HomeMy WebLinkAboutItem 10d - Baldwin Avenue Concrete Rehabilitation Improvements Project
STAFF REPORT
DEVELOPMENT SERVICES DEPARTMENT
DATE: February 17, 2026
TO: Honorable Mayor and City Council
FROM: Lisa Flores, Interim Development Services Director
Kevin Merrill, City Engineer
By: Johnathan Doojphibulpol, Principal Civil Engineer
SUBJECT: CONTRACT WITH GENTRY BROTHERS, INC. FOR THE BALDWIN AVENUE
CONCRETE REHABILITATION IMPROVEMENTS PROJECT IN THE AMOUNT
OF $1,227,444.50
CEQA: Exempt
Recommendation: Approve
SUMMARY
The Baldwin Avenue Concrete Rehabilitation Improvements Project includes
concrete street, curb ramp, and sidewalk improvements on Baldwin Avenue, from
Camino Real Avenue to Longden Avenue. The project also includes alternate bid
items for concrete rehabilitation of the intersections of Live Oak Avenue with Las
Tunas Drive, Santa Anita Avenue, and Second Avenue. The project was advertised for
bids on November 20, 2025, and bids were opened on December 11, 2025. Two (2)
bids were received, with Gentry Brothers, Inc. submitting the lowest responsive bid.
It is recommended that the City Council find the project Categorically Exempt
pursuant to the requirements of the California Environmental Quality Act (“CEQA”);
and authorize and direct the City Manager to execute a contract with Gentry
Brothers, Inc. for the Baldwin Avenue Concrete Rehabilitation Improvements Project
in the amount of $1,227,444.50, plus a 10% contingency.
BACKGROUND
The Baldwin Avenue Concrete Rehabilitation Improvements Project proposes
concrete street rehabilitation using a diamond grind method to provide a smoother
Baldwin Concrete Rehabilitation Improvements Project
February 17, 2026
Page 2 of 4
driving experience, along with spall concrete repairs in areas requiring more detailed
attention. Additional improvements include the installation of accessible curb ramps
and sidewalk improvements. The project was originally planned to rehabilitate
Baldwin Avenue from Camino Real Avenue to Live Oak Avenue, and to include
concrete rehabilitation of the intersections of Live Oak Avenue and Las Tunas Drive,
Santa Anita Avenue, and Second Avenue.
The project was subsequently combined with the Baldwin Avenue at Longden
Avenue Traffic Signal Improvement Project and the Traffic Signal Fiber Optics
Network Extensions project, and all were bid together on August 22, 2024. However,
the bids were rejected on October 1, 2024, as they exceeded the budgeted amount.
As a result, the projects were separated, and the traffic signal portion was rebid, with
bids opened on December 5, 2024. The City Council awarded this portion of the work
to PTM General Engineering Services on January 21, 2025. The rebid of the concrete
rehabilitation work was postponed until a timeline for the traffic signal project could
be determined, as traffic signal equipment has long lead times and related street
work must be completed before rehabilitation can occur.
Sunny Slope Water, which serves a section of the City of Arcadia along Baldwin
Avenue, notified the City of a planned water main replacement project along Baldwin
Avenue, from Garibaldi Avenue to Live Oak Avenue. To avoid potential conflicts and
damage to new concrete, the section from Longden Avenue to Live Oak Avenue was
removed from the rehabilitation project scope of work.
With the scope revised to rehabilitate Baldwin Avenue from Camino Real Avenue to
Longden Avenue, the project was repackaged to include alternate bid items for
concrete rehabilitation at the intersections of Live Oak Avenue and Las Tunas Drive,
Santa Anita Avenue, and Second Avenue.
DISCUSSION
A Notice Inviting Bids was published on November 20, 2025. On December 11, 2025,
the City received two (2) bids, summarized below:
Bidder Base Bid Amount Bid with Alternates
Gentry Brothers, Inc. $793,392.00 $1,227,444.50
PALP, Inc dba Excel Paving $3,389,598.00 $5,068,293.00
Baldwin Concrete Rehabilitation Improvements Project
February 17, 2026
Page 3 of 4
With only two bidders, the discrepancy in bid amount needed evaluation. PALP, Inc.
did not file a protest but submitted information challenging Gentry Brothers, Inc.’s
bid. The bid summary and PALP, Inc’s information was provided to the City’s on-call
design firm, Kreuzer Consulting Group, for review. It was determined that although
the Gentry Brothers bid was lower than the engineer’s estimate, it was closer to the
estimate than PALP, Inc’s bid.
Gentry Brothers, Inc. was then contacted to confirm that, with the knowledge of the
PALP bid, they would still honor their bid price. Their representative confirmed that
there were no issues with the bid. With the lower base bid, there is sufficient budget
to include the alternate bid items as well.
ENVIRONMENTAL ANALYSIS
This project is Categorically Exempt from the California Environmental Quality Act
(“CEQA”) pursuant to Sections 15301 (Class 1 Existing Facilities) and 15302 (Class 2 -
Replacement or Reconstruction).
FISCAL IMPACT
The Baldwin Avenue Concrete Rehabilitation project was first budgeted in the Fiscal
Year 2020-21Capital Improvement Program (“CIP”) with $1,000,000 of Proposition C
(“Prop C”) funds. A portion of these funds were used for the design of this project and
other CIP projects, leaving a remaining balance of $675,171.95.
The Live Oak Avenue portions of the project were budgeted in the Fiscal Year 2021-
22 CIP with $300,000 of Prop C funds, of which $60,866.10, remains after design.
Additional Prop C funds of $200,000 and $900,000 were programmed in Fiscal Years
2022-23 and 2025-26, respectively, and those funds remain untouched. The total
available funds for the project are summarized below:
Programmed Fiscal Year Available Funds
2020-21 $675,171.95
2021-22 $60,866.10
2022-23 $200,000.00
2025-26 $900,000.00
Total Funds $1,836,038.05
Baldwin Concrete Rehabilitation Improvements Project
February 17, 2026
Page 4 of 4
The full bid amount, including alternate bid items, totals $1,227,444.50. With a 10%
contingency, the total budget is $1,350,188.95. Therefore, there are sufficient funds
available to cover the full bid amount with a 10% contingency.
RECOMMENDATION
It is recommended that the City Council find the project categorically exempt under
the California Environmental Quality Act (“CEQA”); and authorize and direct the City
Manager to execute a contract with Gentry Brothers, Inc. for the Baldwin Avenue
Concrete Rehabilitation Improvements Project in the amount of $1,227,444.50, plus
a 10% contingency.