STAFF REPORT
PUBLIC WORKS SERVICES DEPARTMENT
DATE: March 3, 2026
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Carlos Aguilar, General Services Superintendent
SUBJECT: ACCEPT ALL WORK PERFORMED BY CARRIER CORPORATION FOR THE
UPPER CITY HALL HVAC SPLIT SYSTEMS PROJECT AS COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On July 15, 2025, the City Council approved a contract with Carrier Corporation in the
amount of $126,085 for the Upper City Hall HVAC Split Systems Project. The terms
and conditions of this project have been complied with, and the work has been
performed to the satisfaction of the Project Manager for a total project cost of
$125,185. This amount reflects the approved contract amount of $126,085, less
minor cost savings resulting from unused labor hours totaling $900, or 0.71% less
than the approved contract amount.
It is recommended that the City Council accept all work performed by Carrier
Corporation for the Upper City Hall HVAC Split Systems Project as complete and
authorize the final payment to be made in accordance with the contract documents,
subject to the retention of $12,518.50.
BACKGROUND
The Public Works Services Department (“PWSD”) is responsible for the maintenance
and repair of all City facilities, which include the Heating, Ventilation, and Air
Conditioning (“HVAC”) units. Although there are HVAC units that serve the upper level
of City Hall, these units are only located on the west side of the building and there
are no HVAC units dedicated to cooling the north side of Upper City Hall. When City
Accept Upper City Hall HVAC Split Systems Project
March 3, 2026
Page 2 of 3
Hall was expanded many years ago, the ductwork was extended to supply air to the
north side of the building; however, the airflow has never been sufficient to properly
cool the area. The installation of three new split-system HVAC units in the north part
of Upper City Hall was needed to ensure adequate cooling.
DISCUSSION
On July 15, 2025, the City Council approved a contract with Carrier Corporation for
the Upper City Hall HVAC Split Systems Project. As part of this project, three new
HVAC split systems in the north portion of Upper City Hall were installed. Each system
consists of a three-ton heat pump condenser, paired with two separate 1.5-ton wall-
mounted air handling units, totaling six condensers installed at ground level in the
planter area. The new air-handlers were placed in six locations to ensure adequate
cooling throughout all areas of the north portion of Upper City Hall. In addition, new
refrigerant line sets, electrical connections to the new units, and thermostats were
included for a complete installation.
It was anticipated that approximately 40 hours of labor would be required for two
HVAC technicians to complete installation work on Saturdays, in order to minimize
disruptions during regular work hours. However, it was later determined that the
work could be completed at alternate times with minimal interruptions to
operations. As a result, a portion of the labor needed to complete this project was
eliminated, resulting in a cost savings of $900.
All terms and conditions of the contract have been complied with, and the work has
been performed to the satisfaction of the Project Manager. Carrier Corporation
completed the work as defined in the project plans and specifications in an efficient
and timely manner.
ENVIRONMENTAL ANALYSIS
This Project was considered a Class 1 exemption as defined in Section 15301(a)
“Existing Facilities” projects of the California Environmental Quality Act (“CEQA”),
which exempts projects consisting of the minor alteration of existing public
structures.
Accept Upper City Hall HVAC Split Systems Project
March 3, 2026
Page 3 of 3
FISCAL IMPACT
Funds in the amount of $138,639.35 were available in the combined Capital
Improvement Program budgets for this work: Fiscal Year 2022-23 Annual
Replacement of HVAC Units Project; Fiscal Year 2023-24 Annual Replacement of
HVAC Units Project; Fiscal Year 2023-24 Council Chamber Chiller Replacement
Project; and Fiscal Year 2024-25 Library Cooling Tower Replacement Project. The total
project cost for the HVAC split systems for upper City Hall was $125,185, which
reflects the approved contract amount of $126,085, minus cost savings of $900, or
0.71%.
RECOMMENDATION
It is recommended that the City Council determine that this project is exempt under
the California Environmental Quality Act (“CEQA”); and accept all work performed by
Carrier Corporation for the Upper City Hall HVAC Split Systems Project as complete
and authorize the final payment to be made in accordance with the contract
documents, subject to the retention of $12,518.50.