HomeMy WebLinkAboutItem 10a - Water and Sewer Cost of Service Study UpdateWater and Sewer Cost of Service Study Update
September 1, 2020
Page 1 of 8
DATE: September 1, 2020
TO: Honorable Mayor and City Council
FROM: Tom Tait, Public Works Services Director
By: Jacquelyn Mercado, Senior Management Analyst
SUBJECT: REPORT, DISCUSSION, AND DIRECTION REGARDING THE WATER
AND SEWER COST OF SERVICE STUDY UPDATE
Recommendation: Provide direction on moving forward with water
and sewer rate adjustments
SUMMARY
In October 2015, the City Council adopted a tiered water rate structure and approved a
five-year water and sewer rate adjustment through the end of calendar year 2020,
based on the completed Water and Sewer Cost of Service Study (“Cost Study”). In
December 2019, the City Council adopted resolutions for the fifth and final year of the
previously approved water and sewer rate adjustment. To continue to fund the City’s
water and sewer systems ongoing operation and maintenance costs, an update to the
Cost Study was completed to recommend a new five-year water and sewer rate
adjustment.
In order to fund operations, maintenance, water supply costs, capital expenditures, and
maintain a sufficient Reserve Fund balance, the Cost Study Update recommends that
the City increase water rates by 5% for calendar years 2021 and 2022, and 6% for the
following calendar years through 2025. The Cost Study Update also proposes that the
City increase sewer revenues by 2% for calendar years 2021 through 2025, in order to
fund ongoing sewer operations and achieve a 75-year replacement cycle for the City’s
sewer system.
It is recommended that the City Council provide direction to the Public Works Services
Department (“PWSD”) to move forward with the adoption of the Cost Study Update and
water and sewer rate adjustment process following Proposition 218 (“Prop 218”)
balloting procedures to establish a five-year water and sewer rate structure for calendar
years 2021 through 2025.
Water and Sewer Cost of Service Study Update
September 1, 2020
Page 2 of 8
BACKGROUND
The City provides and maintains water and sewer services to more than 56,000
residents. Utility rate increases are necessary to fund ongoing operations, maintenance,
and capital improvements, and to maintain adequate Reserve Fund balances for the
water and sanitary sewer systems, in order to provide quality services to Arcadia
residents and businesses. In February 2014, the City Council awarded a Professional
Services Agreement to Carollo for the preparation of the Water and Sewer Cost of
Service Study and the development of a financial model that would determine how best
to recover projected ongoing operational costs, capital improvements to water and
sewer infrastructure, and water supply costs, over a five-year period. The PWSD and
Carollo gathered and analyzed data on the City’s water and sanitary sewer operations
and established a seasonal tiered water rate structure that would meet the City’s
primary objectives of providing revenue stability, while encouraging water use efficiency.
On January 19, 2016, the City Council adopted a seasonal tiered water rate structure
and approved a five-year water and sewer rate adjustment schedule for calendar years
2016 through 2020. The PWSD annually reviews water and sewer operating budgets,
revenues, expenditures, and Reserve Fund balances to determine whether the
approved maximum rate adjustment is necessary. The City of Arcadia’s water and
sewer rates are among the lowest in the area and have remained so even with annual
rate adjustments over the past five years.
Although the Governor declared the drought emergency to be over in 2017, local
regions continue to suffer from long-term drought impacts. In the Main Basin, from
which the City draws most of its water, basin levels have not recovered to minimum
operating levels. In response, the Main Basin Watermaster adopted a Drought
Management Plan that includes a Resource Development Assessment (“RDA”), which
is a pass-through fee based on each individual producer’s annual amount of water
pumped from the Main Basin. The purpose of the RDA is to restore ground water levels
by purchasing imported water from the State Water Project, separate from the purchase
of Replacement Water. The RDA has continued to increase annually and is anticipated
to cost the City over $2 million dollars in Fiscal Year 2021-22. The Main Basin
Watermaster implemented the RDA in Fiscal Year 2016-2017; therefore, this cost was
not accounted for in the 2015 Cost Study, and the City has not been able to recover the
costs of this charge from ratepayers.
