HomeMy WebLinkAboutItem 11f - Fiscal Year 2018-19 Pavement Rehabiliation Project
DATE: March 5, 2019
TO: Honorable Mayor and City Council
FROM: Tom Tait, Public Works Services Director
By: Eddie Chan, P.E., Principal Civil Engineer
SUBJECT: CONTRACT WITH ALL AMERICAN ASPHALT FOR THE FISCAL YEAR
2018-19 PAVEMENT REHABILITATION PROJECT IN THE AMOUNT OF
$2,517,700
Recommendation: Approve
SUMMARY
As part of the City’s Capital Improvement Program (“CIP”), the Public Works Services
Department (“PWSD”) is preparing to rehabilitate the asphalt pavement on various
streets in the City. The streets were identified in the Pavement Management Program
as the streets that most need to be rehabilitated based on their usage and Pavement
Condition Index (“PCI”). To ensure that the City is receiving the most competitive prices
and quality service for this work, the PWSD conducted a formal bid. All American
Asphalt submitted the lowest responsive bid.
It is recommended that the City Council approve, and authorize and direct the City
Manager to execute a contract with All American Asphalt for the Fiscal Year 2018-19
Pavement Rehabilitation Project in the amount of $2,517,700, and approve a 5%
contingency.
BACKGROUND
The PWSD is responsible for the maintenance and repair of approximately 147 miles of
paved streets within the City. As part of the City’s Pavement Management Program, the
conditions of all City streets were inspected and rated on a scale of 0 -100, with scores
below 40 generally being considered a street that has failed. Scores between 40 and
60 are poor/fair in nature. This rating is called the Pavement Condition Index (“PCI”) and
is used to help determine which streets require asphalt pavement rehabilitation.
According to the Citywide Pavement Management Program , the following street
segments are most in need of being addressed:
Contract for the 2018/2019 Pavement Rehabilitation Project
March 5, 2019
Page 2 of 3
Fallen Leaf Avenue from Hampton Road to Glencoe Drive -- PCI of 44
Rodeo Road from Foothill Boulevard to Hacienda Drive -- PCI of 39
Las Flores Avenue from Holly Avenue to El Monte Avenue -- PCI of 37
Las Flores Avenue from El Monte Avenue to Santa Anita Avenue -- PCI of 39
Camino Real Avenue from Santa Anita Avenue to Sixth Avenue -- PCI of 32
It should be noted that PCIs alone do not determine which streets should be
rehabilitated; for instance, the City also takes into consideration the streets that have
high traffic volume. Furthermore, it is more cost efficient to rehabilitate streets prior to
the PCI lowering to poor or very poor condition. A copy of the Project Location Map is
attached as Exhibit “A”.
DISCUSSION
The project involves the repair of any localized potholes and failed pavement, grinding
the edges of the pavement adjacent to the gutters to transition the new pavement to the
existing gutter, replacing broken curb and gutter as necessary, and installing new ADA -
compliant curb ramps at the intersections. The new pavement surface will utilize
recycled rubber in the pavement mix to help reduce future cracking and to add strength
to the asphalt pavement. The rubber in the pavement mixture also reduces road noise.
Following the repairs, the condition of these street sections will be raised to a PCI of
100. Annual concrete repair work was also included in the Pavement Rehabilitation
Project bid specification. The concrete repair work is being included to take advantage
of the economies of scale and savings of not going out to bid on this work separately.
The concrete, curb, and gutter work will be done in the Fiscal Year 2018 -19 Slurry Seal
and Pavement Rehabilitation Project area.
A Notice Inviting Bids was published in the City’s adjudicated newspaper and bid
packages were provided to contractors that perform this type of work. On February 20,
2019, the City Clerk’s office received eight bids with the following results:
Bidder Location Bid Amount
All American Asphalt Corona, CA $2,517,700.00
Onyx Paving Co. Inc. Anaheim, CA $2,627,000.00
Gentry Brothers Inc. Irwindale, CA $2,636,128.25
Sequel Contractors, Inc. Santa Fe Springs, CA $2,744,423.65
Hardy & Harper, Inc. Santa Ana, CA $2,810,000.00
Sully-Miller Contracting Co. Brea, CA $2,883,000.00
Palp, Inc. dba Excel Paving Long Beach, CA $2,954,144.65
EC Construction S. El Monte, CA $3,180,501.86
Contract for the 2018/2019 Pavement Rehabilitation Project
March 5, 2019
Page 3 of 3
Bid documents were reviewed for content and the contractor’s background was also
investigated. Based on this review, it has been determined that All American Asphalt is
the lowest responsive bidder and is qualified to complete the project as defined in the
bid documents. All American Asphalt has successfully completed similar projects on
time and within budget for several agencies such as the Cities of Inglewood, Industry,
La Palma, Los Angeles, Long Beach, and Santa Ana.
