HomeMy WebLinkAboutItem 12h - Baldwin Avenue Sewer Capacity Improvement ProjectAward Baldwin Avenue Sewer Capacity Improvement Project
July 21, 2020
Page 1 of 3
DATE: July 21, 2020
TO: Honorable Mayor and City Council
FROM: Tom Tait, Public Works Services Director
By: Eddie Chan, P.E., Principal Civil Engineer
SUBJECT: REJECT LOW BID FROM CEM CONSTRUCTION CORP. AND
CONTRACT WITH GRBCON, INC. FOR THE BALDWIN AVENUE SEWER
CAPACITY IMPROVEMENT PROJECT IN THE AMOUNT OF $424,465
Recommendation: Approve
SUMMARY
Based on the City’s Sewer Master Plan, the section of sewer pipe on Baldwin Avenue
between Fairview Avenue and Duarte Road needs to be replaced in order to
accommodate peak sewer flows. The Fiscal Year 2019-20 Capital Improvement Program
budget allocates funding to replace the existing 12-inch sewer pipe with a 16-inch sewer
pipe.
To ensure that the City is receiving the most competitive price and quality service for this
work, a formal bid was conducted and CEM Construction Corp. submitted the lowest bid.
During the bid evaluation process, it was discovered that CEM Construction Corp. did not
provide evidence of enough experience required to perform the work. As a result, it was
determined that CEM Construction Corp. bid was non-responsive. GRBCON, Inc. was
the second lowest bid received and their bid was determined to be responsive.
It is recommended that the City Council reject the low bid from CEM Construction Corp.,
and approve, authorize, and direct the City Manager to execute a Contract with GRBCON,
Inc. for the Baldwin Avenue Sewer Capacity Improvement Project in the amount of
$424,465, including a 10% contingency.
BACKGROUND
In 2006, the State Water Resources Control Board adopted the Waste Discharge
Requirement Program for all publicly-owned sanitary sewer collection systems in
California with more than one mile of sewer pipeline. Under this program, the City was
Award Baldwin Avenue Sewer Capacity Improvement Project
July 21, 2020
Page 2 of 3
required to prepare and implement a Sewer System Management Plan (“SSMP”). The
SSMP identifies routine preventative operation and maintenance activities that assist the
City in achieving a goal of zero sewer system overflows. This is achieved through annual
inspections, routine cleaning of the sewer pipes, repair of broken pipes, and replacement
of pipes flowing above their design capacity.
The City of Arcadia’s 2006 Sewer Master Plan Update identified sections of sanitary
sewer pipe on Baldwin Avenue as inadequate in accommodating the current high demand
flows and is at risk of experiencing sewer overflows. The existing 12-inch sewer pipe
along Baldwin Avenue between Fairview Avenue and Duarte Road was installed in 1949
and is 71 years old. This section of sewer pipe will be replaced with a 16-inch sewer pipe
to alleviate the potential of a sewer back up and overflow. In-ground pipe bursting will be
used to replace the existing 12-inch pipe in order to reduce the excavation required to
replace the existing sewer pipe as well as to reduce the disruption to traffic along Baldwin
Avenue, Duarte Road, Arcadia Avenue, and Fairview Avenue. The work is anticipated to
begin in August, and construction will take approximately two months to complete. A copy
of the Project Location Map is shown on Exhibit “A”.
DISCUSSION
A Notice Inviting Bids was published in the City’s adjudicated newspaper, and bid
packages were provided to contractors that perform this type of work. On June 2, 2020,
the City Clerk received seven bids with the following results:
Bidder Location Bid Amount___
CEM Construction Corp. Downey, CA $ 417,650
GRBCON, Inc. Baldwin Park, CA $ 424,465
Mike Prlich & Sons, Inc. Baldwin Park, CA $ 448,420
Kordich Construction, Inc. Cypress, CA $ 550,420
GRFCO, Inc. Brea, CA $ 579,400
MNR Construction, Inc. La Verne, CA $ 686,625
Ramona, Inc. Baldwin Park, CA $ 739,500
All bid documents were reviewed for content. CEM Construction Corp. submitted the
lowest bid. Consequently, during the bid evaluation process, it was discovered that their
bid did not list any projects which demonstrated that they had the ability and experience
to perform the required work. CEM Construction Corp. was contacted after the bid
opening and given another opportunity to provide evidence showing that they could
perform the work. However, they were still unable to provide the requested evidence and
were willing to withdraw their bid.
As a result, the second low bidder, GRBCON, Inc. is considered the lowest responsive
bidder. The bid submitted by GRBCON, Inc. was reviewed for content, and the
Award Baldwin Avenue Sewer Capacity Improvement Project
July 21, 2020
Page 3 of 3
contractor’s background was also investigated. Based on this review, it has been
determined that GRBCON, Inc. is the lowest responsive bid, and is qualified to complete
the project as defined in the bid documents. GRBCON, Inc. has successfully completed
similar projects on time and within budget for the Cities of Norwalk, Bradbury, and Los
Angeles.
