HomeMy WebLinkAboutItem 2e - Accept Pavement Rehabilitation Project on Lemon Ave., Camino Real Ave., and Sixth Ave. as Complete DATE: January 16, 2018
TO: Honorable Mayor and City Council
FROM: Tom Tait, Public Works Services Director By: Eddie Chan, P.E., Principal Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY ALL AMERICAN ASPHALT FOR
THE PAVEMENT REHABILITATION PROJECT ON LEMON AVENUE, CAMINO REAL AVENUE, AND SIXTH AVENUE AS COMPLETE. Recommendation: Approve
SUMMARY
On February 21, 2017, the City Council approved a contract with All American Asphalt in the amount of $1,037,700 for the Pavement Rehabilitation Project on Lemon Avenue,
Camino Real Avenue, and Sixth Avenue. The terms and conditions of this project have
been complied with and the work has been performed to the satisfaction of the Project
Manager for a total project cost of $983,922.01. This amount reflects the original contract amount of $1,037,700, minus quantity changes totaling $53,777.99, or 5.2% less than the original contract amount.
It is recommended that the City Council accept all work performed by All American
Asphalt for the Pavement Rehabilitation Project on Lemon Avenue, Camino Real Avenue, and Sixth Avenue as complete, and authorize the final payment to be made in accordance with the contract documents, subject to retention of $ 49,196.11.
BACKGROUND
The Public Works Services Department (“PWSD”) is responsible for the maintenance and repair of approximately 147 miles of paved streets within the City. As part of the
City’s Pavement Management Program, the conditions of all City streets were inspected
and rated on a scale of 0-100, with scores below 40 generally being considered a street
which has failed. Scores between 40 and 60 are poor/fair in nature. This rating is called the Pavement Condition Index (“PCI”) and is used to help determine which streets require asphalt pavement rehabilitation.
According to the Citywide Pavement Management Program, the street section of Lemon
Avenue between Baldwin Avenue and Holly Avenue had a PCI of 56, Camino Real
Accept Pavement Rehabilitation Project – All American Asphalt
January 16, 2018
Page 2 of 4
Avenue between El Monte Avenue and Santa Anita Avenue had a PCI of 62, and Sixth
Avenue from Camino Real Avenue to Longden Avenue had a PCI rating of 27. PCIs
alone do not determine which streets should be rehabilitated; for instance, the City also
takes into consideration streets that have a high volume of traffic. Additionally, it is more cost effective to rehabilitate streets prior to the PCI lowering to poor or very poor condition.
DISCUSSION
On February 21, 2017, the City Council approved a contract with All American Asphalt for the Pavement Rehabilitation Project on Lemon Avenue, Camino Real Avenue, and
Sixth Avenue. The work performed involved repairing localized potholes and failed
pavement, grinding the edges of the pavement adjacent to the gutters to transition the
new pavement to the existing gutter, replacing broken curb and gutter as necessary, and installing new ADA-compliant curb ramps at the intersections. The new pavement surface included recycled rubber in the pavement mix to help reduce future cracking
and to add strength to the asphalt pavement. Following the repairs, the conditions of
these street sections were raised to a PCI of 100.
During the course of work, it was discovered that the asphalt thickness on Lemon Avenue, Camino Real Avenue, and Sixth Avenue varied, which resulted in change
orders that decreased the amount of work needed. Additional striping and pavement
markings were needed on Live Oak Avenue and Las Tunas Drive in the vicinity of
Longley Way Elementary School and was included into the scope of work. The additional street striping will help improve traffic safety in the area. Additional ADA Curb Ramps were also installed along Camino Real Avenue and additional driveway
approach/cross gutter and asphalt digouts were included as additional work. Below is a
breakdown of contract change orders.
CCO Description Amount
1. Deleted (4778 SF) - Construct 4-inch Cold Mill Grind (Lemon Avenue) ($1,433.40)
2. Deleted (592 TONS) – Construct 2-inch Conventional Overlay (Lemon Avenue) ($35,535.60)
3. Deleted (169 TONS) – Construct 2-inch ARHM Overlay (Lemon Avenue) ($12,516.36)
4. Additional (6 EA) – Remove and Replace PCC Curb Ramps (Lemon Avenue) $21,600.00
5. Deleted (4,075 SF) – Construct 4-inch Cold Mill Grind (Camino Real Avenue) ($1,222.50)
6. Deleted (167 TONS) – Construct 2-inch Conventional Overlay (Camino Real Avenue) ($9,990.60)
7. Deleted (134 TONS) – Construct 2-inch ARHM Overlay (Camino Real Avenue) ($9,923.40)
8. Deleted (10 SF) – Remove and Replace PCC Sidewalk (Camino Real Avenue) ($65.00)
Accept Pavement Rehabilitation Project – All American Asphalt
January 16, 2018
Page 3 of 4
9. Deleted (2 LF) – Remove and Replace PCC Curb and Gutter (Camino Real
Avenue) ($90.00)
10. Deleted (8,543 SF) - Construct 4-inch Cold Mill Grind (Sixth Avenue) ($2,562.90)
11. Deleted (873 TONS) - Construct 2-inch Conventional Overlay (Sixth Avenue) ($52,358.40)
12. Deleted (291 TONS) - Construct 2-inch ARHM Overlay (Sixth Avenue) ($21,565.08)
13. Deleted (24 SF) - Remove and Replace PCC Sidewalk (Sixth Avenue) ($156.00)
14. Deleted (70 LF) - Remove and Replace PCC Curb and Gutter (Sixth Avenue) ($3,150.00)
15. Additional (1 LS) Move-In (Remobilization) $19,443.75
16. Additional (1 LS) – Traffic Control $4,300.00
17. Additional (1 LS) – Striping at Las Tunas Drive / Live Oak Avenue Area $19,500.00
18. Additional (1 LS) – Restripe Existing Yellow Cross Walk, Limit Line & Slow Stencil
at Las Tunas Drive $3,780.00
19. Additional (67 SF) - Remove and Replace PCC Driveway Approach (Sixth Avenue) $1,005.00
20. Additional (1 LS) – Install Striping at Santa Anita Avenue / Live Oak Avenue $670.00
21. Additional (2,090 SF) – 4-inch AC Digouts $15,152.50
22. Additional (180 SF) Construct PCC Cross Gutter $11,340.00
Total ($53,777.99)
The terms and conditions of this contract have been complied with and the work has
been performed to the satisfaction of the Project Manager. All American Asphalt completed the work as defined in the project plans and specifications in an efficient and
timely manner.
FISCAL IMPACT
Funds in the amount of $1,245,000 have been budgeted in the Fiscal Year 2016-17
Capital Improvement Program, $745,000 from the Capital Outlay Fund and $500,000
from Measure R Fund. The total cost for the Pavement Rehabilitation Project is
$983,922.01. This amount reflects the original contract amount of $1,037,700 minus quantity changes totaling $53,777.99.
Accept Pavement Rehabilitation Project – All American Asphalt
January 16, 2018
Page 4 of 4
RECOMMENDATION
It is recommended that the City Council accept all work performed by All American
Asphalt for the Pavement Rehabilitation Project on Lemon Avenue, Camino Real Avenue, and Sixth Avenue as complete, and authorize the final payment to be made in accordance with the contract documents, subject to retention of $49,196.11.