ENVIRONMENTAL ANALYSIS
This project is a Class 1 exemption pursuant to California Environmental Quality Act
(“CEQA”) Section 15301 Existing Facilities. Class 1 consists of the operation, repair,
maintenance, permitting, leasing, licensing or minor alteration of existing public or
private structures, facilities, mechanical equipment or topographical features involving
negligible or no expansion of use beyond tha t existing at the time of the lead agency’s
determination.
FISCAL IMPACT
Funds in the amount of $2,452,800 have been budgeted in the Fiscal Year 2018-19
Capital Improvement Program (“CIP”) for the Pavement Rehabilitation Project. Funds in
the amount of $200,000 have been budgeted in the Fiscal Year 2018-19 CIP for
concrete repairs as part of the Annual Slurry Seal Program. The total amount of funding
available for this project is $2,652,800. The total cost for the Fiscal Year 2018-19
Pavement Rehabilitation Project is $2,517,700. With the request of 5% construction
contingency, the project cost would be $2,643,585.
RECOMMENDATION
It is recommended that the City Council approve, and authorize and direct the City
Manager to execute a contract with All American Asphalt for the Fiscal Year 2018-19
Pavement Rehabilitation Project in the amount of $2,517,700 and approve a 5%
construction contingency.
Attachments: Exhibit “A” - Project Location Map
Proposed Contract
CITY OF ARCADIA
2018/2019 PAVEMENT REHABILITATION PROGRAM
PROJECT NO.: 33854019
BETWEEN
CITY OF ARCADIA
AND
ALL AMERICAN ASPHALT
CONTRACT
(PROJECT NO. 33854019)
Contract - 1
CONTRACT FOR THE
CITY OF ARCADIA
THIS CONTRACT is made this _____ day of _________, 20__, in the County of Los
Angeles, State of California, by and between the City of Arcadia, hereinafter called City, and All
American Asphalt, hereinafter called Contractor. The City and the Contractor for the
considerations stated herein agree as follows:
ARTICLE 1. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated
the Contract and shall provide all labor, materials, equipment, tools, utility services, and
transportation to complete all of the Work required in strict compliance with the Contract Documents
as specified in Article 5 below for the following Project:
2018/2019 Pavement Rehabilitation Program / Project No.: 33854019
The Contractor and its surety shall be liable to the City for any damages arising as a result of the
Contractor’s failure to comply with this obligation.
ARTICLE 2. TIME FOR COMPLETION.
2.1 The Work shall be commenced on the date stated in the City’s Notice to Proceed. The
Contractor shall complete all Work required by the Contract Documents within Ninety (90)
calendar days from the commencement date stated in the Notice to Proceed. By its
signature hereunder, Contractor agrees the time for completion set forth above is adequate
and reasonable to complete the Work.
2.2 Contractor shall coordinate the Work with the other work being performed on the Project, in
accordance with those schedules as may be issued from time to time during the
performance of the Work, and any other scheduling requirements listed in this Contract, so
as not to delay, impede, obstruct, hinder or interfere with the commencement, progress or
completion of the whole or any part of the Work or other work on the Project.
2.3 The Contractor shall participate and cooperate with the City in the development of schedules
and other efforts to achieve timely completion of the Work providing information for the
scheduling of the times and sequence of operations required for its Work (“Contractor
Schedule”) to meet City’s overall master project schedule requirements (“Master Schedule”).
The Contractor shall continuously monitor the Master Schedule so as to be fully familiar
with the timing, phasing and sequence of operations of the Work and of other work on the
Project, and shall execute the Work in accordance with the requirements of the Master
Schedule including any revisions thereto. The Contractor shall notify the Engineer within 48
hours of any slippage in the Contractor Schedule and shall submit a detailed recovery plan
to the Engineer for approval within five (5) calendar days of such notice.
