Loading...
HomeMy WebLinkAboutItem 11c - Accept Pavement REhabilitation Project as Complete DATE: August 7, 2018 TO: Honorable Mayor and City Council FROM: Tom Tait, Public Works Services Director By: Eddie Chan, P.E., Principal Civil Engineer SUBJECT: ACCEPT ALL WORK PERFORMED BY HARDY & HARPER, INC. FOR THE FISCAL YEAR 2017-18 PAVEMENT REHABILITATION PROJECT AS COMPLETE Recommendation: Approve SUMMARY On February 6, 2018, the City Council approved a contract with Hardy & Harper, Inc. in the amount of $1,234,000 for the Fiscal Year 2017-18 Pavement Rehabilitation Project. The terms and conditions of this project have been complied with and the work has been performed to the satisfaction of the Project Manager for a total project cost of $1,254,243.79. This amount reflects the original contract amount of $1,234,000, plus additional quantity changes totaling $20,243.79, or 1.6% more than the original contract amount. It is recommended that the City Council accept all work performed by Hardy & Harper, Inc. for the Fiscal Year 2017-18 Pavement Rehabilitation Project as complete, and authorize the final payment to be made in accordance with the contract documents, subject to retention of $62,712.19. BACKGROUND The Public Works Services Department (“PWSD”) is responsible for the maintenance and repair of approximately 147 mile s of paved streets within the City. As part of the City’s Pavement Management Program , the conditions of all City streets were inspected and rated on a scale of 0-100, with scores below 40 generally being considered a street which has failed. Scores between 40 and 60 are poor/fair in nature. This rating is called the Pavement Condition Index (“PCI”) and it is used to help determine which streets require asphalt pavement rehabilitation . However, PCIs alone do not determine which streets should be rehabilitated; for instance, the City also takes into consideration whether the street has a high traffic volume. Additionally, it is more cost efficient to rehabilitate streets prior to the PCI reaching a poor or very poor condition. Accept 2017-18 Pavement Rehabilitation Project August 7, 2018 Page 2 of 4 Based on the Citywide Pavement Management Program, the following street segments were included in this year’s project: The street segment of Hampton Road from Michillinda Avenue to Glencoe Drive (PCI of 38), Walnut Avenue from Holly Avenue to El Monte Avenue (PCI of 62), Walnut Avenue from El Monte Avenue to the east end of the cul-de-sac (PCI of 39), Delta Lane from El Monte Avenue to the east end of the cul- de-sac (PCI of 39), Fifth Avenue from Duarte Road to Camino Real Avenue (PCI of 22), and Camino Grove Avenue from Sixth Avenue to Eighth Avenue (PCI of 36). A copy of the Project Location Map is attached as Exhibit “A”. DISCUSSION On February 6, 2018, the City Council approved a contract with Hardy & Harper, Inc. for the Fiscal Year 2017-18 Pavement Rehabilitation Project. The work performed involved repairing localized potholes and failed pavement, grinding the edges of the pavement adjacent to the gutters to transition the new pavement to the existing gutter, replacing broken curb and gutter as necessary, and installing new ADA-compliant curb ramps at the intersections. The new pavement surface utilized recycled rubber in the pavement mix to help reduce future cracking and to add strength to the asphalt pavement. The rubber in the pavement mixture also reduces road noise. Following the repairs, the condition of all relevant street sections was raised to a PCI of 100. Following mobilization of the project, additional work was identified as needed, including pavement rehabilitation on Sierra Madre Boulevard from Santa Anita Avenue to Oakwood Drive, and concrete gutter replacement on Live Oak Avenue and El Capitan Avenue. The additional pavement rehabilitation on Sierra Madre Boulevard helped ease school traffic at Highland Oaks Elementary and also raised the street’s PCI from 52 to 100. The gutter replacement on Live Oak Avenue and El Capitan Avenue addressed drainage issues and improved public safety. While this work was not originally anticipated, it was determined to be high priority and was well within the ten percent contingency approved for the project. Additionally, during the course of work, it was discovered