HomeMy WebLinkAboutItem 11g - Pavement Rehabilitation of Huntington Drive and 2019 Miscellaneous Arterial Rehabilitation
DATE: August 4, 2020
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director
Philip A. Wray, Deputy Director of Development Services/City Engineer
By: Kevin Merrill, Principal Civil Engineer
SUBJECT: CONTRACT WITH HARDY & HARPER, INC. FOR THE PAVEMENT
REHABILITATION OF HUNTINGTON DRIVE BETWEEN SANTA CLARA
STREET AND FIFTH AVENUE, AND 2019 MISCELLANEOUS ARTERIAL
REHABILITATION IN THE AMOUNT OF $1,796,000
Recommendation: Approve
SUMMARY
As part of the City’s ongoing Pavement Management Program, the City annually
appropriates Proposition C funding for arterial repaving projects. For the Fiscal Year
2017-18 Capital Improvement Program (“CIP”), the City Council appropriated funding for
the rehabilitation of Huntington Drive between Santa Clara Street and Fifth Avenue, as
well as traffic signal improvements and other repairs and amenities. The traffic signal
work was bid separately last year to get it completed before the pavement rehabilitation
takes place. That work is now complete.
For the Fiscal Year 2018-19 CIP, the City Council appropriated funding for the
Miscellaneous Arterial Rehabilitation Project. This project is intended to include short
segments of arterial streets that for various reasons require pavement rehabilitation.
Because of the similar nature of this project and the Huntington Drive Pavement
Rehabilitation Project, it was decided to combine them into one project for potentially
better bid results and for ease of administration.
The combined Pavement Rehabilitation Project was advertised for bidding in June 2020,
and bids were opened on June 30, 2020. Six (6) bids were received, and Hardy & Harper,
Inc. submitted the successful low bid in the amount of $1,796,000. It is recommended
that the City Council find the project categorically exempt pursuant to the requirements of
the California Environmental Quality Act (“CEQA”), and authorize and direct the City
Manager to execute a contract with Hardy & Harper, Inc., for the Pavement Rehabilitation
of Huntington Drive between Santa Clara Street and Fifth Avenue, and the 2019
Huntington Drive Rehab and
Miscellaneous Arterial Street Improvements
August 4, 2020
Page 2 of 4
Miscellaneous Arterial Rehabilitation in the amount of $1,796,000, with a 10%
contingency.
BACKGROUND
The City annually appropriates Proposition C funding for arterial street pavement projects.
The City’s Pavement Management Program, which analyzes the existing condition of
street pavement, has identified Huntington Drive between Santa Clara Street and Fifth
Avenue as the highest priority arterial street for repair. This segment of Huntington Drive
has an average Pavement Condition Index (“PCI”) rating of 57, with 100 being best, and
zero being worst.
For the Fiscal Year 2017-18 CIP, the City Council appropriated funding for the Arterial
Pavement Rehabilitation of Huntington Drive between Santa Clara Street and Fifth
Avenue. The rehabilitation will include removing and replacing isolated sections of
pavement and grinding and resurfacing the entire street with 1-1/2 inches of new asphalt.
The project includes other elements such as traffic signal improvements, sidewalk,
driveway, curb and gutter repairs, drainage improvements, additional electrical service
conduit installation for street center median decorations, and the removal of the
decorative crosswalk at Morlan Place.
The traffic signal improvements include the two new pedestrian traffic signals at the mid-
block crosswalks between Santa Anita Avenue and Second Avenue, and miscellaneous
signal improvements at other Huntington Drive signalized intersections. The project was
divided into two phases because of the need to get the traffic signal work completed
before any street work takes place. That work was awarded by the City Council on
February 5, 2019, to Elecnor Belco Group in the amount of $658,472, and is now
complete.
For the Fiscal Year 2018-19 CIP, the City Council appropriated funding for the
Miscellaneous Arterial Rehabilitation Project. This project is intended to include three
streets isolated segments that need pavement rehabilitation as follows:
• Duarte Road between Santa Anita Avenue and First Avenue – This segment
was left out of a previous Duarte Road repaving project because of the adjacent
private development under construction at the time.