2.4 Should the progress o f the Work or of the Project be delayed disrupted, hindered,
obstructed, or interfered with by any fault or neglect or act or failure to act of the Contractor
or any of its officers, agents, servants, employees, subcontractors or suppliers so as to
cause any additional cost, expense, liability or damage to the City, the Engineer or any
consultants retained by the City for the Project, including legal fees and disbursements
incurred by the City, the Engineer, or the consultants retained by the City for the P roject,
(whether incurred in defending claims arising from such delay or in seeking reimbursement
and indemnity from the Contractor and its surety hereunder or otherwise) or any damages or
additional costs or expenses for which the City, the Engineer or th e consultants retained by
the City for the Project, may or shall become liable, the Contractor and its surety shall and
does hereby agree to compensate the City, the Engineer or the consultants retained by the
(PROJECT NO. 33854019)
Contract - 2
City for the Project,, for and indemnify them against all such costs, expenses, damages and
liability.
2.5 The City, in its sole discretion, may direct the Contractor to work overtime and, if so directed,
the Contractor shall work said overtime and, provided that the Contractor is not in default
under any of the terms or provisions of this Contract or of any of the other Contract
Documents, the City will pay the Contractor for such actual additional wages paid, if any, at
the prevailing wage rates plus taxes imposed by law on such additional wages, plu s
workers' compensation insurance, liability insurance and levies on such additional wages if
required to be paid by the Contractor.
2.6 If, however, the progress of the Work or of the Project is delayed by any fault or neglect or
act or failure to act of the Contractor or any of its officers, agents, servants, employees,
subcontractors or suppliers, then the Contractor shall, in addition to all of the other
obligations imposed by this Contract upon the Contractor in such case, and at its own cost
and expense, work such overtime as may be necessary to make up for all time lost in the
completion of the Work and of the Project due to such delay. Should the Contractor fail to
make up for the time lost by reason of such delay, the Engineer or City shall have th e right
to cause other contractors to work overtime and to take whatever other action it deems
necessary to avoid delay in the completion of the Work and of the Project, and the cost and
expense of such overtime and/or such other action shall be borne sole ly by the Contractor.
ARTICLE 3. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for
the performance of the Contract, subject to any additions or deductions as provided in the Contract
Documents, and including all applicable taxes and costs , the sum of TWO MILLION, FIVE
HUNDRED SEVENTEEN THOUSAND, SEVEN HUNDRED DOLLARS AND NO CENTS
($2,517,700.00). Payment shall be made as set forth in the General Conditions.
ARTICLE 4. PAYMENTS
4.1 The City shall make monthly progress payments following receipt of undisputed and properly
submitted payment requests. Contractor shall be paid a sum equal to ninety-five percent
(95%) of the value of Work performed up to the last day of the previous month, less the
aggregate of previous payments.
4.2 The Contractor shall, after the full completion of The Work, submit a final payment
application. All prior progress estimates shall be subject to correction in the final estimate
and payment.
4.3 Unless otherwise required by law, the final payment of five percent (5%) of the value of the
Work, if unencumbered, shall be paid no later than sixty (60) Days after the date of
recordation of the Notice of Completion.
4.4 Acceptance by Contractor of the final payment shall constitute a waiver of all claims against
the City arising from this Contract.
4.5 Payments to the Contractor shall not be construed to be an acceptance of any defective
work or improper materials, or to relieve the Contractor of its obligations under the Contract
Documents.
4.6 The Contractor shall submit with each payment request the Contractor’s conditional waiver
of lien for the entire amount covered by such payment request, as well as a valid
unconditional waiver of lien from the Contractor and all subcontractors and materialmen for
all work and materials included in any prior invoices. Waivers of lien shall be in the forms
(PROJECT NO. 33854019)
Contract - 3
prescribed by California Civil Code sections 8132, 8134, 8136, and 8138. Prior to final
payment by the City, the Contractor shall submit a final waiver of lien for the Contractor’s
work, together with releases of lien from any subcontractor or materialmen.
ARTICLE 5. PAYMENTS WITHHELD AND BACKCHARGES In addition to amounts which the
City may retain under other provisions of the Contract Documents the City may withhold payments
due to Contractor as may be necessary to cover:
a. Stop Notice Claims.
b. Defective work not remedied.
c. Failure of Contractor to make proper payments to its subcontractors or suppliers.
d. Completion of the Contract if there exists a reasonable doubt that the Work can be
completed for balance then unpaid.
e. Damage to another contractor or third party.
f. Amounts which may be due the City for claims against Contractor.
g. Failure of Contractor to keep the record (“as-built”) drawings up to date.
h. Failure to provide updates on the construction schedule.
i. Site clean-up.
j. Failure of the Contractor to comply with requirements of the Contract Documents.
k. Liquated damages.
l. Legally permitted penalties.
