court Lights (single)8EA$3,500.00$28,000.00
Tennis / Pickel Court Lights (double)6EA$4,500.00$27,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Resurface Tennis Courts2EA$7,000.00$14,000.00
Sub-Total $253,648.00
Sand Volleyball Courts
Play Area Curb340SF$13.50$4,590.00
Beach Sand (12" deep)90CY$50.00$4,500.00
Volleyball Post (pair)2EA$3,500.00$7,000.00
Volleyball Court Lights (single)8EA$3,500.00$28,000.00
Volleyball Court Lights (double)6EA$4,500.00$27,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
3 Row x 21' Long Bleacher w/ Canopy2EA$7,500.00$15,000.00
Sub-Total $94,090.00
Site Furnishings
Trash Receptacles17EA$1,500.00$25,500.00
Bench10EA$3,500.00$35,000.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table13EA$4,500.00$58,500.00
B.B.Q. Units Small5EA$1,500.00$7,500.00
B.B.Q. Ash Urns5EA$3,500.00$17,500.00
Drinking Fountain and Sump5EA$6,000.00$30,000.00
Site Signage1EA$5,000.00$5,000.00
Shade Shelters (32' Octagon)1EA$64,000.00$64,000.00
Shade Shelters (20' x 30' )1EA$64,000.00$64,000.00
2-5 Year Play Equipment1Allow$75,000.00$75,000.00
5-12 Year Play Equipment1Allow$264,000.00$264,000.00
Play Area Surfacing (Rubber)5,583SF$13.50$75,370.50
Sub-Total $722,870.50
3/6/2017
Preliminary Opinion of Construction Costs
For
Newcastle Park
Fencing
8' High Aluminum Fence at Perimeter581LF$28.00$16,268.00
8' x 30" Sq. Pilasters at Aluminum Fence12EA$4,500.00$54,000.00
8' H x 5' W. Aluminum Gates2EA$2,500.00$5,000.00
8' High Block Wall at Property Line459LF$30.00$13,770.00
8' x 30" Sq. Pilasters at Block Wall10EA$4,500.00$45,000.00
Vehicle Access Gates (pair)1EA$5,000.00$5,000.00
Sub-Total $134,038.00
Landscape
Landscaping (trees, shrubs & groundcover)29,105SF$5.00$145,525.00
Sod 36,758SF$0.50$18,379.00
Sub-Total $163,904.00
Irrigation System
Irrigation System65,863SF$0.75$49,397.25
Sub-Total $49,397.25
Site Lighting
Parking Lot Lights6EA$4,500.00$27,000.00
Walkway Lights13EA$2,500.00$32,500.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $67,500.00
5
Sub Total $2,390,403.2
10% Contingency $239,040.33
Construction Total
$2,629,443.58
8% - 10% Consulting Fees262,944.36
5% City Management Fees131,472.18
Grand Total3,023,860.11
Average Cost Per Acre
Development Acreage
2.6
Estimated Development Cost$3,023,860.11
Cost per Acre$1,163,023.12
3/6/2017
Preliminary Opinion of Construction Costs
For
Orange Grove Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$76,000.00$76,000.00
Construction Cost)
Sub-Total $76,000.00
Demolition
Miscellaneous Debris1Allow$65,000.00$65,000.00
Sub-Total $65,000.00
Earthwork
Grading & Drainage1Allow$65,000.00$65,000.00
Sub-Total $65,000.00
Utilities
6" Sewer Line50LF$50.00$2,500.00
Sewer Cleanouts1EA$600.00$600.00
Sewer Manhole1EA$2,500.00$2,500.00
2" Domestic Water Line50LF$12.00$600.00
2" Domestic Water Backflow Preventer50EA$9,000.00$450,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $483,600.00
Site Hardscape
4" Concrete Paving1,510SF$6.50$9,815.00
4" Enhanced Concrete Paving1,334SF$9.00$12,006.00
21,523LF$6.00$129,138.00
Asphalt Paving at Parking Lot
1,643LF$21.00$34,503.00
6" Parking Lot Curb
Sub-Total $185,462.00
Architectural
Restroom Facility 210SF$150.00$31,500.00
Sub-Total $31,500.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Orange Grove Park
Tennis Courts
20' High C.L.F. (Black)866LF$28.00$24,248.00
8SF$1,500.00$12,000.00
8' H. x 5' W. C.L. Gates
8' Long Players Bench8EA$1,500.00$12,000.00
Tennis Court Net4EA$3,500.00$14,000.00
Trash Receptacles8EA$1,500.00$12,000.00
Tennis Court Lights (single)4EA$3,500.00$14,000.00
Tennis Court Lights (double)6EA$4,500.00$27,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Tennis Court Surfacing28,224SF$1.25$35,280.00
Running Track Surfacing10,866SF$1.25$13,582.50
Tank Field Surfacing24,929SF$1.25$31,161.25
Resurface Existing Tennis Courts5EA$7,000.00$35,000.00
Sub-Total $238,271.75
Site Furnishings
Trash Receptacles1EA$1,500.00$1,500.00
Bench1EA$3,500.00$3,500.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table4EA$4,500.00$18,000.00
Drinking Fountain and Sump1EA$6,000.00$6,000.00
Site Signage2EA$5,000.00$10,000.00
Par Course Equipment1Allow$57,000.00$57,000.00
Par Course Surfacing (Rubber)600Allow$13.50$8,100.00
3 Row x 21' Long Bleacher w/ Canopy4EA$7,500.00$30,000.00
Sub-Total $135,600.00
Fencing
8' High Aluminum Fence at Perimeter435LF$28.00$12,180.00
8' x 30" Sq. Pilasters at Aluminum Fence12EA$4,500.00$54,000.00
8' H x 10' W. Aluminum Gates2EA$2,500.00$5,000.00
4' High Aluminum Fence at Tank958LF$14.00$13,412.00
8' High Block Wall at Property Line870LF$30.00$26,100.00
