HomeMy WebLinkAboutItem 11u - Accept ADA Curb Ramp Project as Complete
DATE: June 17, 2025
TO: Honorable Mayor and City Council
FROM: Jason Kruckeberg, Assistant City Manager/Development Services Director
Kevin Merrill, City Engineer
By: Johnathan Doojphibulpol, Principal Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY CARTER ENTERPRISES
GROUP, INC. FOR THE AMERICANS WITH DISABILITIES ACT CURB
RAMP PROJECT IN THE AMOUNT OF $211,886
CEQA: Exempt
Recommendation: Approve
SUMMARY
On March 4, 2025, the City Council awarded a contract to Carter Enterprises Group, Inc.,
in the amount of $211,000, for the Americans with Disabilities Act (“ADA”) Curb Ramp
Project. During the project, there was one (1) Change Order for final quantity adjustments,
totaling an increase of $886, or about 0.4% of the original contract amount.
The terms and conditions of this project have been complied with, and the required work
has been performed to the City’s satisfaction, for a final cost of $211,886. It is
recommended that the City Council accept the project as complete and authorize the final
payment in accordance with the approved contract.
BACKGROUND
On January 21, 2025, the City Council approved Resolution No. 7610, authorizing an
amendment to the Statement of Objectives and Projects for the Community Development
Block Grant (“CDBG”) Program, and adding the proposed Curb Ramp Project to the
Fiscal Year 2024-25 Capital Improvement Program. The ADA Curb Ramp Project
constructed 16 accessible curb ramps throughout the City. Locations for the new ramps
were chosen based on a number of factors, which included engineering analysis, resident
requests, the absence of existing ramps, and the proximity of the proposed locations to
schools. Selected locations for the ramps were:
• Eight (8) ramps located on Sierra Madre Boulevard between Claridge Street and
Perkins Drive.
ADA Curb Ramp Project
June 17, 2025
Page 2 of 3
• Two (2) ramps located at Sunset Boulevard and Okoboji Drive.
• Two (2) ramps located at Lovell Avenue and Winnie Way.
• Four (4) ramps located on Hugo Reid Drive at Magellan Drive and Old Ranch
Road.
The project was advertised for bids in January 2025 and bids were opened on February
13, 2025, with Carter Enterprises Group, Inc. as the qualifying low bidder with a $211,000
bid. A contract in the amount of $211,000 was awarded by the City Council on March 4,
2025.
DISCUSSION
Construction began in April 2025 and was completed in May 2025. There was one
Change Order for the final adjustment of quantities, totaling a net increase of $886.
Quantity adjustments on the project include a slight decrease in the sidewalk, curb and
gutter constructed, and an increase in cross gutter and spandrel. As a result of the
adjustments, the final amount is a net increase of $886, about 0.4% of the contract
amount. A summary of the construction contract, with the Change Order, is as follows:
Original Contract: $211,000
Change Order #1 (Quantity Adjustment) $866
Final Total Contract: $211,866
ENVIRONMENTAL ANALYSIS
This project is categorically exempt pursuant to the California Environmental Quality Act
(“CEQA”) under Section 15301 (Existing Facilities) and Section 15302 (Replacement or
Reconstruction). The project is constructing curb ramps at existing infrastructure locations
and replacing sidewalks, curbs and gutters, cross gutters, and spandrels where they are
damaged or not up to industry standards, with no expansion of use; therefore, the
exemption is warranted.
FISCAL IMPACT
This project is funded from two sources: $160,000 of CDBG funds and $58,729.53 of
Transportation Development Act Article 3 (“TDA 3”) funds. The CDBG funds were
appropriated for the project by the City Council at the January 21, 2025, meeting. TDA
Article 3 funds are appropriated each year for ADA projects and funds are available from
the Fiscal Year 2023-24 and 2024-25 budgets. Combined, CDBG and TDA Article 3 funds
provide a sufficient budget to cover the final contract amount of $211,886.
ADA Curb Ramp Project
June 17, 2025
Page 3 of 3
RECOMMENDATION
It is recommended that the City Council determine that the proposed action is exempt
under the California Environmental Quality Act (“CEQA”); and accept all work performed
by Carter Enterprises Group, Inc. for the Americans with Disabilities Act Curb Ramp
Project as complete; and authorize the final payment to be made in accordance with the
contract documents.