Upon completion of the Contract, the City will reduce the final Contr act amount to reflect costs
charged to the Contractor, backcharges or payments withheld pursuant to the Contract Documents.
ARTICLE 6. CHANGES AND EXTRA WORK
6.1 The City, without invalidating the Contract, may order changes in the Work consisting of
additions, deletions or other revisions, the Contract amount and Contract time being
adjusted accordingly. All such changes in the Work shall be authorized by Change Order, in
the form attached hereto and incorporated herein as Exhibit “A,” and shall be performed
under the applicable conditions of the Contract Documents. A Change Order signed by the
Contractor indicates the Contractor's agreement therewith, including any adjustment in the
Contract amount or the Contract time, and the full and final settlement of all cost s (direct,
indirect and overhead) related to the Work authorized by the Change Order.
6.2 All claims for additional compensation to the Contractor shall be presented in writing before
the expense is incurred and will be adjusted as provided herein. No wor k shall be allowed
to lag pending such adjustment, but shall be promptly executed as directed, even if a
dispute arises. No claim will be considered after the work in question has been done unless
a written contract change order has been issued or a timel y written notice of claim has been
made by Contractor. Contractor shall not be entitled to claim or bring suit for damages,
whether for loss of profits or otherwise, on account of any decrease or omission of any item
(PROJECT NO. 33854019)
Contract - 4
or portion of Work to be done. Whenever any change is made as provided for herein, such
change shall be considered and treated as though originally included in the Contract, and
shall be subject to all terms, conditions and provisions of the original Contract.
6.3 Owner Initiated Change. The Contractor must submit a complete cost proposal, including
any change in the Contract time, within seven (7) Days after receipt of a scope of a
proposed change order, unless the City requests that proposals be submitted in less than
seven (7) Days.
6.4 Contractor Initiated Change. The Contractor must give written notice of a proposed change
order required for compliance with the Contract Documents within seven (7) Days of
discovery of the facts giving rise to the proposed change order.
6.5 Whenever possible, any changes to the Contract amount shall be in a lump sum mutually
agreed to by the Contractor and the City.
6.6 Price quotations from the Contractor shall be accompanied by sufficiently detailed
supporting documentation to permit verification by the C ity.
6.7 If the Contractor fails to submit the cost proposal within the seven (7) Day period (or as
requested), the City has the right to order the Contractor in writing to commence the work
immediately on a force account basis and/or issue a lump sum chan ge to the contract price
in accordance with the City’s estimate of cost. If the change is issued based on the City
estimate, the Contractor will waive its right to dispute the action unless within fifteen (15)
Days following completion of the added/deleted work, the Contractor presents written proof
that the City’s estimate was in error.
6.8 Estimates for lump sum quotations and accounting for cost -plus-percentage work shall be
limited to direct expenditures necessitated specifically by the subject extra w ork, and shall
be segregated as follows:
(a) Labor. The costs of labor will be the actual cost for wages prevailing locally
for each craft or type of worker at the time the extra work is done, plus
employer payments of payroll taxes and insurance, health and welfare,
pension, vacation, apprenticeship funds, and other direct costs resulting from
Federal, State or local laws, as well as assessment or benefits required by
lawful collective bargaining agreements. The use of a labor classification
which would increase the extra work cost will not be permitted unless the
contractor establishes the necessity for such additional costs. Labor costs
for equipment operators and helpers shall be reported only when such costs
are not included in the invoice for equipm ent rental.
(b) Materials. The cost of materials reported shall be at invoice or lowest current
price at which such materials are locally available in the quantities involved,
plus sales tax, freight and delivery. Materials cost shall be based upon
supplier or manufacturer’s invoice. If invoices or other satisfactory evidence
of cost are not furnished within fifteen (15) Days of delivery, then the
Engineer shall determine the materials cost, at its sole discretion.
(c) Tool and Equipment Use. No payment will be made for the use of small
tools, tools which have a replacement value of $1,000 or less. Regardless of
ownership, the rates to be used in determining equipment use costs shall not
exceed listed rates prevailing locally at equipment rental agencie s, or
distributors, at the time the work is performed.