The goal of the 2015 Cost Study was to utilize Reserve Funds to minimize larger rate
adjustments. Due to changes in water use trends resulting from the last drought
emergency, increases to operations and maintenance budgets, mainly due to the cost
of the RDA and Replacement Water, and funding capital improvements, an update to
the 2015 Cost Study is necessary. In July 2019, the City Council approved a
Professional Services Agreement with Carollo to complete an update to the 2015 Cost
Water and Sewer Cost of Service Study Update
September 1, 2020
Page 3 of 8
Study and to recommend a new five-year water and sewer rate adjustment for calendar
years 2021 through 2025.
DISCUSSION
The Cost Study Update relies on the City’s financial and rate models, which were
exclusively developed for the City by Carollo during the 2015 Cost Study, and they were
subsequently updated and refined in 2017. These models have again been updated to
include actual revenues and operational expenditures, capital improvement costs, and
customer usage data, along with additional items that were necessary to develop
financial projections for Fiscal Years 2020-21 through 2024-25. The current sewer and
tiered water rate structures remain the same, but minor modifications have been
recommended to the seasonal tier allotments. These changes include increasing and
decreasing allotments based on the analysis of actual tiered customer usage data
during the last five years. Adjusting the tier allotments is necessary in order to realign
tier usage with meter size and current customer demand patterns. The tier allotments
are now more proportional across all tiers and meter sizes, which makes the proposed
rate structure fairer and legally defensible.
The following goals were identified in the 2015 Cost Study and carried forward through
the Cost Study Update:
• Generate enough revenue to fund continued operations and maintenance of the
City’s sewer and water supply and distribution system, including increases in
water supply costs driven by the Main Basin’s Drought Management Plan to
restore the health of the basin.
• Provide for equipment replacement and improvements to the water and sewer
systems infrastructure through capital improvements.
• Review reserve policies and set rates to adequately maintain a reserve fund to
make necessary repairs in the event of an emergency.
Based on discussions and previous direction from the City Council, rate adjustments
have been designed to eliminate the ongoing use of Reserve Funds to fund operations
and capital improvement expenditures.
Water Rates
Operations and maintenance expenditures comprise most of the expenses within the
Water budget, with the single largest line item being water supply costs. The updated
Cost Study financial model was used to forecast water sales and expenditures that
include looking at the cost of current and future water supplies, including the rising cost
of replacement water, system operation costs, and Watermaster’s imposed RDA fee.
Water and Sewer Cost of Service Study Update
September 1, 2020
Page 4 of 8
In addition to regular replacement water costs, the RDA fee has increased annually
since Fiscal Year 2016-17, from $40 per acre-foot to $175 per acre-foot in Fiscal Year
2020-21. To date, the City has paid over $6 million dollars in RDA fees without passing
any of those charges on to ratepayers. The RDA fee will continue for the foreseeable
future and is estimated to cost the City approximately $2 million annually. The RDA fee
has been included in the Cost Study Update and the proposed five-year water rate
adjustments has accounted for this cost.
The previous annual rate adjustments were designed to use Reserve Funds to lessen
the amount of annual water rate adjustments. Accordingly, the City Council agreed to
lower the water Reserve Fund balance from $20 million to $12 million over the five-year
period. The updated Cost Study has estimated the value of the City’s water system
replacement at $236 million. Based on industry standards for such a valuation, the Cost
Study determined that $7.1 million in capital reserve (or 3% of $236M) is required,
combined with about $3.8 million required to fund operation and maintenance costs for
at least 90 days. As such, the total reserve required for an emergency is $11 million.
Based on those factors and taking into account the current pandemic, the Cost Study
Update recommends that the City increase water revenues by 5% for calendar years
2021 and 2022, and 6% for the following calendar years through 2025, in order to fund
expected operations, maintenance, and CIP expenditures, and maintain a sufficient
Reserve Fund balance. The proposed water rates shown in the tables below will not
exceed the estimated amount necessary to fund the operation of the City Water
System:
The table below shows the proposed increase to the current fixed bimonthly meter
charge for all customer classes to adequately reflect the actual cost of service incurred.
