HomeMy WebLinkAboutItem 2g: Accept Work by Palm Springs Pump and Drilling for Destruction of Longely Well No. 2 and Camino Real Well No. 1DATE: December 15, 2009
TO: Mayor and City Council
STAFF REPORT
Public Works Services Department
FROM: Pat Malloy, Assistant City Manager /Public Works Services Direct
Prepared by: Lubomir Tomaier, Principal Civil Engineer
Ken Herman, Associate Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY PALM SPRINGS PUMP &
DRILLING FOR THE DESTRUCTION OF LONGLEY WELL NO. 2 AND
CAMINO REAL WELL NO. 1 PROJECT AS COMPLETE AND
AUTHORIZE THE FINAL PAYMENT TO BE MADE IN ACCORDANCE
WITH CONTRACT DOCUMENTS
Recommendation: Approve
SUMMARY
On September 1, 2009, the City Council awarded a contract to Palm Springs Pump &
Drilling in the amount of $28,500 for the Destruction of Longley Well No. 2 and Camino
Real Well No.1 Project, plus a 10% contingency for a total project cost of $31,350. The
terms and conditions of this project have been complied with and the work has been
performed to staff's satisfaction for a total project cost of $35,890.30. This amount
reflects the original contract amount of $28,500 plus one Change Order totaling
$7,390.30 or 25.9% above the original contract amount.
Staff recommends that the City Council accept all work performed by Palm Springs
Pump & Drilling as complete and authorize the final payment to be made in accordance
with the contract documents.
BACKGROUND
Longley Well No. 2 was constructed in March of 1949 and production of the well was
stopped in 1977 due to nitrate contamination. Camino Real Well No. 1 was constructed
in December of 1949. In the later years of its production the well developed sanding
problems and collapsed in 1993. Both wells are also in the process of being replaced
with the construction of Longley Well No. 3 and Camino Well No. 3.
Page 1 of 3
Mayor and City Council
December 15, 2009
DISCUSSION
Both wells were destroyed in compliance with California Department of Public Health
requirements intended to limit contamination of ground water aquifers through out -of-
service wells. The destruction process for both wells was witnessed by a representative
(inspector) for the Los Angeles County Department of Environmental Health.
Destruction of a well involves cleaning out all loose or deleterious material from the well
casing, filling the lower section of casing with concrete slurry, perforating the upper
section of blank casing, and filling that section with concrete. The weight of the concrete
in the casing pushes the concrete slurry out through the louvers and perforations into
any voids that may exist outside the casing (see attachment for pre and post well
destruction process).
It is difficult to project the amount of concrete and concrete slurry necessary to fill a well.
The amount of underground voids behind the casing wall is generally unknown and can
be difficult and costly to determine. For the purposes of bidding, the volume of the well
casing is used as the volume of fill material required to fill the well. Payment is based on
the actual volume of material used to fill the well which is determined from material
delivery tickets. This volume may vary based on the voids which may be present
beyond the well casing.
Per Health Department inspector direction and due to the large amount of underground
voids, the contractor had to install additional concrete at the Camino Real facility (39
cubic yards) and at the Longley facility (27 cubic yards). These amounts exceeded the
amount of concrete reflected in the original bid quantity. The change order reflects the
cost for the extra concrete required to fill the two wells. Public works staff negotiated the
extra cost with the contractor to pay only for material, but not for extra labor and
equipment cost to place the extra material.
Project Cost
Original Contract Amount
Change Order No.1
Additional 66 cubic yards of concrete installed per California Public
Health Department requirement to seal underground voids around
decommissioned wells
$ 28,500.00
$ 7,390.30
Total Contract Cost $ 35,890.30
The terms and conditions of this contract have been complied with and the work has
been performed to staff's satisfaction. Therefore, staff recommends that the City
Council accept all work performed by Palm Springs Pump & Drilling as complete and
authorize the final payment to be made in accordance with the contract documents,
subject to retention of $3,589.03.
Page 2 of 3
Mayor and City Council
December 15, 2009
ENVIRONMENTAL IMPACT:
On November 18, 2008 the City Council adopted Mitigated Negative Declaration for the
project satisfying all CEQA requirements.
FISCAL IMPACT
Water Funds in the amount of $3,400,000 are budgeted in the '2008-2009 Capital
Improvement Program for the Longley and Camino Well Construction Project. Well
destruction is included as a part of this work.
RECOMMENDATIONS
1. Accept all work performed by Palm Springs Pump & Drilling for the
Destruction of Longley Well No. 2 and Camino Real Well No.1 Project as
complete.
2. Authorize final payment to be made in accordance with the contract
documents, subject to retention of $3,589.03.
PM:LT:KH
Approved by:
Page 3 of 3
Donald Penman, City Manager
GROUND LEVEL
GRAVEU SAND
WATER BEARING
STRATA
GRAVEL/ SAND
WATER BEARING
STRATA
PRE - DESTRUCTION
1
WELL PEDESTAL
GROUND LEVEL
23 SACKS
NEAT
CEMENT
NEW
PERFORATIONS
23 SACKS
NEAT
CEMENT
POST - DESTRUCTION
WELL PEDESTAL
EW
PERFORATIONS
23 SACKS
NEAT
CEMENT
GRAVEU SAND
WATER BEARING
STRATA
GRAVED SAND
WATER BEARING
STRATA
NEW
PERFORATIONS