(PROJECT NO. 33854019)
Contract - 5
(d) Overhead, Profit and Other Charges. The mark -up for overhead (including
supervision) and profit on work added to the Contract shall be according to
the following:
i. “Net Cost” is defined as consisting of costs of labor, materials and tools and
equipment only excluding overhead and profit. The costs of applicable insurance
and bond premium will be reimbursed to the Contractor and subcontractors at cost
only, without mark-up.
ii. For Work performed by the Contractor’s forces the added cost for overhead and
profit shall not exceed fifteen (15%) percent of the Net Cost of the Work.
iii. For Work performed by a subcontractor, the added cost for overhead and profit shall
not exceed fifteen (15%) percent of the Net Cost of the Work to which the Contractor
may add five (5%) percent of the subcontractor’s Net Cost.
iv. For Work performed by a sub-subcontractor the added cost for overhead and profit
shall not exceed fifteen (15%) percent of the Net Cost for Work to which the
subcontractor and general contractor may each add an additional five (5%) percent
of the Net Cost of the lower tier subcontractor.
v. No additional mark up will be allowed for lower tier subcontractors, and in no case
shall the added cost for overhead and profit payable by City exceed twenty-five
(25%) percent of the Net Cost as defined herein.
6.9 For added or deducted Work by subcontractors, the Contractor shall furnish to the
City the subcontractor’s signed detailed estimate of the cost of labor, material and
equipment, including the subcontractor markup for overhead and profit. The same
requirement shall apply to sub-subcontractors.
6.10 For added or deducted work furnished by a vendor or supplier, the Contractor shall
furnish to the City a detailed estimate or quotation of the cost to the Contractor,
signed by such vendor or supplier.
6.11 Any change in The Work involving both additions and deletions shall indicate a net
total cost, including subcontracts and materials. Allowance for overhead and profit,
as specified herein, shall be applied if the net total cost is an extra; overhead and
profit allowances shall not be applied if the net total cost is a credit. The estimated
cost of deductions shall be based on labor and material pric es on the date the
Contract was executed.
6.12 Contractor shall not reserve a right to assert impact costs, extended job site costs,
extended overhead, constructive acceleration and/or actual acceleration beyond
what is stated in the change order for work. No claims shall be allowed for impact,
extended overhead costs, constructive acceleration and/or actual acceleration due to
a multiplicity of changes and/or clarifications. The Contractor may not change or
modify the City’s change order form in an attem pt to reserve additional rights.
6.13 If the City disagrees with the proposal submitted by Contractor, it will notify the
Contractor and the City will provide its opinion of the appropriate price and/or time
extension. If the Contractor agrees with the City, a change order will be issued by
the City. If no agreement can be reached, the City shall have the right to issue a
unilateral change order setting forth its determination of the reasonable additions or
savings in costs and time attributable to the ex tra or deleted work. Such
(PROJECT NO. 33854019)
Contract - 6
determination shall become final and binding if the Contractor fails to submit a claim
in writing to the City within fifteen (15) Days of the issuance of the unilateral change
order, disputing the terms of the unilateral change o rder.
6.14 No dispute, disagreement or failure of the parties to reach agreement on the terms of
the change order shall relieve the Contractor from the obligation to proceed with
performance of the work, including extra work, promptly and expeditiously.
6.15 Any alterations, extensions of time, extra work or any other changes may be made
without securing consent of the Contractor’s surety or sureties.
ARTICLE 7. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85,
it is agreed that the Contractor will pay the City the sum of $3,000.00 for each and every calendar
day of delay beyond the time prescribed in the Contract Documents for finishing the Work, as
Liquidated Damages and not as a penalty or forfeiture. In the event this is not paid, the Con tractor
agrees the City may deduct that amount from any money due or that may become due the
Contractor under the Contract. This Article does not exclude recovery of other damages specified in
the Contract Documents.
ARTICLE 8. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the
following:
Notice Inviting Bids
Instructions to Bidders
Contractor's Bid Forms
Contractor’s Certificate Regarding Workers’ Compensation
Bid Bond
Designation of Subcontractors
Information Required of Bidders
Non-Collusion Declaration form
Iran Contracting Act Certification form
Public Works Contractor Registration Certification form
Contract
Performance Bond
Payment (Labor and Materials) Bond
General Conditions
Special Provisions (or Special Conditions)
Technical Specifications
California Building Codes as defined in the General Conditions
Addenda
Plans and Contract Drawings
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract
The Contactor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the
Contract Documents and not by others shall be done as if required by all. This Contract shall
supersede any prior agreement of the parties.
ARTICLE 9. PROVISIONS REQUIRED BY LAW. Each and every provision of law required to be
included in these Contract Documents shall be deemed to be included in these Contract
Documents. The Contractor shall comply with all requirements o f applicable federal, state and local
(PROJECT NO. 33854019)
Contract - 7
laws, rules and regulations, including, but not limited to, the provisions of the California Labor Code
and California Public Contract Code which are applicable to this Project.