8' x 30" Sq. Pilasters at Block Wall20EA$4,500.00$90,000.00
Vehicle Access Gates (pair)2EA$5,000.00$10,000.00
Sub-Total $210,692.00
Landscape
Landscaping (trees, shrubs & groundcover)15,658SF$5.00$78,290.00
Sub-Total $78,290.00
Irrigation System
Irrigation System15,658SF$0.75$11,743.50
Sub-Total $11,743.50
3/6/2017
Preliminary Opinion of Construction Costs
For
Orange Grove Park
Site Lighting
Parking Lot Lights4EA$4,500.00$18,000.00
Walkway Lights8EA$2,500.00$20,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $46,000.00
Sub Total $1,627,159.25
10% Contingency $162,715.93
Construction Total
$1,789,875.18
8% - 10% Consulting Fees178,987.52
5% City Management Fees89,493.76
Grand Total2,058,356.45
Average Cost Per Acre
Development Acreage
2.67
Estimated Development Cost$2,058,356.45
Cost per Acre$770,920.02
3/6/2017
Preliminary Opinion of Construction Costs
For
Par-3 Golf Course
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$348,000.00$348,000.00
Construction Cost)
Sub-Total $348,000.00
Demolition
Miscellaneous Debris1Allow$165,500.00$165,500.00
Sub-Total $165,500.00
Earthwork
Grading & Drainage1Allow$165,500.00$165,500.00
Infiltration Swale1Allow$17,500.00$17,500.00
Sub-Total $183,000.00
Utilities
6" Sewer Line450LF$50.00$22,500.00
Sewer Cleanouts5EA$600.00$3,000.00
Sewer Manhole1EA$2,500.00$2,500.00
2" Domestic Water Line450LF$12.00$5,400.00
2" Domestic Water Backflow Preventer1EA$9,000.00$9,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
8" Fire Water Line1,550LF$95.00$147,250.00
Fire Hydrant5EA$2,500.00$12,500.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $229,550.00
Site Hardscape
4" Concrete Paving10,084SF$6.50$65,546.00
4" Enhanced Concrete Paving12,158SF$9.00$109,422.00
622LF$220.00$136,840.00
18" High Seat Walls
86,219SF$6.00$517,314.00
Asphalt Paving at Parking Lot
18,477SF$6.00$110,862.00
Asphalt Paving at Bike Path
35,862SF$22.00$788,964.00
Porous Pavers at Parking Stalls
5,481LF$21.00$115,101.00
6" Parking Lot Curb
8EA$100.00$800.00
Concrete Wheel Stop
Sub-Total $1,844,849.00
Architectural
Club House Facility18,977SF$150.00$2,846,550.00
Trash Enclosures w/ Lattice Roof1EA$15,000.00$15,000.00
Two Level Driving Range6,000SF$150.00$900,000.00
Sub-Total $3,761,550.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Par-3 Golf Course
Site Furnishings
Trash Receptacles10EA$1,500.00$15,000.00
Bench10EA$3,500.00$35,000.00
Bike Rack2EA$1,500.00$3,000.00
Picnic Table16EA$4,500.00$72,000.00
Drinking Fountain and Sump2EA$6,000.00$12,000.00
Site Signage5EA$5,000.00$25,000.00
Water Feature1EA$30,000.00$30,000.00
Bridge at Wash1EA$500,000.00$500,000.00
Flag Pole1EA$6,500.00$6,500.00
Bicycle Rote Kiosk 1EA$4,500.00$4,500.00
Second Protable Shade Structure1Allow$75,000.00$75,000.00
Solar Canopies (36' x 88')3EA$65,000.00$195,000.00
Sub-Total $973,000.00
Fencing
8' High Aluminum Fence at Perimeter1,669LF$28.00$46,732.00
8' x 30" Sq. Pilasters at Aluminum Fence35EA$4,500.00$157,500.00
3 Rail Equestrian Fence at Bike Path1,842LF$18.00$33,156.00
8' High Block Wall at Property Line2,551LF$30.00$76,530.00
8' x 30" Sq. Pilasters at Block Wall52EA$4,500.00$234,000.00
Removable Bollards4EA$2,500.00$10,000.00
Sub-Total $547,918.00
Landscape
Landscaping (trees, shrubs & groundcover)37,834SF$5.00$189,170.00
Sod2,320SF$0.50
$1,160.00
Putting Green9,130SF$2.00
$18,260.00
Sub-Total $208,590.00
Irrigation System
Irrigation System49,284SF$0.75$36,963.00
Sub-Total $36,963.00
Site Lighting
Parking Lot Lights18EA$4,500.00$81,000.00
Walkway Lights13EA$2,500.00$32,500.00
Sports Lighting at Driving Range2EA$25,000.00$50,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $171,500.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Par-3 Golf Course
Sub Total $8,470,420.00
10% Contingency $847,042.00
Construction Total
$9,317,462.00
8% - 10% Consulting Fees931,746.20
5% City Management Fees465,873.10
Grand Total10,715,081.30
Average Cost Per Acre
Development Acreage
6.62
Estimated Development Cost$10,715,081.30
$1,618,592.34
Cost per Acre
3/6/2017
Preliminary Opinion of Construction Costs
For
Tierra Verde Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$63,000.00$63,000.00
Construction Cost)
Sub-Total $63,000.00
Demolition
Miscellaneous Debris1Allow$38,750.00$38,750.00
Sub-Total $38,750.00
Earthwork
Grading & Drainage1Allow$38,750.00$38,750.00
Infiltration Swale1Allow$16,864.00$16,864.00
Sub-Total $55,614.00
Utilities
6" Sewer Line120LF$50.00$6,000.00
Sewer Cleanouts2EA$600.00$1,200.00
Sewer Manhole1EA$2,500.00$2,500.00
2" Domestic Water Line120LF$12.00$1,440.00
2" Domestic Water Backflow Preventer1EA$9,000.00$9,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $47,540.00
