HomeMy WebLinkAboutItem 10g - Accept Reroof at Various Facilities ProjectAccept Reroof at Various City Facilities Project October 15, 2024 Page 1 of 3 DATE: October 15, 2024 TO: Honorable Mayor and City Council FROM: Paul Cranmer, Public Works Services Director By: Carlos Aguilar, General Services Superintendent SUBJECT: ACCEPT ALL WORK PERFORMED BY R&R ROOFING & WATERPROOFING, INC. FOR THE REROOF AT VARIOUS CITY FACILITIES PROJECT AS COMPLETE CEQA: Exempt Recommendation: Approve SUMMARY On December 19, 2023, the City Council approved a contract with R&R Roofing & Waterproofing, Inc. in the amount of $846,440, with a 10% contingency for the Reroof at Various City Facilities Project. The terms and conditions of this project have been complied with and the work has been performed to the satisfaction of the Project Manager for a total project cost of $897,085.54. This amount reflects the original contract amount of $846,440 plus quantity changes totaling $50,645.54, or 6% more than the original contract amount. The project change orders were required to address additional wear and tear on the roofing surfaces than originally estimated. It is recommended that the City Council accept all work performed by R&R Roofing & Waterproofing, Inc. for the Reroof at Various City Facilities Project as complete, and authorize the final payment to be made in accordance with the contract documents. BACKGROUND The Fiscal Year 2023-24 CIP provided for the reroofing of the Chamber of Commerce, City Council Chambers, and the Community Center buildings, as well as a roof restoration at the Police Department. It was determined that the roof replacement and restoration project would be performed by a licensed roofing contractor, using materials that were purchased and supplied by the City. On November 7, 2023, the City Council approved a purchase order with The Garland Company, Inc. for the purchase of roofing materials in the amount $142,709.94. The actual cost of all materials totaled $133,330.08. This approach to construction reduced the total project cost by eliminating a material price markup from the contractor. Accept Reroof at Various City Facilities Project October 15, 2024 Page 2 of 3 DISCUSSION On December 19, 2023, the City Council approved a contract with R&R Roofing & Waterproofing, Inc. for the Reroof at Various City Facilities Project. The project included replacing the existing wood shingles at the Chamber of Commerce with a polymer wood shingle style covering; a roof replacement at the City Council Chambers that included an asphalt primer coating, and a topcoat designed to provide enhanced protection and lower interior temperatures; replacement of the flat roof at the Community Center, redoing the valleys and repairing damaged tile areas to create a leak-free roof system; and a roof restoration at the Police Department that addressed damage to the original roof, including cracks and loss of protective granules. During the scope of work, it was determined that there were many damaged pieces of plywood and various cracked tiles on the sloped sides of the roofs that needed to be replaced. Additionally, several sections of the valleys were replaced and resealed. Even with the additional scope of work, the project remained within the contingency budget. All terms and conditions of this contract have been complied with and the work has been performed to the satisfaction of the Project Manager. R&R Roofing & Waterproofing, Inc. completed the work as defined in the project plans and specifications, in an efficient and timely manner. ENVIRONMENTAL ANALYSIS This project was considered a Class 1 exemption as defined in Section 15301(d) “Existing Facilities” projects of the California Environmental Quality Act (“CEQA”), which exempts projects consisting of the repair and maintenance of existing public structures. FISCAL IMPACT Funds in the amount of $1,500,000, for both labor and materials, were budgeted in the Fiscal Year 2023-24 Capital Improvement Program for the Reroof at Various City Facilities Project. The roofing materials were purchased under a separate contract in the amount of $133,330.08. The total construction cost was $897,085.54. This amount reflects the original contract amount of $846,440 plus quantity changes totaling $50,645.54, or 6% more than the original contract amount. The total cost for this project was $1,030,415.62. RECOMMENDATION It is recommended that the City Council determine that this project is exempt under the California Environmental Quality Act (“CEQA”); and accept all work performed by R&R Roofing & Waterproofing, Inc. for the Reroof at Various City Facilities Project as complete. Accept Reroof at Various City Facilities Project October 15, 2024 Page 3 of 3