• Santa Anita Avenue between Santa Clara Street and Huntington Drive – This
segment needs repair because of the many utility cuts that have been made.
• Santa Clara Street between Santa Anita Avenue and Huntington Drive – This
segment needs repair because of the many utility cuts that have been made and
the need to modify the existing striping.
Huntington Drive Rehab and
Miscellaneous Arterial Street Improvements
August 4, 2020
Page 3 of 4
Because of the similar nature of the two rehabilitation projects, it was decided to combine
them into one project for potentially better bid results and for ease of administration.
On September 4, 2018, the City Council approved a Professional Services Agreement
with Kreuzer Consulting Group for project design services. The City’s Downtown Arcadia
Improvement Association participated in the design process for the electrical services to
the center medians. They will take responsibility for completing the electrical services to
the medians on Huntington Drive between Santa Anita Avenue and Second Avenue. The
City will be responsible for the electrical services to the medians between Santa Clara
Street and Santa Anita Avenue. The final design was completed in December 2019.
DISCUSSION
The project was advertised for bids in June 2020, and bids were opened on June 30,
2020. Bids were received from six (6) prospective contractors with the following results:
NAME AMOUNT
Hardy & Harper $1,796,000.00
Gentry Brothers Inc. $1,828,580.26
All American Asphalt $1,909,057.12
Sully Miller Contracting $1,996,000.00
Palp Inc., dba Excel Paving $2,082,078.77
Onyx Paving Co., Inc. $2,524,000.00
After reviewing the bid documents, Hardy & Harper, Inc. was determined to be the lowest
responsible bidder. Hardy & Harper has been in existence for many years and is a very
competent contractor. They have performed work for the City in the past with favorable
results. Based on these results, it is determined that Hardy & Harper can satisfactorily
perform the required work.
It should be noted that Council Member Verlato owns property at 33 E. Huntington Drive,
which is in the proposed project limits of Huntington Drive between Santa Clara Street
and Fifth Avenue. As a result, the City Attorney recommends that Council Member
Verlato recuse herself from this action.
ENVIRONMENTAL IMPACT
This project is categorically exempt per Section 15301(c) of the California Environmental
Quality Act (“CEQA”), as repair and maintenance of an existing highway or street.
FISCAL IMPACT
The funding breakdown for the overall project is as follows:
Huntington Drive Rehab and
Miscellaneous Arterial Street Improvements
August 4, 2020
Page 4 of 4
PROJECT BUDGET FY FUND
Arterial Rehab Program - Huntington Dr $500,000 2017-18 Capital Outlay
Arterial Rehab Program - Huntington Dr $800,000 2017-18 Prop. C
Arterial Rehab Program - Huntington Dr $450,000 2018-19 Prop. C
Arterial Rehab Program - Huntington Dr
(Traffic Signal Improvements including 2
new mid-block traffic signals)
$700,000 2017-18 Transportation
Impact Fees
Miscellaneous Arterial Rehabilitation $400,000 2018-19 Prop C
Total Funds Available $2,850,000
Design costs for the entire project were approximately $200,000 and the traffic signal
work was $658,472, bringing the total of current expenditures to approximately $860,000.
There are sufficient funds in the budget to cover the pavement rehabilitation of Huntington
Drive between Santa Clara Street and Fifth Avenue, and the 2019 Miscellaneous Arterial
Rehabilitation projects in the amount of $1,796,000, including a 10% contingency.
RECOMMENDATION
It is recommended that the City Council find the project categorically exempt pursuant to
the requirements of the California Environmental Quality Act (“CEQA”); and authorize
and direct the City Manager to execute a contract with Hardy & Harper, Inc. for the
Pavement Rehabilitation of Huntington Drive between Santa Clara Street and Fifth
Avenue, and the 2019 Miscellaneous Arterial Rehabilitation in the amount of $1,796,000,
including a 10% contingency.