Site Hardscape
4" Concrete Paving5,788SF$6.50$37,622.00
4" Enhanced Concrete Paving4,845SF$9.00$43,605.00
6" Concrete Mow Curb198SF$7.00$1,386.00
165LF$220.00$36,300.00
18" High Seat Walls
Sub-Total $118,913.00
Architectural
Restroom Facility504SF$150.00$75,600.00
Sub-Total $75,600.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Tierra Verde Park
Tennis Courts
20' High C.L.F. (Paint Exist. Black)536LF$18.00$9,648.00
8' Long Players Bench6EA$1,500.00$9,000.00
Tennis Court Net3EA$3,500.00$10,500.00
Trash Receptacles3EA$1,500.00$4,500.00
Tennis Court Lights (single)4EA$3,500.00$14,000.00
Tennis Court Lights (double)4EA$4,500.00$18,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
20' High C.L.F. (at New Court)240LF$28.00$6,720.00
Post Tension Court7,056SF$12.00$84,672.00
8' H. x 5' W. C.L. Gates2EA$1,500.00$3,000.00
Resurfase Tennis Courts2EA$7,000.00$14,000.00
Sub-Total $182,040.00
Site Furnishings
Trash Receptacles10EA$1,500.00$15,000.00
Bench10EA$3,500.00$35,000.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table9EA$4,500.00$40,500.00
B.B.Q. Units Small4EA$1,500.00$6,000.00
B.B.Q. Ash Urns4EA$3,500.00$14,000.00
Drinking Fountain and Sump2EA$6,000.00$12,000.00
Site Signage2EA$5,000.00$10,000.00
Shade Shelters (32' Octagon)1EA$64,000.00$64,000.00
Shade Shelter at Restroom 36' Half1EA$32,000.00$32,000.00
2-5 Year Play Equipment1Allow$100,000.00$100,000.00
5-12 Year Play Equipment1Allow$219,000.00$219,000.00
Play Area Surfacing (Rubber)4,765SF$13.50$64,327.50
Sub-Total $613,327.50
Fencing
4' High Aluminum Fence at Tot-Lot78LF$28.00$2,184.00
4' x 30" Sq. Pilasters at Aluminum Fence4EA$4,500.00$18,000.00
8' High Block Wall at Property Line521LF$30.00$15,630.00
8' x 30" Sq. Pilasters at Block Wall11EA$4,500.00$49,500.00
Sub-Total $85,314.00
Landscape
Landscaping (trees, shrubs & groundcover)13,323SF$5.00$66,615.00
Sod 22,969SF$0.50$11,484.50
Sub-Total $78,099.50
Irrigation System
Irrigation System36,292SF$0.75$27,219.00
Sub-Total $27,219.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Tierra Verde Park
Site Lighting
Walkway Lights9EA$2,500.00$22,500.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $30,500.00
Sub Total $1,415,917.00
10% Contingency $141,591.70
Construction Total
$1,557,508.70
8% - 10% Consulting Fees155,750.87
5% City Management Fees77,875.44
Grand Total1,791,135.01
Average Cost Per Acre
Development Acreage
1.55
Estimated Development Cost$1,791,135.01
Cost per Acre$1,155,570.97
3/6/2017
Preliminary Opinion of Construction Costs
For
Tripolis Friendship Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$24,000.00$24,000.00
Construction Cost)
Sub-Total $24,000.00
Demolition
Miscellaneous Debris1Allow$8,500.00$8,500.00
Sub-Total $8,500.00
Earthwork
Grading & Drainage1Allow$8,500.00$8,500.00
Infiltration Swale1Allow$7,500.00$7,500.00
Sub-Total $16,000.00
Site Hardscape
4" Concrete Paving1,908SF$6.50$12,402.00
4" Enhanced Concrete Paving2,533SF$9.00$22,797.00
Sub-Total $35,199.00
Site Furnishings
Trash Receptacles4EA$1,500.00$6,000.00
Bench4EA$3,500.00$14,000.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table4EA$4,500.00$18,000.00
B.B.Q. Units Small2EA$1,500.00$3,000.00
B.B.Q. Ash Urn2EA$3,500.00$7,000.00
Drinking Fountain and Sump1EA$6,000.00$6,000.00
Site Signage2EA$5,000.00$10,000.00
Shade Shelters (32' Octagon)1EA$64,000.00$64,000.00
2-5 Year Play Equipment1Allow$150,000.00$150,000.00
Play Area Surfacing (Rubber)2,277Allow$13.50$30,739.50
Sub-Total $310,239.50
Fencing
4' High Aluminum Fence at Perimeter165LF$14.00$2,310.00
4' x 30" Sq. Pilasters at Aluminum Fence9EA$2,250.00$20,250.00
8' High Block Wall at Property Line240LF$30.00$7,200.00
8' x 30" Sq. Pilasters at Block Wall6EA$4,500.00$27,000.00
Sub-Total $56,760.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Tripolis Friendship Park
Landscape
Landscaping (trees, shrubs & groundcover)4,822SF$5.00$24,110.00
Sod 6,012SF$0.50$3,006.00
Sub-Total $27,116.00
Irrigation System
Irrigation System10,834SF$0.75$8,125.50
Sub-Total $8,125.50
Site Lighting
Walkway Lights3EA$2,500.00$7,500.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $15,500.00
Sub Total $501,440.00
10% Contingency $50,144.00
Construction Total
$551,584.00
8% - 10% Consulting Fees55,158.40
5% City Management Fees27,579.20
Grand Total634,321.60
Average Cost Per Acre
Development Acreage
0.34
Estimated Development Cost$634,321.60
Cost per Acre$1,865,651.76
3/6/2017
Preliminary Opinion of Construction Costs
For
Wilderness Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$213,000.00$213,000.00
