HomeMy WebLinkAboutDowntown 2000 - Storm Drain Project with County of LAHARRY W. STONE, Director
DEPARTMENT OF PUBLIC WORKS
900 SOUTH FREMONT AVENUE
ALHAMBRA, CALIFORNIA 91803 -1331
Telephone: (818) 458 -5100
February 15, 1996
Mr. Richard Gomez
Development Services Director/
Deputy City Manager
City of Arcadia
P.O. Box 60021
Arcadia, CA 91066 -6021
Attention Mr. Mohammad R. Mostahkami
Dear Mr. Gomez:
ARCADIA DOWNTOWN 2000 STREETSCAPE PROJECT
CITY - COUNTY AGREEMENT NO. 68792
L.AC
B 2 2
({X�
ADDRESS ALL CORRESPONDENCE TO:
P.O,BOX 1460
ALHAMBRA, CALIFORNIA 91802 -1460
IN REPLY PLEASE
REFER TO FILE: F-0
1996
n gineering Division'""
Enclosed for your file is a fully executed original of the Agreement
for this project. The Agreement was approved by the County Board of
Supervisors on February 6, 1996.
If you have any questions, please contact our Project Manager,
Mr. Dave Pilker, at (818) 458 -5196.
Very truly yours,
HARRY W. STONE
Director of Public Works
SHARI AFS RI
Supervising Civil Engineer III
Flood Management Group
DP: ad
ARC2TRAN
Enc
RECENVED
F i 1 ` Q i q F X163
R � � d..S � 61
l I (oroyir�/
COUNTY OF LOS ANGELES
Development Iiervices
VI ORIC31NAL
A G R E E M E N T 7 912'
THIS AGREEMENT by and between the COUNTY OF LOS ANGELES, a
political subdivision of the State of California, hereinafter
referred to as "COUNTY," acting on behalf of the Los Angeles
County Flood Control District, a body corporate and politic; and
the CITY OF ARCADIA, a political subdivision in the County of
Los Angeles, hereinafter referred to as "CITY."
W I T N E S S E T H
WHEREAS, COUNTY is administering all matters for the
Los Angeles County Flood Control District pursuant to
Section 56-3/4 of the COUNTY'S Charter and in accordance with an
Agreement approved on December 26, 1984, between COUNTY and the
Los Angeles County Flood Control District; and
WHEREAS, CITY is proposing a storm drain project along
Huntington Drive as part of a Redevelopment project, which work
is hereinafter referred to as "PROJECT"; and
WHEREAS, PROJECT is entirely within the jurisdictional
limits of the CITY; and
WHEREAS, PROJECT is in the general interest of CITY and
COUNTY; and
-2-
WHEREAS, CITY proposes to prepare plans, specifications,
cost estimates, and administer the construction contract for
PROJECT at CITY'S cost; and
WHEREAS, in order to expedite the construction of PROJECT,
COUNTY is willing to contribute a fixed sum of four hundred
thousand dollars ($400,000) toward the construction contract cost
of PROJECT; and
WHEREAS, CITY proposes to finance the remaining costs to
construct PROJECT in excess of COUNTY'S fixed contribution.
NOW, THEREFORE, in consideration of the mutual benefits to
be derived by CITY and COUNTY and of the promises herein
contained, it is hereby agreed as follows:
(1) COUNTY AGREES:
a. To deposit with CITY four hundred thousand dollars
($400,000) upon execution of this Agreement and within
thirty (30) days of receipt of the invoice thereof.
(2) CITY AGREES:
a. To prepare plans and specifications, and to administer
the construction contract for PROJECT at CITY'S cost.
-3-
b. To advertise PROJECT for construction bids, to award
and to administer the construction contract, to do all
things necessary to complete PROJECT in accordance with
said plans and specifications.
C. To finance construction contract cost of PROJECT in
excess of COUNTY'S fixed contribution.
d. Upon completion of construction, to operate and
maintain PROJECT until PROJECT is accepted for transfer
to COUNTY.
e. To furnish COUNTY, within one hundred and twenty (120)
calendar days after the completion of PROJECT, a final
accounting of the construction contract costs of
PROJECT, including an itemization of actual unit costs
and actual quantities for project. If construction
contract cost of PROJECT is less than COUNTY'S fixed
contribution, CITY shall within sixty (60) days of
final accounting refund to COUNTY the difference
between construction contract cost of PROJECT and
COUNTY'S deposit.
-4-
(3) IT IS MUTUALLY UNDERSTOOD AND AGREED AS FOLLOWS:
a. That the construction contract costs of PROJECT, as
referred to in this Agreement, shall consist of the
total of all payments to the construction contractor
for PROJECT. The construction contract cost of PROJECT
shall not include the cost of preliminary engineering,
contract administration, construction inspection and
engineering, materials testing, construction survey and
engineering for utility relocation.
b. That COUNTY authorizes CITY to use the deposits made in
Section (1), paragraph a., at its discretion to pay its
contractor for constructing PROJECT.
C. That CITY and COUNTY shall have no financial obligation
to each other under this Agreement except as herein
expressly provided.
d. That this Agreement can be amended or terminated by
mutual written consent of both CITY and COUNTY.
e. Neither COUNTY nor any officer or employee of COUNTY
shall be responsible for any damage or liability
occurring by reason of any acts or omissions on the
part of CITY under or in connection with any work,
authority or jurisdiction delegated to CITY under this
-5-
Agreement. It is also understood and agreed that,
pursuant to Government Code, Section 895.4, CITY shall
fully indemnify, defend and hold COUNTY harmless from
any liability imposed for injury (as defined by
Government Code, Section 810.8) occurring by reason of
any acts or omissions on the part of CITY under or in
connection with any work, authority or jurisdiction
delegated to CITY under this Agreement.
f. Neither CITY nor any officer or employee of CITY shall
be responsible for any damage or liability occurring by
reason of any acts or omissions on the part of COUNTY
under or in connection with any work, authority or
jurisdiction delegated to COUNTY under this Agreement.
It is also understood and agreed that, pursuant to
Government Code, Section 895.4, COUNTY shall fully
indemnify, defend and hold CITY harmless from any
liability imposed for injury (as defined by Government
Code, Section 810.8) occurring by reason of any acts or
omissions on the part of COUNTY under or in connection
with any work, authority or jurisdiction delegated to
COUNTY under this Agreement.
-6-
g. That the provisions of any previous Assumption of
Liability Agreement heretofore entered into between the
parties hereto are inapplicable to this Agreement.
-7-
IN WITNESS WHEREOF, the parties hereto have caused this
Agreement to be executed by their respective officers, duly
authorized, by the CITY OF ARCADIA on
the COUNTY OF LOS ANGELES on 9((ko,f]6;
J
ATTEST:
JOANNE STURGES
Executive Officer-Clerk
of the Board of SupervisorF
1 1995 and by
19
CHAIR, BOARD OF SUPERVISORS
10,
25 FEB 61996
OR
APPROVED AS TO FORM
DE WITT W. CLINTON
County Counsel
JOANNE STURGEs
EXECUTIVE OFFICER
APPROVED AS TO FORM
L' - P r 1 1995
City Attorney
BY BY
-7
DEPUTY
ATTEST:
NX
BY
CITY CLER,�/
I
CITY OF ARCADIA