Attachment: Proposed Contract
CITY OF ARCADIA
HUNTINGTON DRIVE REHABILITATION IMPROVEMENTS
FROM SANTA CLARA STREET TO FIFTH AVE NUE
PROJECT NO. 41854319
&
2019 MISCELLANEOUS ARTERIAL REHABILITATION
PROJECT NO. 41854919
BETWEEN
CITY OF ARCADIA
AND
HARDY & HARPER, INC.
CONTRACT
Contract - 1
CONTRACT FOR THE
CITY OF ARCADIA
This CONTRACT, No. ________ is made and entered into this ____ day of _______, ______, by
and between City of Arcadia, sometimes hereinafter called “City,” and Hardy & Harper, Inc.,
sometimes hereinafter called “Contractor.”
WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these
presents do covenant and agree with each other as follows:
A. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated in the
Contract, and shall provide all labor, materials, equipment, tools, utility services, and
transportation to complete all of the Work required in strict compliance with the Contract
Documents as specified in Article 5, below, for the following Project:
HUNTINGTON DRIVE REHABILITATION IMPROVEMENTS
FROM SANTA CLARA STREET TO FIFTH AVENUE
PROJECT NO. 41854319
&
2019 MISCELLANEOUS ARTERIAL REHABILITATION
PROJECT NO. 41854919
The Contractor and its surety shall be liable to the City for any damages arising as a result of the
Contractor’s failure to comply with this obligation.
B. TIME FOR COMPLETION. Time is of the essence in the performance of the Work. The Work
shall be commenced on the date stated in the City’s Notice to Proceed. The Contractor shall
complete all Work required by the Contract Documents within 60 calendar days from the
commencement date stated in the Notice to Proceed. By its signature hereunder, Contractor
agrees the time for completion set forth above is adequate and reasonable to complete the Work.
C. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for the
performance of the Contract, subject to any additions or deductions as provided in the Contract
Documents, and including all applicable taxes and costs, the sum of one million seven-hundred
ninety-six dollars and zero cents ($1,796,000). Payment shall be made as set forth in the General
Conditions.
D. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85, it is
agreed that the Contractor will pay the City the sum set forth in Special Conditions, Article 1.11
for each and every calendar day of delay beyond the time prescribed in the Contract Documents
for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this
is not paid, the Contractor agrees the City may deduct that amount from any money due or that
may become due the Contractor under the Contract. This Article does not exclude recovery of
other damages specified in the Contract Documents.
E. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the
following:
Notice Inviting Bids
Instructions to Bidders
Bid Form
Bid Bond
Designation of Subcontractors
Contract - 2
Information Required of Bidders
Non-Collusion Declaration Form
Iran Contracting Act Certification
Public Works Contractor Registration Certification
Performance Bond
Payment (Labor and Materials) Bond
General Conditions
Special Conditions
Technical Specifications
Addenda
Plans and Drawings
Standard Specifications for Public Works Construction “Greenbook”, latest edition, Except
Sections 1-9
Applicable Local Agency Standards and Specifications, as last revised
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract
The Contractor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the
Contract Documents and not by others shall be done as if required by all. This Contract shall
supersede any prior agreement of the parties.
F. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE. Each and every
provision of law required to be included in these Contract Documents shall be deemed to be
included in these Contract Documents. The Contractor shall comply with all requirements of
applicable federal, state and local laws, rules and regulations, including, but not limited to, the
provisions of the California Labor Code and California Public Contract Code which are applicable
to this Work.
G. INDEMNIFICATION. Contractor shall provide indemnification and defense as set forth in the
General Conditions.
H. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in
accordance with the Labor Code which such rates shall be made available at the City’s
Administrative Office or may be obtained online at dir.ca.gov and which must be posted at the job
site.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
Contract - 3
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on
the day and year above written.
CITY OF ARCADIA
By:
Dominic Lazzaretto
City Manager
HARDY & HARPER, INC.
By:
Signature
Print Name and Title
Attest:
By:
City Clerk
By:
Signature
Print Name and Title
Approved as to Form:
Stephen P. Deitsch
City Attorney