Construction Cost)
Sub-Total $213,000.00
Demolition
Miscellaneous Debris1Allow$215,000.00$215,000.00
Sub-Total $215,000.00
Earthwork
Grading & Drainage1Allow$215,000.00$215,000.00
Sub-Total $215,000.00
Utilities
6" Sewer Line900LF$50.00$45,000.00
Sewer Cleanouts10EA$600.00$6,000.00
Sewer Manhole4EA$2,500.00$10,000.00
2" Domestic Water Line900LF$12.00$10,800.00
2" Domestic Water Backflow Preventer2EA$9,000.00$18,000.00
2" Domestic Water Gate Valve2EA$400.00$800.00
6" Irrigation Backflow Preventer1EA$12,000.00$12,000.00
8" Fire Water Line900LF$95.00$85,500.00
Fire Hydrant3EA$2,500.00$7,500.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $210,600.00
Site Hardscape
4" Concrete Paving2,965SF$6.50$19,272.50
4" Enhanced Concrete Paving10,810SF$9.00$97,290.00
36,028LF$6.00$216,168.00
Asphalt Paving at Parking Lot
7,092SF$22.00$156,024.00
Porous Pavers at Parking Stalls
2,979SF$12.00$35,748.00
Concrete Ramp
1,464SF$12.00$17,568.00
Concrete Steps
545SF$24.00$13,080.00
Concrete Amphitheater
1,533LF$85.00$130,305.00
18" High Rock Wall
465LF$85.00$39,525.00
Keystone Wall
374LF$27.00$10,098.00
Play Area Curb
Sub-Total $488,754.50
Architectural
Concession Building / Shelter5,000SF$150.00$750,000.00
Nature Center / Remodel4,000SF$120.00$480,000.00
Trash Enclosures w/ Lattice Roof2EA$15,000.00$30,000.00
Sub-Total $1,260,000.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Wilderness Park
Trails
5' Wide Natural Trail20,895SF$1.50$31,342.50
326EA$375.00$122,250.00
6" x 8" x 5' Long Landscape Tie Step
$54,000.00
Water Diverter at 5' Wide Trail30EA$1,800.00
$9,847.50
Natural Trail at Picnic Areas6,565SF$1.50
$157,164.00
River Rock Lined Infiltration Swale 5,613LF$28.00
$224,730.00
Lodge Pole Fence (no conc. footing.)6,810LF$33.00
$140,000.00
Trail Directional / Interpretative Signage40EA$3,500.00
Sub-Total $217,440.00
Site Furnishings
Trash Receptacles20EA$1,500.00$30,000.00
Bench2EA$3,500.00$7,000.00
Bike Rack2EA$1,500.00$3,000.00
Picnic Table52EA$4,500.00$234,000.00
B.B.Q. Units Small20EA$1,500.00$30,000.00
B.B.Q. Ash Urns14EA$3,500.00$49,000.00
Drinking Fountain and Sump4EA$6,000.00$24,000.00
Site Entry Signage1EA$8,000.00$8,000.00
Nature Walk Structures1Allow$345,000.00$345,000.00
5-12 Year Play Equipment1Allow$365,000.00$365,000.00
Play Area Surfacing (wood Chips)5,998SF$2.25$13,495.50
Flag Pole1EA$6,500.00$6,500.00
Fire Pit Ring 1EA$2,500.00$2,500.00
Sub-Total $1,114,995.50
Fencing
8' High Aluminum Fence at Perimeter2,910LF$28.00$81,480.00
8' x 30" Sq. Pilasters at Aluminum Fence60EA$4,500.00$270,000.00
8' H x 11' W. Aluminum Gates8EA$6,000.00$48,000.00
Vehicular Barrier Post24EA$1,000.00$24,000.00
Vehicular Post and Rail Barrier27EA$3,500.00$94,500.00
Sub-Total $399,480.00
Landscape
Native Landscaping (shrubs & groundcover)1Allow$75,000.00$75,000.00
Sod 15,308SF$0.50$7,654.00
Sub-Total $82,654.00
Irrigation System
Drip Irrigation System at Native Landscaping1Allow$50,000.00$50,000.00
Irrigation System at Sod15,308SF$0.75$11,481.00
Sub-Total $50,000.00
3/6/2017
Preliminary Opinion of Construction Costs
For
Wilderness Park
Sub Total $4,466,924.00
10% Contingency $446,692.40
Construction Total
$4,913,616.40
8% - 10% Consulting Fees491,361.64
5% City Management Fees245,680.82
Grand Total5,650,658.86
Average Cost Per Acre
Development Acreage
8.7
Estimated Development Cost$5,650,658.86
$649,501.02
Cost per Acre
7/19/2017
Preliminary Opinion of Construction Costs
For
LA County, Arcadia Park
SUB TOTAL EXTENSION OF EXTENSION
BASE COSTBASE COSTTOTALS
BASE BID ITEMSQTYUNITUNIT COST
Construction Costs
Mobilization/Overhead & Profit
Mobilization/Overhead & Profit (5% of
1Allow$318,200.00$318,200.00
Construction Cost)
Sub-Total $318,200.00
Demolition
Miscellaneous Debris1Allow$41,250.00$41,250.00
Sub-Total $41,250.00
Earthwork
Grading & Drainage1Allow$41,250.00$41,250.00
Sub-Total $41,250.00
Utilities
6" Sewer Line650LF$50.00$32,500.00
Sewer Cleanouts7EA$600.00$4,200.00
Sewer Manhole1EA$2,500.00$2,500.00
2" Domestic Water Line650LF$12.00$7,800.00
2" Domestic Water Backflow Preventer1EA$9,000.00$9,000.00
2" Domestic Water Gate Valve1EA$400.00$400.00
8" Fire Water Line650LF$95.00$61,750.00
Fire Hydrant2EA$2,500.00$5,000.00
Electrical Transformer Pad1EA$15,000.00$15,000.00
Sub-Total $138,150.00
Site Hardscape
4" Concrete Paving16,991SF$6.50$110,441.50
4" Enhanced Concrete Paving27,257SF$9.00$245,313.00
498SF$12.00$5,976.00
ADA Concrete Ramp
502LF$85.00$42,670.00
Concrete Retaining Wall
32SF$12.00$384.00
Concrete Steps
Sub-Total $404,784.50
Basketball Courts
17,101SF$12.00$205,212.00
6" Post Tension Conc. @ Basketball Ct.
