Loading...
HomeMy WebLinkAboutItem 10k - Accept Miscellaneous Arterial Rehabilitation Project as Complete DATE: May 21, 2024 TO: Honorable Mayor and City Council FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director Kevin Merrill, City Engineer By: Johnathan Doojphibulpol, Associate Civil Engineer SUBJECT: ACCEPT ALL WORK PERFORMED BY GENTRY BROTHERS, INC. FOR THE MISCELLANEOUS ARTERIAL REHABILITATION OF FIRST AVENUE AND SANTA CLARA STREET AND ST. JOSEPH STREET, IN THE AMOUNT OF $1,257,862.55 CEQA: Exempt Recommendation: Approve SUMMARY On January 17, 2023, the City Council awarded a contract to Gentry Brothers, Inc. in the amount of $1,321,361.10 for the Miscellaneous Arterial Rehabilitation of First Avenue and Santa Clara Street, and St. Joseph Street, with a 10% contingency. There were two (2) change orders that resulted in a net decrease of $63,498.55 in total project cost. The terms and conditions of this project have been complied with and the required work has been performed to the City’s satisfaction, for a final cost of $1,257,862.55. It is recommended that the City Council accept the project as complete and authorize the final payment in accordance with the approved contract. BACKGROUND As part of the City’s ongoing Pavement Management Program, the City annually appropriates Proposition C funding for arterial repaving projects. These street segments were selected for the program because the Pavement Condition Indexes for the project streets were in ‘poor’ condition in addition to the fact that previous work had impacted the streets. The City budgeted $800,000 in Fiscal Year 2021-22 and $400,000 in Fiscal Year 2022-23 for a total of $1,200,000 of Proposition C funds, as well as a budget transfer of $300,000 from the Downtown Alley project, providing a total project budget of $1,500,000. The project included the following segments: • First Avenue from Colorado Boulevard to Wheeler Avenue Accept Miscellaneous Arterial Rehabilitation Project May 21, 2024 Page 2 of 3 • Santa Clara Street from First Avenue to Fifth Avenue • St. Joseph Street from Flower Street to Second Avenue • Westerly Alley off First Avenue between St. Joseph Street and La Porte Street The project was advertised for bids in November 2022 and bids were opened on December 15, 2022, with Gentry Brothers, Inc. as the qualifying low bidder. A contract in the amount of $1,321,361.10, plus a 10% contingency, was awarded by the City Council on January 17, 2023. DISCUSSION Construction began in July 2023 and was completed in April 2024. During the life of the project, there were two (2) change orders issued: one for extra traffic signal loop work and striping changes; and one for the final adjustment of quantities, with a net decrease of $63,498.55. The traffic signal loop work, located at the intersection of First Avenue and Santa Clara Street, was added once it was determined that the project would come in under budget. This work was added to complete signal upgrades at the intersection once the streets were rehabilitated. The striping changes were required in the field to provide better clarity for vehicle movements on First Avenue, and extra work was required around the bulb- outs on Santa Clara St. Quantity adjustments were attributed to: • Change in asphalt depth removal due to field conditions; and • Change in the drainage system type to handle higher volume. As a result of all the adjustments, the final amount is a net decrease of $63,498.55, just over 3% of the contract amount. A summary of the construction contract with the change orders, is as follows: Original Contract: $1,321,361.10 Change Order #1 (Traffic Loops and Striping) $43,850.00 Change Order #2 (Quantity Adjustments) ($107,348.55) Final Total Contract: $1,257,862.55 FISCAL IMPACT The Miscellaneous Arterial Rehabilitation project was budgeted in the Fiscal Year 2021- 22 and 2022-23 Capital Improvement Programs (“CIP”), with a total of $1,200,000 in Proposition C funds. In order to cover the additional cost of the alley improvements plus contingencies, a budget transfer of $300,000 was included at the time of contract approval from the Downtown Alley project, for a total budget of $1,500,000. The total construction Accept Miscellaneous Arterial Rehabilitation Project May 21, 2024 Page 3 of 3 cost for this project is $1,257,862.55. There are sufficient funds in the project budget to cover the construction contract. ENVIRONMENTAL IMPACT This project is categorically exempt per Section 15301(c) of the California Environmental Quality Act (“CEQA”), as repair and maintenance of an existing highway or street. RECOMMENDATION It is recommended that the City Council determine that the proposed action is exempt under Section 15301(c) of the California Environmental Quality Act (“CEQA”); and accept all work performed by Gentry Brothers, Inc. for the Miscellaneous Arterial Rehabilitation – First Avenue and Santa Clara Street and St. Joseph Street Project as complete; and authorize the final payment to be made in accordance with the contract documents.