that the asphalt thickness on Hampton Road, Walnut Avenue, Delta Lane, Fifth Avenue, and Camino Grove Avenue varied, which resulted in change orders that decreased the amount of work needed. Below is a breakdown of contract change orders: CCO Description Amount 1. Deleted (4,815 SF) – Construct 10-Inch Cold Mill Grind (Hampton Rd) ($4,574.25) 2. Deleted (1,213.63 TONS) – Construct 6-inch thick Crushed Aggregate Base (Hampton Rd) ($44,904.31) 3. Additional (190.75 TONS) – Construct 2-inch thick Conventional Overlay Leveling (Hampton Rd) $12,780.25 4. Deleted (6.28 EA) – Construct 2-Inch ARHM Overlay (Hampton Rd) ($477.28) Accept 2017-18 Pavement Rehabilitation Project August 7, 2018 Page 3 of 4 5. Additional (10 LF) – Remove and Replace PCC Curb and Gutter (Hampton Rd) $450.00 6. Deleted (26 SF) – Remove and Replace PCC Cross Gutter / Spandrel (Hampton Rd) ($364.00) 7. Deleted (3033 SF) – Construct 2-Inch Cold Mill Grind (Walnut Ave) ($697.59) 8. Deleted (149.6 TONS) – Construct 2-Inch ARHM Overlay (Walnut Ave) ($11,369.60) 9. Deleted (35.26 TONS) – Construct ½-Inch HMA leveling (Walnut Ave from Holly Ave to El Monte Ave) ($2,362.42) 10. Deleted (125 LF) – Remove and Replace PCC Curb and Gutter (Walnut Ave) ($5,625.00) 11. Deleted (30 SF) – Remove and Replace PCC Cross Gutter / Spandrel (Walnut Ave) ($420.00) 12. Deleted (1033 SF) - Construct 2-inch Cold Mill Grind (Delta Ln) ($237.59) 13. Deleted (7.34 TONS) – Construct 2-Inch ARHM Overlay (Delta Ln) ($557.84) 14. Deleted (38 LF) - Remove and Replace PCC Curb and Gutter (Delta Ln) ($1,710.00) 15. Additional (45 SF) – Remove and Replace PCC Sidewalk (Delta Ln) $405.00 16. Deleted (7 SF) – Remove and Replace PCC Cross Gutter / Spandrel (Delta Ln) ($98.00) 17. Additional (1 EA) – Remove and Replace PCC ADA Curb Ramps (Delta Ln) $3,700.00 18. Deleted (2,993 SF) – Construct 2-Inch Cold Mill Grind (Fifth Ave) ($688.39) 19. Deleted (166.54 TONS) – Construct 2-Inch ARHM Overlay (Fifth Ave) ($12,657.04) 20. Deleted (48.7 TONS) – Construct ½-Inch HMA Leveling (Fifth Ave) ($3,262.90) 21. Deleted (299 LF) – Remove and Replace PCC Curb and Gutter (Fifth Ave) ($13,455.00) 22. Deleted (13 SF) – Remove and Replace PCC Sidewalk (Fifth Ave) ($117.00) 23. Deleted (24 SF) – Remove and Replace PCC Cross Gutter / Spandrel (Fifth Ave) ($336.00) 24. Deleted (266 SF) – Remove and Replace PCC Driveway Approach (Fifth Ave) ($3,192.00) 25. Deleted (2 EA) – Furnish and Installation of Traffic Signal Loops (Fifth Ave) ($2,000.00) 26. Deleted (633 SF) – Construct 2-Inch Cold Mill Grind (Camino Grove Ave) ($145.59) 27. Additional (34.64 TONS) – Construct 2-Inch ARHM Overlay (Camino Grove Ave) $2,632.65 28. Deleted (61 LF) – Remove and Replace PCC Curb and Gutter (Camino Grove Ave) ($2,745.00) Accept 2017-18 Pavement Rehabilitation Project August 7, 2018 Page 4 of 4 29. Additional (87 SF) – Remove and Replace PCC Sidewalk (Camino Grove Ave) $783.00 30. Deleted (390 SF) – Remove and Replace PCC Cross Gutter / Spandrel (Camino Grove Ave) ($5,460.00) 31. Additional Work to Reconstruct Sierra Madre Bl from Santa Anita Ave to Oakwood Dr $84,278.69 32. Additional Work for PCC repairs on El Capitan Ave and Live Oak Ave $32,671.00 Total $20,243.79 The terms and conditions of this contract have been complied with and the work has been performed to the satisfaction of the Project Manager. Hardy & Harper, Inc. completed the work as defined in the project plans and specifications in an efficient and timely manner. FISCAL IMPACT Funds in the amount of $1,530,000 were budgeted in the Fiscal Year 2017-18 Capital Improvement Program for this project, including $172,338 from the SB1 RMRA Fund, $747,662 from the Capital Outlay Fund and $610,000 from the Measure R Fund. The total cost for the Pavement Rehabilitation Project is $1,254,243.79. This amount reflects the original contract amount of $1,234,000 plus additional quantity changes totaling $20,243.79, or 1.6% more than the original contract amount. RECOMMENDATION It is recommended that the City Council accept all work performed by Hardy & Harper, Inc. for the Fiscal Year 2017-18 Pavement Rehabilitation Project as complete and authorize the final payment to be made in accordance with the contract documents, subject to retention of $62,712.19. Attachment: Exhibit “A” - Project Location Map