ENVIRONMENTAL ANALYSIS
This project involves the replacement and minor alteration of an existing utility system
with no expansion of the system and, therefore, qualifies as a Class 2 categorical
exemption per Section 15302(c) of the California Environmental Quality Act.
FISCAL IMPACT
Funds in the amount of $750,000 have been budgeted in the Fiscal Year 2019-20 Capital
Improvement Program for this project. The total cost for this project is $424,465. With
the request of 10% construction contingency, the project cost would be $466,911.50,
which is within the adopted budget.
RECOMMENDATION
It is recommended that the City Council determine the project to be categorically exempt
pursuant to the requirements of the California Environmental Quality Act (“CEQA”), reject
the low bid from CEM Construction Corp., and approve, authorize, and direct the City
Manager to execute a contract with GRBCON, Inc. for the Baldwin Avenue Sewer
Capacity Improvement Project in the amount of $424,465, including a 10% contingency.
Attachments: Exhibit “A” - Project Location Map
Proposed Contract
Contract - 1
CONTRACT FOR THE
CITY OF ARCADIA
This CONTRACT, No. ________ is made and entered into this ____ day of _______, 2020, by
and between City of Arcadia, sometimes hereinafter called “City,” and GRBCON, Inc., sometimes
hereinafter called “Contractor.”
WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these
presents do covenant and agree with each other as follows:
A. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated in the
Contract, and shall provide all labor, materials, equipment, tools, utility services, and
transportation to complete all of the Work required in strict compliance with the Contract
Documents as specified in Article 5, below, for the following Project:
Baldwin Avenue Sewer Capacity Improvement Project; Project No.: 33861820
The Contractor and its surety shall be liable to the City for any damages arising as a result of
the Contractor’s failure to comply with this obligation.
B. TIME FOR COMPLETION. Time is of the essence in the performance of the Work. The Work
shall be commenced on the date stated in the City’s Notice to Proceed. The Contractor shall
complete all Work required by the Contract Documents within 60 calendar days from the
commencement date stated in the Notice to Proceed. By its signature hereunder, Contractor
agrees the time for completion set forth above is adequate and reasonable to complete the Work.
C. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for the
performance of the Contract, subject to any additions or deductions as provided in the Contract
Documents, and including all applicable taxes and costs, the sum of Four Hundred Twenty-Four
Thousand, Four Hundred Sixty-Five Dollars and No Cents, ($424,465.00). Payment shall be
made as set forth in the General Conditions.
D. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85, it is
agreed that the Contractor will pay the City the sum set forth in Special Conditions, Article 1.11
for each and every calendar day of delay beyond the time prescribed in the Contract Documents
for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this
is not paid, the Contractor agrees the City may deduct that amount from any money due or that
may become due the Contractor under the Contract. This Article does not exclude recovery of
other damages specified in the Contract Documents.
E. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the
following:
Notice Inviting Bids
Instructions to Bidders
Bid Form
Bid Bond
Designation of Subcontractors
Information Required of Bidders
Non-Collusion Declaration Form
Iran Contracting Act Certification
Public Works Contractor Registration Certification
Performance Bond
Contract - 2
Payment (Labor and Materials) Bond
General Conditions
Special Conditions
Technical Specifications
Addenda
Plans and Drawings
Standard Specifications for Public Works Construction “Greenbook”, latest edition, Except
Sections 1-9
Applicable Local Agency Standards and Specifications, as last revised
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract
The Contractor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the
Contract Documents and not by others shall be done as if required by all. This Contract shall
supersede any prior agreement of the parties.
F. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE. Each and every
provision of law required to be included in these Contract Documents shall be deemed to be
included in these Contract Documents. The Contractor shall comply with all requirements of
applicable federal, state and local laws, rules and regulations, including, but not limited to, the
provisions of the California Labor Code and California Public Contract Code which are applicable
to this Work.
G. INDEMNIFICATION. Contractor shall provide indemnification and defense as set forth in the
General Conditions.
H. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in
accordance with the Labor Code which such rates shall be made available at the City’s
Administrative Office or may be obtained online at dir.ca.gov and which must be posted at the job
site.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
Contract - 3
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on
the day and year above written.
CITY OF ARCADIA
By: ______________________________
Dominic Lazzaretto
City Manager
GRBCON, INC.
By: _______________________________
Signature
________________________________
Print Name and Title
Attest:
By: ______________________________
City Clerk
By: _______________________________
Signature
_______________________________
Print Name and Title
Approved as to Form:
Stephen P. Deitsch
City Attorney