Proposed Meter Charge ($/Meter Size)
Meter Size
(in inches)
Current
Rate 2021 2022 2023 2024 2025
5/8” $30.33 $31.96 $33.56 $35.57 $37.71 $39.97
3/4” $32.40 $34.15 $35.86 $38.01 $40.29 $42.71
1” $36.55 $38.53 $40.46 $42.88 $45.46 $48.18
1 1/2” $46.93 $49.48 $51.96 $55.07 $58.38 $61.88
2” $59.39 $62.62 $65.75 $69.70 $73.88 $78.31
3” $88.45 $93.29 $97.95 $103.83 $110.06 $116.66
4” $ 129.97 $137.09 $143.95 $152.58 $161.74 $171.44
6” $ 254.53 $268.51 $281.93 $298.85 $316.78 $335.79
8” $ 399.85 $421.83 $442.92 $469.49 $497.66 $527.52
10” $ 607.45 $640.85 $672.89 $713.27 $756.06 $801.43
Water and Sewer Cost of Service Study Update
September 1, 2020
Page 5 of 8
Additionally, the Cost Study Update has proposed a few minor adjustments to some of
the tier break points, which are necessary to realign tier usage with each meter size to
current water demand patterns. These tier break points are shown seasonally in the
following tables.
Bimonthly Tier Break Points (in HCF) for Winter Water Usage
(November through April)
Meter Size
Tier 5/8” 3/4” 1” 1 1/2” 2”
Tier 1 0 - 22 0 - 22 0 - 22 0 - 22 0 - 22
Tier 2 23 - 32 23 - 34 23 - 42 23 - 48 23 - 60
Tier 3 33 - 42 35 - 44 43 - 58 49 - 70 61 - 90
Tier 4 43+ 45+ 59+ 71+ 91+
Bimonthly Tier Break Points (in HCF) for Summer Water Usage
(May through October)
Meter Size
Tier 5/8” 3/4” 1” 1 1/2” 2”
Tier 1 0 - 22 0 - 22 0 - 22 0 - 22 0 - 22
Tier 2 23 - 34 23 - 42 23 - 60 23 - 70 23 - 94
Tier 3 35 - 44 43 - 58 61 - 92 71 - 112 95 - 148
Tier 4 45+ 59+ 93+ 113+ 149+
A seasonal single-family tiered water rate structure assists in managing customer
demand for water by pricing discretionary water uses, such as landscape irrigation, at a
higher rate than water used for drinking and sanitation purposes. This is to provide a
price signal to customers to use water efficiently and to offer an incentive to reduce
excess water use. As water usage increases, so does the cost per unit of additional
water; this methodology has proven effective in curtailing wasteful water practices. The
table below shows the proposed single-family rates.
Proposed Single-Family Rates for Commodity Charges ($/HCF)
Tier
Current
Rate 2021 2022 2023 2024 2025
Tier 1 $1.82 $1.91 $2.00 $2.12 $2.25 $2.38
Tier 2 $2.23 $2.32 $2.44 $2.59 $2.74 $2.91
Tier 3 $2.53 $2.39 $2.51 $2.66 $2.82 $2.99
Tier 4 $2.72 $3.00 $3.15 $3.34 $3.54 $3.75
Water and Sewer Cost of Service Study Update
September 1, 2020
Page 6 of 8
The table below shows the two-tier water allocations based on the number of dwelling
units in each multi-family complex, followed by a table showing the proposed multi-
family rates.
Bimonthly Tier Allotments (Per Dwelling Unit)
Tier Tier (HCF) x Per Dwelling Unit
Tier 1 12
Tier 2 13 +
Proposed Multi-Family Rates for Commodity Charges ($/HCF)
Tier Current
Rate 2021 2022 2023 2024 2025
Tier 1 $1.69 $1.82 $1.91 $2.02 $2.14 $2.27
Tier 2 $1.97 $2.01 $2.11 $2.23 $2.37 $2.51
Finally, the following table shows specific uniform rates for Commercial, Government,
and Institutional classes.
Proposed Rates for Commodity Charges ($/HCF)
Current
Rate 2021 2022 2023 2024 2025
Commercial $1.81 $1.92 $2.02 $2.14 $2.27 $2.40
Government
& Institutional $2.13 $2.27 $2.38 $2.52 $2.67 $2.83
The net change to a customer’s water bill will be affected by the customer’s ability to
use water efficiently. A typical single-family customer with a 1” water meter and 55
Hundred Cubic Feet (“HCF”) usage in the summer will see a $6.93 or 4.6% bimonthly
increase in their water bill. The percent increase will vary among customers based on
usage.