4" Concrete Paving10,806SF$6.50$70,239.00
4" Enhanced Concrete Paving1,100SF$9.00$9,900.00
Basketball Back Boards8EA$4,500.00$36,000.00
3 Row x 21' Long Bleacher w/ Canopy8EA$7,500.00$60,000.00
Trash Receptacles16EA$1,500.00$24,000.00
Bench16EA$3,500.00$56,000.00
Drinking Fountain and Sump2EA$6,000.00$12,000.00
Sub-Total $473,351.00
7/19/2017
Preliminary Opinion of Construction Costs
For
LA County, Arcadia Park
Permiter Walking Trail
6' Decomposed Granite Walking Trail72,612SF$8.00$580,896.00
Walkway Lighting Standard33EA$3,500.00$115,500.00
Pedestrian Bridge2EA$35,000.00$70,000.00
Sub-Total $766,396.00
Architectural
Teen Center / Gymnasium 24,414SF$150.00$3,662,100.00
Sub-Total $3,662,100.00
Site Furnishings
Trash Receptacles10EA$1,500.00$15,000.00
Bench2EA$3,500.00$7,000.00
Bike Rack1EA$1,500.00$1,500.00
Picnic Table14EA$4,500.00$63,000.00
B.B.Q. Units Small8EA$1,500.00$12,000.00
B.B.Q. Ash Urns8EA$3,500.00$28,000.00
Drinking Fountain and Sump2EA$6,000.00$12,000.00
Site Signage2EA$5,000.00$10,000.00
Arbor Structure at Picnic Area3EA$15,000.00$45,000.00
Arbor Structure at Flag Pole8EA$5,000.00$40,000.00
Arbor Structure at Tot-Lot2EA$10,000.00$20,000.00
2-5 Year Play Equipment1Allow$150,000.00$150,000.00
Boundless Play Structure1Allow$138,000.00$138,000.00
Rock and Rope Play Structure1Allow$410,000.00$410,000.00
Play Area Surfacing (Rubber) at 2-5 Tot1,412SF$13.50$19,062.00
Play Area Surfacing (Rubber)6,307SF$13.50$85,144.50
Play Area Surfacing (Wood Chips)3,117SF$2.25$7,013.25
Flag Pole1EA$6,500.00$6,500.00
Sub-Total $1,069,219.75
Fencing
4' High Aluminum Guardrail277LF$14.00$3,878.00
8' High Aluminum Fence at Perimeter31LF$28.00$868.00
8' H. x 5' W. C.L.Gates4EA$1,500.00$6,000.00
Sub-Total $10,746.00
Landscape
Landscaping (trees, shrubs & groundcover)8,724SF$5.00$43,620.00
Sod 59,509SF$0.50$29,754.50
Sub-Total $73,374.50
Irrigation System
Irrigation System68,233SF$0.75$51,174.75
Sub-Total $51,174.75
7/19/2017
Preliminary Opinion of Construction Costs
For
LA County, Arcadia Park
Site Lighting
Walkway Lights27EA$2,500.00$67,500.00
Basketball Court Lights (single)4EA$3,500.00$14,000.00
Basketball Court Lights (double)6EA$4,500.00$27,000.00
Electrical Gear and Pad1EA$8,000.00$8,000.00
Sub-Total $116,500.00
Sub Total $7,166,496.50
10% Contingency $716,649.65
Construction Total
$7,883,146.15
8% - 10% Consulting Fees788,314.62
5% City Management Fees394,157.31
Grand Total9,065,618.07
Average Cost Per Acre
Development Acreage
1.65
Estimated Development Cost$9,065,618.07
Cost per Acre$5,494,313.98
Part 1
Park Amenity Standards
Aluminum Fence 4’ High
•Manufacturer:Ameristar
•Product: Echelon II Industrial
Ornamental Aluminum Fence
•Phone #: (888) 333-3422
Aluminum Fence 8’ High
•Manufacturer:Ameristar
•Product: Echelon II Industrial
Ornamental Aluminum Fence
•Phone #: (888) 333-3422
Arbor Structure
• Manufacturer:Polygon/Icon Shelter Systems
• Model No.:As determined by Architect
• Phone #: (800) 748-0985
Ash Urn
•Manufacturer: Outdoor Creations
•Model No.:300CR w/Rock Veneer
•Phone #:(530) 365-6106
Bar-B-Que – 1a
•Manufacturer: DuMor, Inc.
