HomeMy WebLinkAboutItem 11l - Accept Traffic Signal Improvements Project
DATE: January 21, 2020
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director
Philip A. Wray, Deputy Director of Development Services/City Engineer
By: Kevin Merrill, Principal Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY BELCO ELECNOR GROUP FOR
TRAFFIC SIGNAL IMPROVEMENTS, INCLUDING TRAFFIC
SIGNALIZATION AND CROSSWALK MODIFICATIONS AT DUARTE
ROAD AND LOVELL AVENUE, TRAFFIC SIGNALIZATION AT SUNSET
BOULEVARD AND FAIRVIEW AVENUE, AND TRAFFIC SIGNAL
IMPROVEMENTS AT HUNTINGTON DRIVE AND SECOND AVENUE,
AS COMPLETE
Recommendation: Approve
SUMMARY
On August 21, 2018, the City Council awarded a contract to Belco Elecnor Group, in the
amount of $873,774, plus a 10% contingency, for traffic signal improvements, including
traffic signalization and crosswalk modifications at Duarte Road and Lovell Avenue,
traffic signalization at Sunset Boulevard and Fairview Avenue, and traffic signal
improvements at Huntington Drive and Second Avenue. There were six (6) change
orders on the project in the amount of $47,462.33, or 5.43%. With the adjustment for
change orders and actual quantities, the final contract amount is $921,236.33, which is
within the total authorized amount.
The terms and conditions of this project have been complied with, and the required work
has been performed to staff’s satisfaction. It is recommended that the City Council
accept the project as complete, and authorize the final payment in accordance with the
contract documents.
BACKGROUND
This project proposed traffic signal improvements at multiple locations. The
improvements included the installation of two new traffic signals at the intersections of
Duarte Road and Lovell Avenue, and Sunset Boulevard and Fairview Avenue, the
removal of the crosswalk and flashing warning light system on Duarte Road,
approximately 600 feet east of Baldwin Avenue, and the addition of a
Accept Traffic Signalization at Duarte Road/Lovell Avenue, Sunset Blvd./Fairview
Avenue, and Traffic Signal Improvements at Huntington Drive/Second Avenue
January 21, 2020
Page 2 of 3
protected/permissive left turn phase to the traffic signal at Huntington Drive and Second
Avenue.
The plans and specifications were completed in May 2018, and the project was
advertised for bids in July 2018. On August 21, 2018, the City Council awarded a
contract to Belco Elecnor Group, in the amount of $873,774, plus a 10% contingency.
DISCUSSION
The construction began in November 2018, and was ultimately completed in December
2019. The project was delayed several months due to the long equipment delivery time
period, and the wait for Southern California Edison to remove its streetlights. The
project was completed to the City’s satisfaction.
There were six (6) change orders on the project, totaling $47,462.33, or 5.43% of the
original contract amount. The first change order was for the early removal of the mid-
block crosswalk on Duarte Road approximately 600 feet east of Baldwin Avenue. This
was because of the City’s desire to remove the crosswalk and lighted warning system
immediately after approval of the contract.
The second and third change orders were for the purchase and installation of a small
mast arm and reflective street name sign for Duarte Road at the intersection of Duarte
Road and Lovell Avenue. This was inadvertently left off the plans, but is important and
necessary for the street name identification.
The fourth change order was for the boring and installation of approximately 320 feet of
conduit along the west side of Santa Anita Avenue from Colorado Boulevard south to
the north side of the Santa Anita Bridge. This work was to provide a connection from
the decorative LED bridge lights controller to the City’s fiber optics network. Since the
contractor was already installing conduit as part of the project for the communication
network connections to the two new signals, it benefited the City to have the additional
conduit installed for the bridge lighting connection.
The fifth change order was for additional work required to install a signal pole at the
Huntington Drive and Second Avenue intersection. Due to a pocket of sandy soil
conditions, the contractor had no choice but to over-excavate, refill with a slurry mix,
and re-excavate for the pole foundation.
The sixth and final change order was for adjustments to the original bid quantities for
the removal and replacement of additional curbs, gutters, sidewalks, asphalt pavement,
and landscaping based on the bid unit prices, and for the lowering of the two horizontal
five-section heads in the north and southbound directions of Second Avenue at
Huntington Drive for the protected/permissive phase signal function. Upon installation
of the horizontal heads, it was determined that their sightlines could be improved under
the bridge by lowering them slightly and still maintaining minimum vertical clearances.
Accept Traffic Signalization at Duarte Road/Lovell Avenue, Sunset Blvd./Fairview
Avenue, and Traffic Signal Improvements at Huntington Drive/Second Avenue
January 21, 2020
Page 3 of 3
A summary of the change order costs is as follows:
Original Contract: $873,774.00
CO #1 $2,000.00
CO #2 $1,700.00
CO #3 $850.00
CO #4 $20,311.41
CO #5 $8,226.44
CO #6 $14,374.48
COs Sub Total: $47,462.33
Final Total Contract: $921,236.33
These change orders brought the final construction total to $921,236.33, which is within
the approved 10% contingency.
FISCAL IMPACT
The traffic signalization and crosswalk modifications at Duarte Road and Lovell Avenue,
traffic signalization at Sunset Boulevard and Fairview Avenue, and traffic signal
improvements at Huntington Drive and Second Avenue projects were budgeted as
separate projects in multiple fiscal years within the Capital Improvement Program (FY
2015-2019). The total budget for all projects was $1,050,000, with $100,000 from
Capital Outlay funds and $950,000 from Transportation Impact funds. Design services
were in the amount of $72,806, leaving a balance of approximately $977,000. There
are sufficient funds to cover the final cost of $921,236.33.
RECOMMENDATION
It is recommended that the City Council accept all work performed by Belco Elecnor
Group for traffic signal improvements, including traffic signalization and crosswalk
modifications at Duarte Road and Lovell Avenue, traffic signalization at Sunset
Boulevard and Fairview Avenue, and traffic signal improvements at Huntington Drive
and Second Avenue, as complete; and authorize the final payment to be made in
accordance with the contract documents.