HomeMy WebLinkAboutItem 10l - Accept Orange Grove Well 2A Rehab Project as CompleteAccept Inspection and Rehabilitation of
Orange Grove Well 2A Project
September 17, 2024
Page 1 of 3
DATE: September 17, 2024
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Tiffany Lee, P.E., Interim Principal Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY GENERAL PUMP COMPANY,
INC. FOR THE INSPECTION AND REHABILITATION OF THE ORANGE
GROVE WELL 2A PROJECT AS COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On November 21, 2023, the City Council approved a contract with General Pump
Company, Inc. in the amount of $333,800, for the Inspection and Rehabilitation of the
Orange Grove Well 2A Project. The terms and conditions of this project have been
complied with and the work has been performed to the satisfaction of the Project Manager
for a total project cost of $332,688. This amount reflects the original contract amount of
$333,800 minus quantity changes totaling $1,112, or 0.33% less than the original contract
amount.
It is recommended that the City Council accept all work performed by General Pump
Company, Inc. for Inspection and Rehabilitation of the Orange Grove Well 2A Project as
complete and authorize the final payment to be made in accordance with the contract
documents, subject to the retention of $16,634.40.
BACKGROUND
The City operates and maintains 11 groundwater wells, which produce an average of
14,000 acre-feet of water for Arcadia customers each year. Regular inspection and
maintenance of City wells is crucial to ensuring that the wells are operating at maximum
production capacity and efficiency.
The American Water Works Association (“AWWA”) is a nonprofit organization that
develops and publishes standards for the proper treatment, transportation, and storage
of drinking water supplies. The AWWA Standards for Water Supply Wells recommend
performing preventative maintenance every 7 to 10 years, which includes removing the
Accept Inspection and Rehabilitation of
Orange Grove Well 2A Project
September 17, 2024
Page 2 of 3
well pump assembly and components. The Public Works Services Department (“PWSD”)
has developed a water supply well inspection and rehabilitation program that follows
these guidelines. Each year, one to two wells are selected for preventative maintenance
based on the date of the last inspection, maintenance records, and the current well
efficiency. Preventative maintenance performed on the City’s water supply wells protects
against higher emergency repair costs and the possibility of not meeting system demands
should a water supply well go out of service for an extended period.
DISCUSSION
On November 21, 2023, the City Council approved a contract with General Pump
Company, Inc. for the inspection and rehabilitation of the Orange Grove Well 2A Project.
Orange Grove Well 2 is located 600’ east of Well 5 on the southeast property line of the
facility, north of 29 W. Orange Grove Avenue. The project began with removal and
inspection of the well motor, shaft, and pump, and video inspection of the well casing.
Based on this inspection, a scope of work consistent with the contract documents was
agreed upon by the contractor and PWSD. The original contract estimate for all work was
$333,800. After the well was pulled, a more defined project cost was determined with final
construction costs totaling $332,688.
The work included cleaning of the well casing, replacing the existing worn column pipe,
worn or damaged shaft assembly, oil lubrication, suction with stainless steel cone strainer,
sounding tube, stainless steel airline and gauge, and replacing the inadequate pump bowl
assembly and motor. Following re-assembly and installation of the well equipment, the
well was disinfected, and water quality samples were taken, tested, and approved in
accordance with California Department of Public Health requirements.
All terms and conditions of this contract have been complied with and the work has been
performed to the satisfaction of the Project Manager. General Pump Company, Inc.
completed the work as defined in the project plans and specifications in an efficient and
timely manner.
ENVIRONMENTAL ANALYSIS
This well inspection and rehabilitation project is considered a Class 1 exemption as
defined in Section 15301(b) of the California Environmental Quality Act, since the project
consists of the maintenance of an existing public facility providing public utility service.
FISCAL IMPACT
Funds in the amount of $350,000 were budgeted in the Fiscal Year 2023-24 Capital
Improvement Program for the Inspection and Rehabilitation of the Orange Grove Well 2A.
The total construction cost for this project is $332,688. This amount reflects the original
Accept Inspection and Rehabilitation of
Orange Grove Well 2A Project
September 17, 2024
Page 3 of 3
contract amount of $333,800 minus quantity changes totaling $1,112, or 0.33% less than
the original contract amount.
RECOMMENDATION
It is recommended that the City Council determine that this project is exempt under the
California Environmental Quality Act (“CEQA”); and accept all work performed by General
Pump Company, Inc. for the Inspection and Rehabilitation of the Orange Grove Well 2A
Project as complete and authorize the final payment to be made in accordance with the
contract documents, subject to the retention of $16,634.40.