DATE: November 7, 2023
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Tiffany Lee, P.E. Senior Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY 316 ENGINEERING &
CONSTRUCTION, INC. FOR THE WATER MAIN REPLACEMENT
PROJECT AS COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On March 21, 2023, the City Council approved a contract with 316 Engineering &
Construction, Inc. in the amount of $435,907, for the Water Main Replacement Project
along the alley south of La Porte Street between First Avenue and Saint Joseph Street.
The terms and conditions of this project have been complied with and the work has been
performed to the satisfaction of the Project Manager for a total project cost of $412,047.
This amount reflects the original contract amount of $435,907, minus quantity changes
totaling $23,860, or 5.47% less than the original contract amount.
It is recommended that the City Council accept all work performed by 316 Engineering &
Construction, Inc. for the Water Main Replacement Project as complete, and authorize
the final payment to be made in accordance with the contract documents, subject to the
retention of $20,602.35.
BACKGROUND
The 4-inch steel water main along the alley south of La Porte Street between First Avenue
and Saint Joseph Street was installed in 1916. In recent years, Public Works Services
Department maintenance crews have made several emergency repairs to this water
main, primarily due to its age.
The project replaced the existing 4-inch steel water main with an 8-inch ductile iron water
main. Ductile iron is the industry standard for water pipes and has corrosion resistance
and strength. Ductile iron can also tolerate movement or deflection without breaking. This
results in improving the overall reliability of the City’s water distribution system.
Accept Water Main Replacement Project
November 7, 2023
Page 2 of 3
DISCUSSION
On March 21, 2023, the City Council approved a contract with 316 Engineering &
Construction, Inc. for the Water Main Replacement Project. The work performed included
replacing a 4-inch water main with an 8-inch ductile iron water main. During the course
of work, the City received credits for reducing the quantities of several bid items. Below
is a breakdown of the contract change orders.
CCO Description Amount
1. Deleted (38 LF) - Installation of 8-Inch Ductile Iron Pipe ($7,638)
2. Deleted (254 SF) – Asphalt Pavement ($5,080)
3. Deleted (38 LF) – Removal and disposal of existing or abandoned pipe ($342)
4. Deleted (540 SF) – Concrete Pavement ($10,800)
Total: ($23,860)
The change orders listed reduced the overall contract amount by $23,860, or 5.47% less
than the original contract amount. All the terms and conditions of this contract have been
complied with and the work has been performed to the satisfaction of the Project
Manager. The vendor, 316 Engineering & Construction, Inc., completed the work as
defined in the project plans and specifications in an efficient and timely manner.
ENVIRONMENTAL ANALYSIS
The California Environmental Quality Act (“CEQA”) determination was made at project
approval by the Arcadia City Council.
FISCAL IMPACT
Funds in the amount of $400,000 were budgeted in the Fiscal Year 2022-23 Capital
Improvement Program for the Water Main Replacement Project. Due to inflation and
associated increases in fuel costs, material prices, and labor rates, the cost of this project
increased and exceeded the approved budget by $35,907. On March 21, 2023, the City
Council authorized a supplemental budget appropriation in the amount of $79,497.70,
which included the addition of a 10% contingency for the Project.
The total cost for this Project is $412,047; this amount reflects the original contract amount
of $435,907 minus contract changes totaling $23,860, or 5.47% less than the original
contract amount. The remaining funds will revert back to the American Rescue Plan Act
(“ARPA”) Fund balance.
Accept Water Main Replacement Project
November 7, 2023
Page 3 of 3
RECOMMENDATION
It is recommended that the City Council accept all work performed by 316 Engineering &
Construction, Inc. for the Water Main Replacement Project as complete; and authorize
the final payment to be made in accordance with the contract documents, subject to the
retention of $20,602.35.