HomeMy WebLinkAboutItem 08g - Accept First Avenue Arterial Pavement Rehabilitation Project
STAFF REPORT
PUBLIC WORKS SERVICES DEPARTMENT
DATE: October 20, 2026
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Assistant City Manager/Public Works Services Director
By: Johnathan Doojphibulpol, Principal Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY ONYX PAVING COMPANY, INC. FOR
THE FIRST AVENUE ARTERIAL PAVEMENT REHABILITATION PROJECT AS
COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On May 5, 2026, the City Council awarded a contract to Onyx Paving Company, Inc.
in the amount of $1,428,000, with a 10% contingency, for the First Avenue Arterial
Pavement Rehabilitation Project. The project has been completed in accordance with
the contract terms and to the satisfaction of the Project Manager for a total cost of
$1,570,069.96. This amount reflects the approved contract amount of $1,428,000,
plus contract change orders totaling $142,069.96, or 9.9% more.
It is recommended that the City Council accept all work performed by Onyx Paving
Company, Inc. for the First Avenue Arterial Pavement Rehabilitation Project as
complete and authorize the final payment to be made in accordance with the
contract documents.
BACKGROUND
The City annually appropriates Proposition C funding for arterial street rehabilitation
projects. A requirement for local jurisdictions to receive Federal, State, and County
funding is to maintain an updated Pavement Management Program (“PMP”). The
City’s Pavement Management Program analyzes existing street pavement conditions
through a full survey and rating of all roadways. The Pavement Condition Index (“PCI”)
Accept First Avenue Arterial Pavement Rehabilitation Project
October 20, 2026
Page 2 of 5
is used to indicate the general condition of pavement sections. The most recent PCI
survey was conducted in 2021. Although the PCI averages of First Avenue and Second
Avenue were in “fair” condition, the survey data identified First Avenue as the highest
priority secondary collector, and Second Avenue as the highest priority primary
collector, when compared to similar streets that have not already been planned for
or recently completed in the City’s Capital Improvement Program.
In February 2023, HR Green Pacific, Inc., under the On-Call Engineering Design
Services Contract, was tasked with providing the City with a design package that
included plans, specifications, and estimates for the First Avenue and Second Avenue
Arterial Pavement Rehabilitation. The proposed improvements included grinding
and overlaying asphalt pavement, re-striping pavement markings, cutting new traffic
loops, and removing and replacing concrete curb and gutter, sidewalk, driveway
aprons, and Americans with Disabilities Act (“ADA”) compliant curb ramps.
The design package was completed in July 2024. In it, First Avenue, from California
Street to Duarte Road, was planned to be narrowed with curb extensions at the
intersections; however, bike lanes, parallel parking, and two-way left-turn lanes
would remain along the segment. In addition, the existing north-south stop signs at
Diamond Street, which have been repeatedly struck by vehicles over the years, would
be moved out of the center median of the street and placed behind new curb
extensions on First Avenue.
Furthermore, over the years, the City has received requests for additional parking
from businesses along the First Avenue corridor. The City contracted with Willdan
Engineering to perform a traffic analysis for First Avenue, from California Street to
Duarte Road, mostly analyzing the potential for more parking spaces and additional
stop signs. The analysis showed that parking spaces could be gained on some blocks
using a “chicane” design that provides diagonal parking on one side of the street, as
shown in the image below.
Accept First Avenue Arterial Pavement Rehabilitation Project
October 20, 2026
Page 3 of 5
To provide safety improvements and additional traffic calming measures for the new
design, new stop signs were to be placed at El Dorado Street and Fano Street. The
construction plans were adjusted to include the recommended changes from the
study, and a bid package was prepared.
DISCUSSION
On May 5, 2026, the City Council awarded a contract to Onyx Paving Company, Inc.
in the amount of $1,428,000, with a 10% contingency, for the First Avenue Arterial
Pavement Rehabilitation Project. Construction began in June 2026 and was
completed in August 2026, with final survey monuments re-established in September
2026.
During the completion of this project, it was determined that a change order for
quantity adjustments was needed. A complete summary of the change order,
including all contract deductions and additions, is provided below.
Accept First Avenue Arterial Pavement Rehabilitation Project
October 20, 2026
Page 4 of 5
Description Amount
1. Added 1,882 SF – Cold Mill Existing A.C. Pavement (2”, Full
Width) $526.96
2. Added 338 TN – Construct (2” Hot Mix Asphalt (C2 PG64-10)
Overlay $43,264.00
3.
Added 3,512 SF – Sawcut and Remove Existing Concrete
Pavement, AC Pavement and Base Materials to a Depth of 12”
and Reconstruct Pavement with 6” AC Over 6” CMB
$36,876.00
4. Added 588 LF – Remove and Reconstruct 8” PCC Curb and
Gutter $65,268.00
5. Added 3,738 SF – Remove and Reconstruct 4” PCC Sidewalk $48,594.00
6.
Deleted 14 LF – Furnish and Install Galvanized Steel
Checkered Plate Powder Coated Gray and Bolt Flush into Curb
per Plan
($6,300.00)
7. Deleted 1,222 SF – Remove and Reconstruct PCC Cross Gutter
and Spandrel ($34,216.00)
8. Added 1 EA – Remove and Reconstruct PCC Curb Ramp (BCR
to ECR, Including Curb Extensions) $6,369.00
9. Added 4 EA – Remove Existing and Furnish and Install New
Water Meter Box Per Std. 700 $3,108.00
10. Deleted 510 SF – Remove, Grade, and Replace Pavers in kind ($21,420.00)
Total $142,069.96
All terms and conditions of the contract have been complied with, and the work has
been performed to the satisfaction of the Project Manager. Onyx Paving Company,
Inc. completed the work as defined in the project plans and specifications in an
efficient and timely manner.
ENVIRONMENTAL ANALYSIS
Under the California Environmental Quality Act (“CEQA”) Guidelines, this project is
categorically exempt per Section 15301 as a Class 1, Existing Facility, and Section
15302 as a Class 2, Replacement or Reconstruction.
Accept First Avenue Arterial Pavement Rehabilitation Project
October 20, 2026
Page 5 of 5
FISCAL IMPACT
This project was budgeted in the Fiscal Year 2022-23 Capital Improvement Program
for a total of $2 million in Proposition C funds. After expenses for the design contract
with HR Green Pacific, Inc., construction contract for the Second Avenue Arterial
Pavement Rehabilitation Project, and various administrative costs, the current
project balance was $1,106,163.97. The low bid plus a 10% contingency would
require a project budget balance of $1,570,800 to complete the work.
To cover the remaining costs, the City Council authorized an additional appropriation
in the amount of $500,000 from Proposition C funds to cover the shortfall. The total
cost for the First Avenue Arterial Pavement Rehabilitation Project is $1,570,069.96.
This amount reflects the approved contract amount of $1,428,000, plus contract
change orders totaling $142,069.96, or 9.9% more than the approved contract
amount. Therefore, the authorized funds are sufficient to close out this project.
RECOMMENDATION
It is recommended that the City Council find the project categorically exempt under
the California Environmental Quality Act (“CEQA”); and accept all work performed by
Onyx Paving Company, Inc. for the First Avenue Arterial Pavement Rehabilitation
Project as complete and authorize the final payment to be made in accordance with
the contract documents.