•Model No.:BBQ Grill 21-00
•Phone #:(800) 598-4018
Bar-B-Que – 1b (Wilderness Park)
•Manufacturer: Outdoor Creations
•Model No.:300A w/Rock Veneer
•Phone #:(530) 365-6106
Baseball Netting
•Manufacturer:Judge Netting
•Product: As determined by Architect
•Phone #: (855) 987-7556
CityofArcadiaCommunityParksParkAmenityStandards|Page 1
Part 1
Park Amenity Standards
Base Pads
•Manufacturer:Schutt Hollywood/Bolco
•Product: As determined by Architect
•Phone #: (866) 923-5050
Basketball Back Stop
• Manufacturer:Goalrilla
• Model No.: DC72EI
• Phone #: (888) 872-4625
Basketball / Tennis Court Lighting
• Manufacturer:Kim Lighting
•Model No.:Altitude
• Phone #: (800) 825-6030
Basketball / Tennis Court Lighting / Solar Option
• Manufacturer:Ember LED
•Model No.: eShine Solar
• Phone #: (201) 228-0880
Bat Rack
• Manufacturer: L.A. Steel Craft
• Model No.:BR 15 SM Surface Mount
• Phone #: (800) 371-2438
Batting Cage Netting
• Manufacturer:Jugs
• Model No.:Cage Net #10
• Phone #: (800) 547-6843
Benches @ Parks
• Manufacturer: DuMor, Inc.
• Model No.: Custom (Color Black)
• Phone #: (800) 598-4018
CityofArcadiaCommunityParksParkAmenityStandards|Page 2
Part 1
Park Amenity Standards
Benches @ Baseball / Softball Fields
• Manufacturer: L.A. Steel Craft
• Model No.: PBA-15P
• Phone #: (800) 371-2438
Benches @ Basketball / Tennis Courts
• Manufacturer: DuMor, Inc.
• Model No.: 497 (Color Black)
• Phone #: (800) 598-4018
Bike Rack
• Manufacturer: DuMor, Inc.
• Model No.:Custom (Color Black)
• Phone #:(800) 598-4018
Bleachers (3 Row)
• Manufacturer:L.A. Steel Craft
• Model No.:BL0321SA
• Phone #: (800) 371-2438
Bleachers (5 & 7 Row)
• Manufacturer:L.A. Steel Craft
• Model No.:BL0521SA
• Phone #: (800) 371-2438
Bleacher Shade
• Manufacturer:Polygon/Icon Shelters
• Model No.: As determined by Architect
• Phone #: (800) 748-0985
Bollards (Collapsible)
• Manufacturer:Belson Outdoors
• Model No.:BCB-30
• Phone #: (800) 323-5664
4’ Brick Pilaster
• Refer to Standard Detail
CityofArcadiaCommunityParksParkAmenityStandards|Page 3
Part 1
Park Amenity Standards
8’ Brick Pilaster
• Refer to Standard Detail
Concrete Stairs with Handrails
• Refer to Standard Detail
Decomposed Granite Trail
• Supplier:Gail Materials
• Type: NexPave
• Phone #: (951) 667-6106
Doggie Dispenser
• Manufacturer:Doggie Walk Bags
• Model No.:Dispenser, Lock & Metal Sign
• Phone #: (949) 756-2247
Doggie Drinking Fountain
• Manufacturer:Haws
• Model No.:3500D / With Bottle Filler
• Phone #: (888) 640-4297
Doggie Play Equipment
•Manufacturer:National Business Furniture
• Model No.:Ultra Play BarkPark 82303
• Phone #: (800) 558-1010
Drinking Fountain
• Manufacturer:Haws
• Model No.:3500 / With Bottle Filler
• Phone #: (888) 640-4297
CityofArcadiaCommunityParksParkAmenityStandards|Page 4
Part 1
Park Amenity Standards
Fire Pit Ring
• Manufacturer:Outdoor Creations
• Model No.:303 – 6’
• Phone #: (530) 365-6106
Fixed Backstop with Dugout – Refer to Cut Sheet or
Standard Detail
• Manufacturer:L.A. Steel Craft
• Model No.:35T Series
• Model No.:45T Series
• Phone #: (800) 371-2438
Flag Pole
• Manufacturer:L.A. Steel Craft
• Model No.:EC 25’-35’ – As determined by City
• Phone #: (800) 371-2438
Foul Pole
• Manufacturer:L.A. Steel Craft
• Model No.:FLP 30 - As Determined by City
• Phone #: (800) 371-2438
Infield Mix
• Manufacturer:Gail Materials/Corona Clay
• Type: Pro/Gold Angel Mix
• Phone #: (951) 667-6106 or (951) 277-2667
Infiltration Swale Example
Information Kiosk
•Manufacturer: Classic Recreation Systems
• Model No.:Kiosk 1091
• Phone #: (800) 697-2195
CityofArcadiaCommunityParksParkAmenityStandards|Page 5
Part 1
Park Amenity Standards
Monument Signage Example
Par Course Equipment
• Manufacturer:Landscape Structures, Inc.
• Model No.: Health Beat – As Determined by City
• Phone #: (888) 488-9253
Park Identification Sign
• Manufacturer:Impact Signs
• Model No.: As determined by Architect
• Phone #: (909) 598-9111
Parking Lot Lighting
• Manufacturer:Kim Lighting
• Model No.:Archetype
• Phone #: (800) 825-6030
Parking Lot Lighting / Solar Option
• Manufacturer:SolarOne
• Model No.:Sonxt Luminaire
• Phone #: (877) 527-6461
Pavers
• Manufacturer:Angelus Paving Stones
• Model No.:As determined by Architect
• Phone #: (951) 328-9115
Pedestrian Bridge
• Manufacturer:Icon Shelter Systems
• Model No.:As determined by Architect
• Phone #: (800) 748-0985
Pervious Pavers
• Manufacturer:Angelus Paving Stones
• Model No.:As determined by Architect
• Phone #: (951) 328-9115
CityofArcadiaCommunityParksParkAmenityStandards|Page 6
Part 1
Park Amenity Standards
Picnic Table @ Parks
• Manufacturer:Outdoor Creations
• Model No.:100FSS w/City Logo
• Phone #: (503) 365-6106
Portable Pitching Mound
• Manufacturer: Big Brown Mound
• Model No.:As Specified by City
• Phone #: (509) 679-3393
Recycled / Trash Receptacles
• Manufacturer: Bigbelly Solar
• Model No.: Smart Waste & Recycling System
• Phone #: (888) 820-0300
Remote Control Score Board
• Manufacturer: On Deck Sports
• Model No.: SB1103
• Phone #: (800) 365-6171
Rubber Surfacing
• Manufacturer:Landscape Structures, Inc.
