HomeMy WebLinkAboutItem 12s - Accept Orange Grove Well 1A Rehab Project as CompleteAccept Inspection and Rehabilitation of
Orange Grove Well 1A Project
June 20, 2023
Page 1 of 3
DATE: June 20, 2023
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Tiffany Lee, P.E., Senior Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY GENERAL PUMP COMPANY,
INC. FOR THE INSPECTION AND REHABILITATION OF THE ORANGE
GROVE WELL 1A PROJECT AS COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On April 19, 2022, the City Council approved a contract with General Pump Company,
Inc. in the amount of $307,200 for the Inspection and Rehabilitation of the Orange Grove
Well 1A Project. The terms and conditions of this project have been complied with and
the work has been performed to the satisfaction of the Project Manager for a total project
cost of $291,300. This amount reflects the original contract amount of $307,200 minus
quantity changes totaling $15,900, or 5.18% less than the original contract amount.
It is recommended that the City Council accept all work performed by General Pump
Company, Inc. for Inspection and Rehabilitation of the Orange Grove Well 1A Project as
complete and authorize the final payment to be made in accordance with the contract
documents, subject to the retention of $14,565.
BACKGROUND
The City operates and maintains 11 groundwater wells, which produce an average of
16,500 acre-feet, or 5.4 billion gallons, of water to Arcadia customers each year. Regular
inspection and maintenance of City wells is crucial to ensuring that the wells are operating
at maximum production capacity and efficiency.
The American Water Works Association (“AWWA”) is a nonprofit organization that
develops and publishes standards for the proper treatment, transportation, and storage
of drinking water supplies. The AWWA Standards for Water Supply Wells recommend
performing preventative maintenance every 7 to 10 years. This includes removing the
well pump assembly, video inspecting the pump casing, and performing a comprehensive
inspection of the well pump assembly and components. The Public Works Services
Accept Inspection and Rehabilitation of
Orange Grove Well 1A Project
June 20, 2023
Page 2 of 3
Department (“PWSD”) has developed a water supply well inspection and rehabilitation
program that follows these guidelines.
Each year, one to two wells are selected for preventative maintenance based on the date
of the last inspection, maintenance records, and the current well efficiency. Preventative
maintenance performed on the City’s water supply wells protects against higher
emergency repair costs and the possibility of not meeting system demands should a water
supply well go out of service for an extended period of time.
DISCUSSION
On April 19, 2022, the City Council approved a contract with General Pump Company,
Inc. for the inspection and rehabilitation of the Orange Grove Well 1A Project. The project
began with removal and inspection of the well motor, shaft, and pump, and video
inspection of the well casing. Based on this inspection, a scope of work consistent with
the contract documents was agreed upon by the contractor and PWSD. The original
contract estimate for all work was $307,200. After the well was pulled, a more defined
project cost was determined with final construction costs totaling $291,300.
The work included cleaning of the well casing, replacing the existing worn column pipe,
worn or damaged shaft assembly, oil lube tube, suction with stainless steel cone strainer,
sounding tube, stainless steel airline and gauge, rewinding of the electric motor, and
replacing the inadequate pump bowl assembly. Following re-assembly and installation of
the well equipment, the well was disinfected, and water quality samples were taken,
tested, and approved, in accordance with California Department of Public Health
requirements.
All terms and conditions of this contract have been complied with and the work has been
performed to the satisfaction of the Project Manager. General Pump Company, Inc.
completed the work as defined in the project plans and specifications in an efficient and
timely manner.
ENVIRONMENTAL ANALYSIS
This well inspection and rehabilitation project is considered a Class 1 exemption as
defined in Section 15301(b) of the California Environmental Quality Act, since the project
consists of the maintenance of existing public facility providing public utility service.
FISCAL IMPACT
Funds in the amount of $250,000 were budgeted in the Fiscal Year 2021-22 Capital
Improvement Program for this project; however, due to inflation, increased fuel costs, and
material supply and labor shortages, the cost of this project increased and exceeded the
Accept Inspection and Rehabilitation of
Orange Grove Well 1A Project
June 20, 2023
Page 3 of 3
approved budget by $57,200. On April 19, 2022, the City Council authorized a
supplemental budget appropriation in the amount of $57,200 for the Inspection and
Rehabilitation of the Orange Grove Well 1A Project, offset by funds received from the
American Rescue Plan Act (“ARPA”). The total cost for this project is $291,300. This
amount reflects the contract amount of $307,200 minus quantity changes totaling
$15,900, or 5.18% less than the revised contract amount. The remaining funds will go
back to the Capital Improvement Fund balance.
RECOMMENDATION
It is recommended that the City Council determine that this project is exempt under the
California Environmental Quality Act (“CEQA”); and accept all work performed by General
Pump Company, Inc. for the Inspection and Rehabilitation of the Orange Grove Well 1A
Project as complete and authorize the final payment to be made in accordance with the
contract documents, subject to the retention of $14,565.