HomeMy WebLinkAbout7369 RESOLUTION NO. 7369
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ARCADIA,
CALIFORNIA, ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR
2021-22 FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY
ACT OF 2017
WHEREAS, Senate Bill 1 ("SB1"), the Road Repair and Accountability Act of 2017
(Chapter 5, Statues of 2017), was passed by the Legislature and signed into law by the
Governor in April 2017 to address the significant multi-modal transportation funding
shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will
ensure the residents of the City of Arcadia are aware of the projects proposed for funding
in our community and which projects have been completed each fiscal year; and
WHEREAS, the City of Arcadia must include in the City budget a list of all projects
proposed to receive funding from the Road Maintenance and Rehabilitation Account
("RMRA") created by SB 1, which must include a description and the location of each
proposed project, a proposed schedule for the project's completion, and the estimated
useful life of the improvement; and
WHEREAS, SB 1 requires that all projects proposed to receive funding shall be
adopted by resolution by the City Council at a regular public meeting; and
WHEREAS, the City of Arcadia, will receive an estimated $1,151,006 in RMRA
funding in Fiscal Year 2021-22 from SB 1; and
WHEREAS, this is the fifth year in which the City of Arcadia is receiving SB 1
funding and such funding will enable the City of Arcadia to continue essential road
maintenance and rehabilitation projects, safety improvements, repairing and replacing
1
aging bridges, and increasing access and mobility options for the traveling public that
would not have otherwise been possible without SB 1; and
WHEREAS, the City of Arcadia has undergone a robust public process to ensure
public input into our community's transportation priorities/the project list; and
WHEREAS, the City of Arcadia used a Pavement Management Plan to develop
the SB 1 project list to ensure revenues are being used on high priority and cost effective
projects that also meet the community's priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City of Arcadia maintain and
rehabilitate streets/roads throughout the City of Arcadia this year and continue similar
projects into the future; and
WHEREAS, the 2018 California Statewide Local Streets and Road Needs
Assessment found that the City of Arcadia streets and roads are in a "Lower Risk"
condition, and this revenue will help us increase the overall quality of our road system,
and over the next decade will bring our streets and roads into a "Good" condition; and
WHEREAS, the SB 1 project list and overall investment in our local streets and
roads infrastructure, and using cutting-edge technology, materials and practices, will have
significant positive co-benefits Statewide.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF ARCADIA,
CALIFORNIA, DOES HEREBY FIND, DETERMINE, AND RESOLVE AS FOLLOWS:
SECTION 1. The foregoing recitals are true and correct.
SECTION 2. The City Manager of the City of Arcadia, or his designee, is hereby
authorized to submit an application to the California Transportation Commission ("CTC")
2
for any and all funds that may become available to the City from RMRA.
SECTION 3. The following projects being proposed for City Council approval will
utilize the Fiscal Year 2021-22 Road Maintenance and Rehabilitation Account revenues.
1. Fiscal Year 2021-22 Pavement Rehabilitation Program: The project is to be
adopted into the City's Fiscal Year 2021-22 Capital Improvement Program.
a. Anticipated Funding Sources: RMRA fund $1,100,00
b. Project Description: This project will resurface approximately 1.5 miles
of City roadways with rubberized asphalt. Work includes pavement
rehabilitation/reconstruction to extend the roadway service life. Other
repair items to be included in the scope of work are localized AC dig-out
repairs and minor repairs to concrete curb and gutter, sidewalk, and
cross gutters. All striping and pavement markers will be installed upon
completion of the paving.
c. Project Location:
• Elevado Avenue (from Grand View Avenue to Virginia Drive)
• Ontare Road (from Santa Anita Avenue to End of Cul De Sac)
• Old Ranch Road (from Colorado Street to Vaquero Road)
• El Monte Avenue (from Campus Road to Duarte Road)
• Wistaria Avenue (from Holly Avenue to El Monte Avenue)
d. Proposed Schedule:
• Start construction in Summer 2022
• Complete construction in the Winter 2022
e. Estimated Useful Life: 20 years.
3
SECTION 4. The adoption of this Resolution constitutes the approval of the
foregoing projects to be submitted to the California Transportation Commission.
SECTION 5. The City Manager, or his designee, is hereby authorized to execute
all documents necessary to implement and secure any and all funds that may become
available to the City from RMRA.
SECTION 6. The City Clerk shall certify to the adoption of this Resolution.
Passed, approved, and adopted this 15th day of June, 2021.
—
Mayor of the of Arcadia
ATTEST:
Clerk ir
APPROVED AS TO FORM:
Stephen P. Deitsch
City Attorney
4
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) SS:
CITY OF ARCADIA )
I, GENE GLASCO, City Clerk of the City of Arcadia, hereby certifies that the
foregoing Resolution No. 7369 was passed and adopted by the City Council of the City of
Arcadia, signed by the Mayor and attested to by the City Clerk at a regular meeting of said
Council held on the 15th day of June, 2021 and that said Resolution was adopted by the
following vote, to wit:
AYES: Beck, Chandler, Verlato, Cheng, and Tay
NOES: None
ABSENT: None
y Clerk of the City of Arcadia
5