• Model No.:PebbleFlex 2.0
• Phone #: (888) 488-9253
Shade Structures
• Manufacturer:Classic Recreation Systems
• Model No.:As determined by Architect
• Phone #: (800) 697-2195
Shade Structures / Solar Option
• Manufacturer:Classic Recreation Systems
• Model No.:As determined by Architect
• Phone #: (800) 697-2195
Solar Charging Station / Bench
• Manufacturer:Solade Concepts
• Model No.: Solar Charging Station
• Phone #: (800) 991-3013
CityofArcadiaCommunityParksParkAmenityStandards|Page 7
Part 1
Park Amenity Standards
Sports Field Lighting
• Manufacturer:Musco
• Model No.:As determined by Architect
• Phone #: (800) 825-6030
Storage Bin w/Office
• Manufacturer:Mobile Modular
• Model No.:Office & Storage Combo
• Phone #: (866) 459-7600
Synthetic Turf
• Manufacturer:Matrix Turf
• Model No.:As spec’ed by Architect w/Organic Infill
• Phone #: (800) 233-5714
Tennis Court Posts
• Manufacturer:L.A. Steel Craft
• Model No.:CTR-3
• Phone #: (800) 371-2438
Trail Interpretive / Educational Signage
• Manufacturer:Fossil Industries
• Model No.:As Specified by City
• Phone #: (631) 254-9200
Trash Receptacle @ Parks
• Manufacturer:DuMor, Inc.
• Model No.:157
• Phone #: (800) 598-4018
Trash Receptacle @ Tennis Courts
• Manufacturer: Barco Products
• Model No.:Stone AggregateDE-710FF
• Phone #: (800) 338-2697
Volleyball Posts
• Manufacturer:L.A. Steel Craft
• Model No.:AGP-4
• Phone #: (800) 371-2438
CityofArcadiaCommunityParksParkAmenityStandards|Page 8
Part 1
Park Amenity Standards
Walkway Lighting
• Manufacturer:Kim Lighting
• Model No.: Solitaire/SRS1 LED
• Phone #: (800) 825-6030
Walkway Lighting / Solar Option
• Manufacturer:SolarOne
• Model No.: TSO3
• Phone #: (877) 527-6461
Wood Fiber Playground Surfacing
• Manufacturer:RWP
• Model No.: Fiber Fall Engineered Wood Fiber
• Phone #: (877) 476-9797
Picnic Table
• Manufacturer: DuMor, Inc.
• Model No.: Custom (Color Black)
• Phone #: (800) 598-4018
CityofArcadiaCommunityParksParkAmenityStandards|Page 9
Part 2
Playground Standards
1 Bicentennial Park
2 Bonita Park
3 Camino Grove Park
4 Eisenhower Memorial Park
5 Fairview Park
6 Hugo Reid Park
7 New Castle Park
8 Tierra Verde Park
9 Tripolis Friendship Park
10 Wilderness Park
11 Los Angeles County Arcadia Park
These designs are merely suggestions on how the playground equipment
can be designed. Final design and colors will be determined when the
parks is under renovation.
CityofArcadiaCommunityParksPlaygroundStandards
Part 3
Trail Standards
Benches
•Supplier:Barco Products
•Model No.: Sterling Recycled Plastic Slats KBC1350
• Phone #:(800) 338-2697
Concrete Stairs with Handrails
• Refer to Standard Detail
Decomposed Granite Trail
•Supplier:Gail Material
•Type: NexPave
• Phone #: (951) 667-6106
Pressure Treated Wood Steps w/Handrails
• Refer to Standard Detail
Recycled Trash Receptacles
•Supplier:Barco Products
•Model No.: Ravinia Recycled Plastic Slats KTR2200
• Phone #: (800) 338-2697
Trail Fencing
• Refer to Cut Sheet
Trail Signage
• Refer to Cut Sheet
CityofArcadiaCommunityParksΑTrailStandards|Page 1
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 2
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 3
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 4
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 5
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 6
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 7
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 8
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 9
Part 3
Trail Standards
CityofArcadiaCommunityParksΑTrailStandards|Page 10
Part 4
Building & Restroom Standards
Casework/Cabinetry
•Manufacturer: Determined by Architect
•Type: W.I.C. ‘custom grade’ , type 1-style A for high
pressure laminate
Caulking
•Manufacturer: Dow-Corning
•Product: Silicone/Acrylic Blend Mix Building Sealant
•Supplier: As determined by Architect
Ceramic Tile
• Manufacturer:Dal Tile
Product: As determined by Architect
• Supplier: As determined by Architect
Concrete (float work)
• Supplier: Determined by Contractor
• Type: 2500 psi @ 28 days,
conform to ASTM C33 and C150
Concrete Reinforcing
• Supplier: Determined by Engineer
• Type: As recommended by Soils Report and/or
determined by Structural Engineer
.
