DATE: September 17, 2024
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Tiffany Lee, P.E., Interim Principal Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY GENERAL PUMP COMPANY,
INC. FOR THE INSPECTION AND REHABILITATION OF THE ORANGE
GROVE WELL 5 PROJECT AS COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On April 4, 2023, the City Council approved a contract with General Pump Company, Inc.
in the amount of $289,400 for the Inspection and Rehabilitation of the Orange Grove Well
5 Project. The terms and conditions of this project have been complied with and the work
has been performed to the satisfaction of the Project Manager, for a total project cost of
$286,279. This amount reflects the original contract amount of $289,400 minus quantity
changes totaling $3,121, or 1.08% less than the original contract amount.
It is recommended that the City Council accept all work performed by General Pump
Company, Inc. for Inspection and Rehabilitation of the Orange Grove Well 5 Project as
complete and authorize the final payment to be made in accordance with the contract
documents, subject to the retention of $14,313.95.
BACKGROUND
The City operates and maintains 11 groundwater wells, which produce an average of
14,000 acre-feet of water for Arcadia customers each year. Regular inspection and
maintenance of City wells is crucial to ensuring that the wells are operating at maximum
production capacity and efficiency.
The American Water Works Association (“AWWA”) is a nonprofit organization that
develops and publishes standards for the proper treatment, transportation, and storage
of drinking water supplies. The AWWA Standards for Water Supply Wells recommend
performing preventative maintenance every seven to ten years, which includes removing
the well pump assembly, video inspecting the pump casing, and performing a
Accept Inspection and Rehabilitation of
Orange Grove Well 5 Project
September 17, 2024
Page 2 of 3
comprehensive inspection of the well pump assembly and components. The Public Works
Services Department (“PWSD”) has developed a water supply well inspection and
rehabilitation program that follows these guidelines.
Each year, one to two wells are selected for preventative maintenance based on the date
of the last inspection, maintenance records, and the current well efficiency. Preventative
maintenance performed on the City’s water supply wells protects against higher
emergency repair costs and reduces the likelihood of insufficient supply should a water
supply well become inoperable for an extended period.
DISCUSSION
On April 4, 2023, the City Council approved a contract with General Pump Company, Inc.
for the inspection and rehabilitation of the Orange Grove Well 5 Project. Orange Grove
Well 5 is a submersible pump and motor located on the southwest corner of the water
facility, just north of Fire Station 107. The project began with removal and inspection of
the well motor, pump, and appurtenances, and video inspection of the well casing. Based
on this inspection, a scope of work consistent with the contract documents was agreed
upon by the contractor and PWSD. The original contract estimate for all work was
$289,400. After the well was pulled, a more defined project cost was determined with final
construction costs totaling $286,279.
The work included cleaning of the well casing, replacing the existing worn column pipe,
worn or damaged submersible flat cable, check valve, sounding tube, stainless steel
airline and gauge, and replacing the inadequate pump bowl assembly and motor.
Following re-assembly and installation of the well equipment, the well was disinfected,
and water quality samples were taken, tested, and approved, in accordance with
California Department of Public Health requirements.
All terms and conditions of this contract have been complied with and the work has been
performed to the satisfaction of the Project Manager. General Pump Company, Inc.
completed the work as defined in the project plans and specifications in an efficient and
timely manner.
ENVIRONMENTAL ANALYSIS
This well inspection and rehabilitation project is considered a Class 1 exemption as
defined in Section 15301(b) of the California Environmental Quality Act, since the project
consists of the maintenance of an existing public facility providing public utility service.
Accept Inspection and Rehabilitation of
Orange Grove Well 5 Project
September 17, 2024
Page 3 of 3
FISCAL IMPACT
Funds in the amount of $350,000 were budgeted in the Fiscal Year 2022-23 Capital
Improvement Program for the Inspection and Rehabilitation of the Orange Grove Well 5
Project. The total construction cost for this project is $286,279. This amount reflects the
original contract amount of $289,400 minus quantity changes totaling $3,121, or 1.08%
less than the original contract amount.
RECOMMENDATION
It is recommended that the City Council determine that this project is exempt under the
California Environmental Quality Act (“CEQA”); and accept all work performed by General
Pump Company, Inc. for the Inspection and Rehabilitation of the Orange Grove Well 5
Project as complete and authorize the final payment to be made in accordance with the
contract documents, subject to the retention of $14,313.95.