Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutItem 09f - Valve Replacement ProjectAward Valve Replacement Project
May 6, 2025
Page 1 of 3
DATE: May 6, 2025
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Tiffany Lee, P.E., Interim Principal Civil Engineer
SUBJECT: CONTRACT WITH AMERICAN PIPELINE SERVICES FOR THE VALVE
REPLACEMENT PROJECT IN THE AMOUNT OF $92,950
CEQA: Exempt
Recommendation: Approve
SUMMARY
As part of the City’s valve exercising program, the Public Works Services Department
(“PWSD”) inspects water valves for proper functioning and identifies valves that are broken
or in need of repair. During a routine inspection, two locations were identified as having
inoperable valves that need replacement – specifically, at the Santa Anita Plant and the Peck
Well sites. To ensure the City is receiving the most competitive prices and quality service for
this work, the PWSD conducted a formal bid process. American Pipeline Services submitted
the lowest responsive bid.
It is recommended that the City Council approve, authorize, and direct the City Manager to
execute a contract with American Pipeline Services for the Valve Replacement Project in the
amount of $92,950, and approve a 10% contingency.
BACKGROUND
As part of the valve exercising program, valves in the water distribution system are regularly
inspected to verify functionality and identify valves that are broken or in need of repair. During
a routine inspection, it was determined that the water distribution system valves at the
following locations are inoperable and in need of replacement:
• Santa Anita Plant
• Peck Well
The 16-inch pump discharge pipe inside the Peck Well is a cement mortar lined and coated
steel pipe that was constructed in 1962. The 24-inch inlet pipe inside the Santa Anita Plant is
also a cement mortar lined and coated steel pipe that was constructed in 2000. Each pipe
Award Valve Replacement Project
May 6, 2025
Page 2 of 3
has gate valves along its length that allow water utility crews to isolate portions of the pipe in
case of an emergency or a broken water main. Due to their age, the gate valves are not fully
operational and need to be replaced. These gate valves are critical to the emergency
operation of the City’s water system. The project location is shown on Exhibit “A.”
The project involves removal and replacement of one 16-inch butterfly valve, two 18-inch
butterfly valves, and one 18-inch check valve inside the Peck Well and Santa Anita Plant.
DISCUSSION
A Notice Inviting Bids was published in accordance with City Council Resolution No. 7483,
and bid packages were distributed to contractors that perform this type of work. On April 15,
2025, the City Clerk received seven sealed bids with the following results:
Bidder Location Bid_ _
American Pipeline Services Monrovia $ 92,950
J. De Sigio Construction, Inc. Baldwin Park $ 100,630
316 Engineering & Construction, Inc. Rosemead $ 112,500
Toro Enterprises Inc. Oxnard $ 131,927
Vicon Enterprise Anaheim $ 136,500
Gentry Brothers Inc. Irwindale $ 145,000
TE Roberts Incorporated Irvine $ 170,364
Bid documents were reviewed for content and the contractor’s background was also
investigated. Based on the review, it has been determined that American Pipeline Services is
the lowest responsive bidder for this work and is qualified to complete the project as defined
in the bid documents. American Pipeline Services has successfully completed other projects
for Palmdale Water District, the California Department of General Services, the Department
of the Navy, the California National Guard, and the City of Pico Rivera.
ENVIRONMENTAL ANALYSIS
The project involves the replacement and minor alteration of an existing utility system with no
expansion of the system, and therefore, qualifies as a Class 2 categorical exemption per
Section 15302(2) of the California Environmental Quality Act (“CEQA”).
FISCAL IMPACT
Funds in the amount of $250,000 have been budgeted in the Fiscal Year 2024-25 Capital
Improvement Program for the Valve Replacement Project. The total cost for the Valve
Replacement Project is $92,950, and a 10% contingency would bring the total cost to
$102,245, which is within the adopted budget.