Doors/Frames/Hardware
• Manufacturer: Republic, Schlage, Hager, LNC,
Quality, Pemko
• Product:Doors, frames, locksets, hinges, closer,
stops, threshold/weather stripping
Full Mortis Lock Set
• Supplier: As determined by Architect
Drywall
• Manufacturer: US Gypsum
• Product: 5/8”, type-x, water-resistant
• Supplier: As determined by Architect
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 1
Part 4
Building & Restroom Standards
Electrical
•Manufacturer: As selected by Architect
•Product:
Fluorescent: 2 x 4 Lay-In w/3-T5 Lamps
1 x 4 Surface Mount w/2-T5 Lamps
LED: 2 x 4 Lay-In w/LED Lamp Color level 3000k
1 x 4 Surface Mount w/LED Lamp
Color level 3000K
Architectural Exterior Wall Sconce LED Lamp
Color level 3000K
•Supplier:As determined by Architect
Fire Alarm
•Supplier: As determined by City
•Type: As required by local Fire Dept./governing
codes & engineered by City
Fire Extinguishers/Cabinets
•Manufacturer: JL Industries
•Product: 1017F10 with 5 mo. A,B,C
Fire Extinguisher tagged by licensed company prior
to installation.
•Supplier: As determined by Contractor
Fire Sprinkler System
•Supplier: As determined by Architect/Contractor
•Type: As required by local fire dept./governing
codes & engineered by Contractor
Floor Coverings
•Manufacturer: Shaw Commercial
•Product:24 oz. Loop Carpet Tiles
•Supplier:As determined by Architect
Glass/Glazing
•Manufacturer: Pilkington
•Product: Energy Advantage Low E
•Supplier:As determined by Architect
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 2
Part 4
Building & Restroom Standards
HVAC Systems
•Manufacturer: Carrier/Trane
•Product: As determined by Mechanical Engineer
•Supplier:As determined by Contractor
Insulation
•Manufacturer: Owens-Corning
•Product: Preformed glass fiber batt, aluminum foil
backed where required, ‘R’ value as engineered,
ASTM C665, E84, E136
•Supplier:As determined by Contractor
Lumber/Rough Carpentry
•Supplier: Determined by Engineer
•Type: #2 Douglas Fir, S4S, S-dry or MC19, WWPA
Masonry
•Manufacturer: CMU: Angelus Block Co.
Brick: Pacific Clay
•Product: CMU: 8 x 8 x 16 precision and or splitface
Brick: 3 x 4 x 15½“
(thin brick cut from full brick)
•Supplier:Angelus Block, Pacific Clay
Painting
•Manufacturer: Dunn Edwards
•Product: Flat, semi-gloss, egg shell where noted
•Supplier:As determined by Architect
Plumbing
•Manufacturer:
Fixtures: Acorn, American Standard
Faucets: Chicago Faucets (electronic sensor)
Flush Valves: Sloan (electronic sensor)
•Product: As determined by
Plumbing Engineer/Architect
•Supplier:As determined by Architect
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 3
Part 4
Building & Restroom Standards
Roofing
•Manufacturer: Eagle Roofing
•Product: Ponderosa (Color 302 Arcadia)
•Supplier:Eagle Roofing
Sheet Metal
•Manufacturer:As determined by Architect
•Type: Galvanized steel flashings (24 ga. min.)
Gutters/downspouts (22 ga. min.)
•Supplier:As determined by Contractor
Signage
•Manufacturer: Take Form
•Product: Fusion Arch
•Supplier:Take Form
Skylights
•Manufacturer: Solatube
•Product: 750 DS
•Supplier:As determined by Architect
Suspended Acoustical Ceiling
•Manufacturer: Armstrong Ceiling Systems
•Product: 24 x 48 Cirrus (535)
Standard 15/16” Grid (white)
•Supplier:As determined by Architect
Toilet Partitions/Accessories
•Manufacturer: Scranton Products, Bobrick, Dyson
•Product:
Solid Plastic (3000) Partitions
Stainless Steel (satin 304) Toilet Accessories
Airblade dB Hand Dryer
•Supplier:As determined by Architect
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 4
Part 4
Building & Restroom Standards
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 5
Part 4
Building & Restroom Standards
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 6
Part 4
Building & Restroom Standards
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 7
Part 4
Building & Restroom Standards
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 8
Part 4
Building & Restroom Standards
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 9
Part 4
Building & Restroom Standards
CityofArcadiaCommunityParksΑBuilding&RestroomStandards|Page 10
Part 5
Irrigation Standards
Backflow Preventer
•Manufacturer: Febco
•Model No.:As determined by Irrigation Designer
•Phone #:(800) 767-1234
Ball Valve Valve; 2” and smaller
•Manufacturer:
•Model No.:
•Phone #:
Butterfly Valve; 2 ½” and larger
•Manufacturer:
•Model No.:
•Phone #:
Drip Irrigation
•Manufacturer: Rainbird/Hunter
•Model No.:As determined by Irrigation Designer
•Phone #:(800) 724-6247 (760) 744-5240
Flow Sensor
•Manufacturer: Calsense
•Model No.:As determined by Manufacturer
•Phone #:(800) 572-8608
Irrigation Controller
•Manufacturer: Calsense
•Model No.:ET-200E
•Phone #:(800) 572-8608
Master Valve
•Manufacturer: Rainbird
•Model No.:
•Phone #:(800) 724-6247
CityofArcadiaCommunityParksΑIrrigationStandards|Page 1
Part 5
Irrigation Standards
Quick Coupler Valve
•Manufacturer: Rainbird
•Model No.:44LRC
•Phone #:(800) 724-6247
Remote Control Valves
•Manufacturer: Rainbird
•Model No.:GB Series
•Phone #:(800) 724-6247
Rotor Heads
•Manufacturer: Hunter
•Model No.:1.40/PGP/PGJ
•Phone #:(760) 744-5240
Spray Heads
•Manufacturer: Rainbird
•Model No.:1800 Series
•Phone #:(800) 724-6247
Valve Boxes
•Manufacturer: Carson Brooks
•Model No.:As determined by Irrigation Designer
•Phone #:(201) 481-2212
“Y” Strainer
•Manufacturer: Febco
•Model No.:As determined by Irrigation Designer
•Phone #:(800) 767-1234
CityofArcadiaCommunityParksΑIrrigationStandards|Page 2