DATE: February 20, 2018
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director
Philip A. Wray, Deputy Director of Development Services/City Engineer
By: Kevin Merrill, Principal Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY CALIFORNIA PROFESSIONAL
ENGINEERING, INC. FOR TRAFFIC SIGNAL IMPROVEMENTS ON
DUARTE ROAD AT FIRST AND SECOND AVENUE AS COMPLETE
Recommendation: Approve
SUMMARY
On May 2, 2017, the City Council awarded a contract to California Professional
Engineering, Inc., in the amount of $159,050, plus a 10% contingency, for traffic signal improvements on Duarte Road at the intersections of First Avenue and Second Avenue.
There was one (1) change order on the project in the amount of $3,903.62, or 2.50%.
With the adjustment for actual quantities, the final contract amount is $162,953.62.The
terms and conditions of this project have been complied with, and the required work has
been performed to staff’s satisfaction. It is recommended that the City Council accept the project as complete, and authorize the final payment in accordance with the contract
documents.
BACKGROUND
The traffic signals on Duarte Road at the intersections of First Avenue and Second
Avenue previously had no left-turn phases for traffic on First and Second Avenues.
During certain times of the day, the traffic volumes on First and Second Avenues were
high enough to cause extended delays of more than one signal cycle for drivers wishing
to make left turns. The solution was to install protected/permissive left turn phases, where a driver waiting to make a left turn gets a “protected” green arrow for a few
seconds and then a “permissive” green ball for the balance of the phase. This work was
included in the budget for the Pavement Rehabilitation Project on Duarte Road from
Santa Anita Avenue to Fifth Avenue, but was administered as a separate project.
Accept Traffic Signal Improvements on Duarte Road at First and Second Avenue February 20, 2018
Page 2 of 3
The plans and specifications were completed in March of 2017, and the project was advertised for bids in April 2017. On May 2, 2017, the City Council awarded a contract
to California Professional Engineering, Inc., in the amount of $159,050, plus a 10%
contingency.
DISCUSSION
The construction began in October, 2017, and was completed in January, 2018.
Although the project was completed to the satisfaction of the Staff, the project was
delayed by four items that took additional time: order and delivery of new equipment for the signals, wiring, the video detection system, and replacing LED safety lights.
There was one (1) change order on the project, totaling $3,903.62, or 2.5% of the
project cost. The change order was for upgrading the new LED safety lights to include
built-in photo-cells at the Duarte Road and First Avenue intersection. This was necessary because the old safety lights that were removed had their own photo-cells, and there was no provision in the specifications for new photo-cells. This condition was
not apparent prior to construction and thus new photo-cells had to be added. This
change order brought the final construction total to $162,953.62, which is within the
approved contract contingency. ENVIRONMENTAL ANALYSIS
Award of this project would not be considered a project per the California Environmental
Quality Act (“CEQA”) per Section 15061(b)(3) of the CEQA guidelines. FISCAL IMPACT
The Duarte Road Pavement Rehabilitation Project was budgeted in the 2015-16 Capital
Improvement Program at $800,000 from Proposition C funds. The project consisted of both pavement rehabilitation and traffic signal work. The pavement rehabilitation portion of the project was provided under a separate construction contract. That project was
completed last year (2017), at a final cost of $570,000. The remaining balance in the
budget for the traffic signal work was $230,000, which is sufficient to cover the final cost
of $162,953.62. No General Fund dollars were used for this project. RECOMMENDATION
It is recommended that the City Council accept all work performed by California
Professional Engineering, Inc., for Traffic Signal Improvements on Duarte Road at First and Second Avenue in the amount of $162,953.62, as complete, and authorize the final payment to be made in accordance with the contract documents.
Accept Traffic Signal Improvements on Duarte Road at First and Second Avenue February 20, 2018
Page 3 of 3