ARTICLE 10. INDEMNIFICATION.
10.1 To the fullest extent permitted by law, the Contractor shall defend, indemnify and hold
harmless the City, its respective officials, officers, agents, employees, and representatives
(“Indemnitees”) from any and all claims, demands, causes of action, costs, expenses,
liabilities, losses, damages (including without limitation the payment of all consequential
damages and attorneys fees and other related costs and expenses) or injuries, in law or
equity, regardless of whether the allegations are false, fraudulent, or groundles s, to tangible
property or persons (including wrongful death, accidents or injuries arising from the alleged
failure to inspect or to maintain traffic controllers or traffic signals, injuries or damages
occurring during the transport of products or in rend ering services under the Contract
Documents, such as automobile accidents, trip/slip and fall accidents and third party
assaults) arising out of or resulting from the performance of the Work or this Contract
(including claims made by subcontractors for nonpayment), to the extent that the acts,
omissions or willful misconduct are attributable to the Contractor or anyone employed
directly or indirectly by any of them. Contractor shall defend, at Contractor’s own cost,
expense and risk, with legal counsel of Indemnitee’s choosing, any and all such aforesaid
suits, actions or other legal proceedings of every kind that may be brought or instituted
against the City, its respective officials, officers, agents, employees and representatives. To
the extent of its liability, Contractor shall pay and satisfy any judgment, award or decree that
may be rendered against the City and its respective officials, officers, agents, employees,
and representatives, in any such suit, action or other legal proceeding. Contractor s hall
reimburse the City and its respective officials, officers, agents, employees, and
representatives for any and all legal expenses and costs incurred by each of them in
connection therewith or in enforcing the indemnity herein provided. The only limita tions on
this provision shall be those imposed by Civil Code section 2782.
10.2 The duty to defend and to hold harmless, as set forth above, shall include the duty to defend
as established by Section 2778 of the California Civil Code, and the duty to defen d shall
arise upon the making of any claim or demand against the City, its respective officials,
officers, agents, employees and representatives, notwithstanding that no adjudication of the
underlying facts has occurred, and whether or not Contractor has b een named in the claim
or lawsuit.
10.3 Nothing contained in the preceding sections shall be deemed to obligate the Contractor to
indemnify the City or any of the other Indemnitees, against liability for damages or any other
loss, damage or expense sustain ed, suffered or incurred on account of death or bodily injury
to active persons or injury to property caused by the sole negligence or willful misconduct of
the City or any of the other Indemnitees set forth above. Therefore, if it is determined by
legal proceedings or agreement, that the Contractor has no direct contributory or incidental
negligence or other obligation to the City or the other Indemnitees, and the Contractor is in
no way a proper party to a particular claim, then the Contractor shall not be obligated to hold
the City or any Indemnitees harmless with respect to said claim. However, until such
determination is made by legal proceedings or agreement, or if the Contractor is found to
have any degree of direct or contributory negligence or if it is determined that the Contractor
is in any way or to any degree a proper party to said claim, then the Contractor’s obligations
under all of the terms and provisions of the preceding section shall remain in full force and
effect.
10.4 Nothing in this provision, or elsewhere in the Contract Documents, shall be deemed to
relieve the Contractor of its duty to defend the City or any Indemnitee, as specified under
(PROJECT NO. 33854019)
Contract - 8
this Article, pending a determination of the respective liabilities of the City or any Indemnitee,
by legal proceeding or agreement.
10.5 In furtherance to, but not in limitation of the indemnity provisions in this Contract, Contractor
hereby expressly and specifically agrees that its obligation to indemnify, defend and hold
harmless as provided in this Contract shall not in any way be affected or diminished by any
statutory or constitutional immunity it enjoys from suits by its own employees or from
limitations of liability or recovery under workers’ compensation laws.
ARTICLE 11. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of
wages in accordance with the Labor Code which such rates shall be made available at the Public
Works Services Department or may be obtained online at http//www.dir.ca.gov/dlsr and which must
be posted at the job site.
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on the
day and year above written.
CITY OF ARCADIA
By:
Dominic Lazzaretto
City Manager
ALL AMERICAN ASPHALT
By:
Signature
Print Name and Title
Attest:
By:
City Clerk
By:
Signature
Print Name and Title
Approved as to Form:
Stephen P. Deitsch
City Attorney