Loading...
HomeMy WebLinkAboutItem 11d - Accept Traffic Signals Fiber Optics Network Extensions DATE: September 20, 2022 TO: Honorable Mayor and City Council FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director Philip A. Wray, Deputy Director of Development Services/City Engineer By: Ryan Huey, Assistant Engineer SUBJECT: ACCEPT ALL WORK PERFORMED BY ECONOLITE SYSTEMS FOR THE TRAFFIC SIGNALS FIBER OPTICS NETWORK EXTENSIONS PROJECT IN THE AMOUNT OF $62,654.90. Recommendation: Approve SUMMARY On December 7, 2021, the City Council awarded a contract to Econolite Systems in the amount of $60,905.07 for the Traffic Signals Fiber Optics Network Extensions Project, with a 10% contingency. There was one (1) change order for the purchase of additional materials to complete the project, totaling $1,749.83, or 3% of the original contract amount. The terms and conditions of this project have been complied with, and the required work has been performed to the City’s satisfaction, for a final cost of $62,654.90. It is recommended that the City Council accept the project as complete and authorize the final payment in accordance with the approved contract. BACKGROUND The City of Arcadia continues to expand its traffic system network, utilizing the Intelligent Transportation Systems (“ITS”) Master Plan that was created in 2004. With various traffic improvements completed throughout the years, fiber optic cable has become an integral component of the City’s traffic system network. The installation of fiber optic cable has allowed the City to immediately obtain traffic signal data and work efficiently to address known traffic signal issues. Through remote data communication, the City continues to ensure proper traffic signal operation, thus limiting extensive traffic delays and traffic congestion. Traffic Signals Fiber Optics Network Extensions Project September 20, 2022 Page 2 of 3 In this phase of improvements, two large segments of fiber optic cable were installed. One along Baldwin Avenue from Las Tunas Drive to Camino Real Avenue, and the other along First Avenue from Santa Clara Street to Colorado Boulevard. This is the first of several fiber optic network extension projects that look to expand infrastructure throughout the City. The project was advertised for bids in October 2021, and bids were opened on November 18, 2021, with Econolite Systems as the qualifying low bidder. A contract in the amount of $60,905.07, plus a 10% contingency, was awarded by the City Council on December 7, 2021. DISCUSSION Due to longer lead times for material purchases and deliveries, construction began in June 2022 and was completed in July 2022. There was one (1) change order for the purchase of additional materials. The scope of work remained simple and had a minor impact on surrounding areas because of the existing underground conduit that had been installed in previous projects. Fiber optic cable was pulled through the existing conduit, connecting to new traffic signal equipment in existing traffic signal cabinets at each of the intersections. During construction, it became apparent that additional fiber optic cable was needed to complete the work. As a result of the additional materials, the final amount is a net increase of $1,749.83, or 3% of the original contract amount. A summary of the construction contract, with the change order, is as follows: Original Contract: $60,905.07 Change Order #1 (quantity adjustment) $1,749.83 Final Total Contract: $62,654.90 FISCAL IMPACT The Traffic Signals Fiber Optics Network Extensions project was budgeted in the FY 2020/21 and FY 2021/22 Capital Improvement Program. The total budget appropriation was $400,000 in Transportation Impact Funds. The initial contract price was $60,905.07 plus a 10% contingency. One change order was approved for the additional quantities at an increase of $1,749.83. The total cost of the construction, including the change order, is $62,654.90. There are sufficient funds in the project budget to cover the construction contract. Remaining funds in this Program will be used for the Santa Anita Avenue Corridor Phase 2 Traffic Signal Improvements project, currently under construction. Any remaining balance will be budgeted for a project planned in 2023. Traffic Signals Fiber Optics Network Extensions Project September 20, 2022 Page 3 of 3 RECOMMENDATION It is recommended that the City Council accept all work performed by Econolite Systems for the Traffic Signals Fiber Optics Network Extensions project as complete; and authorize the final payment to be made in accordance with the contract documents.