Sewer Rates
The City’s sewer system includes 138 miles of pipe and is, on average, 75 years old.
The Sewer Master Plan is a comprehensive report outlining a long-range program of
capital improvements and preventative maintenance measures to upgrade and maintain
the City’s sewer system. Annual sewer rate adjustments are necessary to fund the
operations and maintenance activities of the sewer system to ensure that the system is
in compliance with state regulations that mandate the elimination of sewer overflows.
Water and Sewer Cost of Service Study Update
September 1, 2020
Page 7 of 8
The Cost Study Update determined that the current sewer rate structure equitably
recovers costs from each customer class but that the City must increase sewer
revenues annually in order to fund ongoing capital improvement projects and meet
projected operating expenditures. revenues must also maintain a Reserve Fund
balance of $1.3 million, or 1.5% of the valuation of the City’s sanitary sewer system,
which is currently estimated at $90 million.
Therefore, the updated Cost Study is recommending that the City increase sewer
revenues by 2% for calendar years 2021 through 2025, in order to fund ongoing
operations and achieve a 75-year replacement cycle for the City’s sewer system. The
proposed sewer rates shown in the tables below will not exceed the estimated amount
necessary to fund the operation of the City Sewer System:
The table below shows Single-Family Residential and Multi-Family Residential
Dwellings Bimonthly Rates
Current
Rate 2021 2022 2023 2024 2025
$16.97 $17.35 $17.70 $18.05 $18.41 $18.78
Commercial Dwellings Bimonthly Rates (Fixed Rate + Variable Per HCF Billed Water
Usage) are shown in the following table.
Current
Rate 2021 2022 2023 2024 2025
$50.69 +
$0.28
Variable
Per HCF
$52.04 +
$0.28
Variable
Per HCF
$53.09 +
$0.29
Variable
Per HCF
$54.15 +
$0.29
Variable
Per HCF
$55.23 +
$0.30
Variable
Per HCF
$56.33 +
$0.31
Variable
Per HCF
The proposed sewer rates are increased proportionally each year to generate the
necessary projected level of revenues provided in the Cost Study Update. Should the
City find that revenue requirements are less than those projected in the study, the City
could opt to forgo rate increases in any given year or implement rates lower than the
proposed increase for that year.
Implementation of New Rates
Following direction from the City Council at the September 1 City Council Meeting, the
PWSD will request that the City Council approve the Water and Sewer Rate Cost of
Service Study update and set a Public Hearing date for December 1, 2020, to consider
any protests to the proposed water and sewer rate adjustments. The PWSD will, at
least forty-five (45) days before the date of the Public Hearing, mail a notice to all water
Water and Sewer Cost of Service Study Update
September 1, 2020
Page 8 of 8
and sewer customers detailing the proposed rate increase in accordance with
Proposition 218 requirements. All public outreach efforts and informational pieces
developed will be approved through the City Attorney’s office to ensure that the City is
following Proposition 218 regulations. If there is no majority protest, the new water and
sewer rates will become effective January 1, 2021.
FISCAL IMPACT
Water and sewer rate increases are necessary to fund ongoing operations and
maintenance budgets and the Capital Improvement Program while maintaining an
adequate Reserve Fund balance in case of an emergency. The lack of a rate
adjustment would not allow the City to recover increasing water supply costs, and
operations and maintenance costs for the City’s water and sewer systems.
The Water and Sewer Costs of Service Study Update recommends that the City
increase water revenues by 5% for calendar years 2021 and 2022, and 6% for the
following three years through 2025 in order to fund expected operations, maintenance,
and Capital Improvement Program expenditures. Additionally, the Cost Study Update
recommends that a 2% sewer rate adjustment for calendar years 2021 through 2025 is
necessary to fund expected operations and maintenance costs for the City’s sewer
system.
RECOMMENDATION
It is recommended that the City Council provide direction to the Public Works Services
Department to move forward with the adoption of the Cost Study Update and water and
sewer rate adjustment process by following Proposition 218 balloting procedures to
establish a five-year water and sewer rate structure for calendar years 2021 through
2025.