Award Valve Replacement Project
May 6, 2025
Page 3 of 3
RECOMMENDATION
It is recommended that the City Council determine that this project is exempt under the
California Environmental Quality Act (“CEQA”); and approve, authorize, and direct the City
Manager to execute a contract with American Pipeline Services for the Valve Replacement
Project in the amount of $92,950, and approve a 10% contingency.
Attachments: Exhibit “A” - Project Location Map
Proposed Contract
CITY OF ARCADIA
VALVE REPLACEMENT PROJECT
PROJECT NO. 61720325
BETWEEN
CITY OF ARCADIA
AND
AMERICAN PIPELINE SERVICES
CONTRACT
Contract - 1
CONTRACT FOR THE
CITY OF ARCADIA
This CONTRACT, No. ________ is made and entered into this ____ day of _______, ______, by
and between City of Arcadia, sometimes hereinafter called “City,” and American Pipeline
Services, sometimes hereinafter called “Contractor.”
WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these
presents do covenant and agree with each other as follows:
A. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated in the
Contract, and shall provide all labor, materials, equipment, tools, utility services, and
transportation to complete all of the Work required in strict compliance with the Contract
Documents as specified in Article 5, below, for the following Project:
VALVE REPLACEMENT PROJECT / PROJECT NO. 61720325
The Contractor and its surety shall be liable to the City for any damages arising as a result of
the Contractor’s failure to comply with this obligation.
B. TIME FOR COMPLETION. Time is of the essence in the performance of the Work. The Work
shall be commenced on the date stated in the City’s Notice to Proceed. The Contractor shall
complete all Work required by the Contract Documents within FOURTEEN (14) CALENDAR
DAYS calendar days from the commencement date stated in the Notice to Proceed. By its
signature hereunder, Contractor agrees the time for completion set forth above is adequate and
reasonable to complete the Work.
C. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for the
performance of the Contract, subject to any additions or deductions as provided in the Contract
Documents, and including all applicable taxes and costs, the sum of NINETY-TWO THOUSAND,
NINE HUNDRED FIFTY DOLLARS AND NO CENTS ($92,950.00). Payment shall be made as
set forth in the General Conditions.
D. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85, it is
agreed that the Contractor will pay the City the sum set forth in Special Conditions, Article 1.11
for each and every calendar day of delay beyond the time prescribed in the Contract Documents
for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this
is not paid, the Contractor agrees the City may deduct that amount from any money due or that
may become due the Contractor under the Contract. This Article does not exclude recovery of
other damages specified in the Contract Documents.
E. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the
following:
Notice Inviting Bids
Instructions to Bidders
Bid Form
Bid Bond
Designation of Subcontractors
Information Required of Bidders
Non-Collusion Declaration Form
Iran Contracting Act Certification
Public Works Contractor Registration Certification
Contract - 2
Performance Bond
Payment (Labor and Materials) Bond
General Conditions
Special Conditions
Technical Specifications
Addenda
Plans and Drawings
Standard Specifications for Public Works Construction “Greenbook”, latest edition, Except
Sections 1-9
Applicable Local Agency Standards and Specifications, as last revised
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract
The Contractor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the
Contract Documents and not by others shall be done as if required by all. This Contract shall
supersede any prior agreement of the parties.
F. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE. Each and every
provision of law required to be included in these Contract Documents shall be deemed to be
included in these Contract Documents. The Contractor shall comply with all requirements of
applicable federal, state and local laws, rules and regulations, including, but not limited to, the
provisions of the California Labor Code and California Public Contract Code which are applicable
to this Work.
G. INDEMNIFICATION. Contractor shall provide indemnification and defense as set forth in the
General Conditions.
H. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in
accordance with the Labor Code which such rates shall be made available at the City’s
Administrative Office or may be obtained online at dir.ca.gov and which must be posted at the job
site.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
Contract - 3
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on
the day and year above written.
CITY OF ARCADIA
By:
Dominic Lazzaretto
City Manager
AMERICAN PIPELINE SERVICES
By:
Signature
Print Name and Title
Attest:
By:
City Clerk
By:
Signature
Print Name and Title
Approved as to Form:
Michael J. Maurer
City Attorney