HomeMy WebLinkAboutItem 11j - Accept Debris Basins Debris Removal Project
STAFF REPORT
PUBLIC WORKS SERVICES DEPARTMENT
DATE: June 2, 2026
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Leonel Martin, Public Works Project Manager
SUBJECT: ACCEPT ALL WORK PERFORMED BY HORIZONS CONSTRUCTION CO.
INT’L INC. FOR THE DEBRIS BASINS DEBRIS REMOVAL PROJECT AS
COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On November 18, 2025, the City Council approved a contract with Horizons
Construction Co. Int’l Inc. in the amount of $302,828.63 for the Debris Basins Debris
Removal Project. The terms and conditions of this project have been complied with,
and the work has been performed to the satisfaction of the Project Manager for a
total project cost of $302,828.63.
It is recommended that the City Council accept all work performed by Horizons
Construction Co. Int’l Inc. for the Debris Basins Debris Removal Project as complete
and authorize the final payment to be made in accordance with the contract
documents, subject to the retention of $15,141.43.
BACKGROUND
As a result of the January 2025 Windstorm Event and subsequent Eaton Fire, the
northern hillsides above the City experienced significant wildfire damage. The
wildfire scarred and destabilized slopes, which led to the uncontrolled movement of
mud, burned vegetation, and other debris that overflowed into two debris basins
located at 2273 Highland Vista Drive and 2225 Canyon Road. The debris basins, which
are engineered to trap and control debris-laden runoff, were at capacity due to mud,
Accept Debris Basins Debris Removal Project
June 2, 2026
Page 2 of 3
burned vegetation, and other materials carried to the sites by the rains that followed
the Eaton Fire. As a result, the debris basins could no longer contain additional flows,
increasing the risk of overflow and downstream damage during future mudflow
events. Clearing the basins was necessary to restore their capacity and structural
integrity, ensuring they continue to function as intended and protect the surrounding
areas.
DISCUSSION
On November 18, 2025, the City Council approved a contract with Horizons
Construction Co. Int’l Inc. for the Debris Basins Debris Removal Project. The project
included the excavation and sorting of approximately 2,530 cubic yards of soil at the
debris basin located at 2225 Canyon Road, and approximately 250 cubic yards of soil
at the debris basin located at 2273 Highland Vista Drive. The contractor hauled and
transported the sorted soil to an approved clean dirt facility and discarded the
remaining debris at a disposal facility, to ensure compliance with environmental
regulations. In addition, after the debris removal was completed, the contractor
conducted rough grading at both sites to ensure proper drainage and stability at the
debris basins. The debris basins can now effectively capture and manage runoff and
debris, protecting downstream properties during future storm events.
All terms and conditions of the contract have been complied with, and the work has
been performed to the satisfaction of the Project Manager. Horizons Construction
Co. Int’l Inc. completed the work as defined in the project plans and specifications in
an efficient and timely manner. The project required no change orders or
adjustments.
ENVIRONMENTAL ANALYSIS
The Project is considered a Class 1 Exemption as defined in Section 15301(a) “Existing
Facilities” projects of the California Environmental Quality Act (“CEQA”), which
exempts projects consisting of the minor alteration of existing public structures.
FISCAL IMPACT
The Debris Basins Debris Removal Project was not anticipated, and therefore, was
not included in the Fiscal Year 2025-26 Capital Improvement Program Budget. As
Accept Debris Basins Debris Removal Project
June 2, 2026
Page 3 of 3
such, a budget appropriation from the Capital Outlay Fund in the amount of
$302,828.63, was requested on November 18, 2025, for this project. The total cost of
the Debris Basins Debris Removal Project is $302,828.63.
The Public Works Services Department collaborated with the Federal Emergency
Management Agency (“FEMA”) and submitted a Public Assistance request for
reimbursement of the project costs. The project remains under FEMA’s review to
determine reimbursement eligibility. Reimbursement is uncertain; however, if
approved, FEMA will reimburse the City 75% of the total cost for this project.
RECOMMENDATION
It is recommended that the City Council determine that this project is exempt under
the California Environmental Quality Act (“CEQA”); and accept all work performed by
Horizons Construction Co. Int’l Inc. for the Debris Basins Debris Removal Project as
complete and authorize the final payment to be made in accordance with the
contract documents, subject to the retention of $15,141.43.