HomeMy WebLinkAboutItem 7i - Accept Baldwin Booster D Project
STAFF REPORT
PUBLIC WORKS SERVICES DEPARTMENT
DATE: October 21, 2025
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Tiffany Lee, Interim Principal Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY GENERAL PUMP COMPANY, INC.
FOR THE REMOVAL AND REPLACEMENT OF BALDWIN BOOSTER PUMP
D PROJECT AS COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On June 18, 2024, the City Council approved a contract with General Pump Company,
Inc. in the amount of $139,790, with a 10% contingency for the removal and
replacement of Baldwin Booster Pump D. Due to unforeseen issues with the Baldwin
Booster, a change order to the Contract with General Pump Company, Inc. was
approved on April 15, 2025, in the amount of $23,039.65, bringing the total contract
amount to $162,829.65. The terms and conditions of this project have been met, and
the work has been performed to the satisfaction of the Project Manager for a total
project cost of $162,826.12.
It is recommended that the City Council accept all work performed by General Pump
Company, Inc. for the Removal and Replacement of Baldwin Booster Pump D Project
as complete and authorize the final payment to be made in accordance with the
contract documents, subject to the retention of $8,141.31.
BACKGROUND
The City of Arcadia’s water system annually delivers an average of 13,000 acre-feet
of potable drinking water to approximately 15,000 water service connections. The
water supply for the system is obtained from 10 active groundwater wells. The water
Accept Removal and Replacement of Baldwin Booster D Project
October 21, 2025
Page 2 of 3
system also utilizes 29 booster pumps that pump water through the distribution
system, and 15 reservoirs that hold approximately 45 million gallons of water. The
Public Works Services Department (“PWSD”) is responsible for the daily operation
and maintenance of the City’s wells and booster pumps. Regular inspections and
maintenance of booster pumps is crucial to ensuring that the pumps are operating
at their maximum capacity and efficiency. Regular inspections and maintenance of
the Baldwin Boosters revealed that Booster Pump D was in need of replacement. The
Baldwin Booster system consists of three booster pumps: B, C, and D. The two 100
horsepower Booster Pumps, B and C, were rehabilitated in 2018. The remaining 60
horsepower Booster Pump D was at the end of its useful life and needed
replacement.
DISCUSSION
On June 18, 2024, the City Council approved a contract with General Pump Company,
Inc., in the amount of $139,790, with a 10% contingency for the removal and
replacement of Baldwin Booster Pump D. General Pump Company, Inc. installed the
new booster pump assembly and was preparing for startup. While preparing for
startup, it was determined that the existing soft start panel and overload relay were
too small to accommodate the upgraded motor. A starter upgrade was necessary to
operate the new booster pump assembly. On April 15, 2025, the City Council
approved a change order to the contract with General Pump Company, Inc. to include
a starter upgrade for the enhanced motor, in the amount of $23,039.65, bringing the
total contract amount to $162,829.65. The terms and conditions of this contract have
been complied with, and the work has been performed to the satisfaction of the
Project Manager. General Pump Company, Inc. completed the work in an efficient
manner, as defined in the project plans and specifications.
ENVIRONMENTAL ANALYSIS
The project involves the replacement and minor alteration of an existing utility
system, with no expansion of the system. As such, the project qualifies as a Class 2
categorical exemption per Section 15302(2) of the California Environmental Quality
Act (“CEQA”).
Accept Removal and Replacement of Baldwin Booster D Project
October 21, 2025
Page 3 of 3
FISCAL IMPACT
Funds in the amount of $200,000 were budgeted in the Fiscal Year 2023-24 Capital
Improvement Program for the removal and replacement of Baldwin Booster Pump
D. The total cost for the removal and replacement of Baldwin Booster Pump D is
$162,826.12. On June 18, 2024, the City Council approved a contract with General
Pump Company, Inc. in the amount of $139,790, with a 10% contingency for the
removal and replacement of Baldwin Booster Pump D. A change order to the
contract with General Pump Company, Inc. was approved on April 15, 2025, in the
amount of $23,039.65, bringing the total contract amount to $162,829.65. Sufficient
funds are available for this project.
RECOMMENDATION
It is recommended that the City Council determine that this project is a Class 2
exemption under the California Environmental Quality Act (“CEQA”); and accept all
work performed by General Pump Company, Inc. for the Removal and Replacement
of Baldwin Booster Pump D Project as complete, and authorize the final payment to
be made in accordance with the contract documents, subject to the retention of
$8,141.31.