HomeMy WebLinkAboutItem 09i - Sewer Main Replacement Program
STAFF REPORT
PUBLIC WORKS SERVICES DEPARTMENT
DATE: October 6, 2026
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Assistant City Manager / Public Works Services Director
By: Michael Kwok, Associate Civil Engineer
SUBJECT: CONTRACT WITH GRBCON, INC. FOR THE SEWER MAIN REPLACEMENT
PROGRAM IN THE AMOUNT OF $1,054,543, WITH A 10% CONTINGENCY
CEQA: Exempt
Recommendation: Approve
SUMMARY
The Fiscal Year 2025-26 Capital Improvement Program Budget provides funding for
the replacement of existing 8–inch and 10-inch sewer mains with 12-inch sewer
mains, along Santa Anita Avenue, between Christina Street and the alley north of El
Dorado Street. The improvements are intended to accommodate future sewer
demand and reduce potential sewer spills.
To obtain competitive pricing and ensure quality service, the City conducted a formal
competitive bidding process for the project. GRBCON, Inc. submitted the lowest
responsive bid. It is recommended that the City Council approve, authorize, and
direct the City Manager to execute a contract with GRBCON, Inc. for the Sewer Main
Replacement Program in the amount of $1,054,543, with a 10% contingency.
BACKGROUND
In 2006, the State Water Resources Control Board adopted the Waste Discharge
Requirements Program for publicly owned sanitary sewer collection systems in
California with more than one mile of sewer pipeline. Under this program, the City is
required to develop and implement a Sewer System Management Plan (“SSMP”).
Award Sewer Main Replacement Program
October 6, 2026
Page 2 of 4
The SSMP establishes routine preventative operation and maintenance activities
designed to support the City’s goal of preventing sanitary sewer overflows. These
activities include annual inspections, routine sewer main cleaning, repair of damaged
or deteriorated sewer infrastructure, and replacement of sewer mains operating
above their design capacity.
The City of Arcadia’s 2022 Sewer Master Plan Study identified and prioritized
segments of sanitary sewer system that are operating at or above their design
capacity. Several segments along Santa Anita Avenue were identified as inadequate
to accommodate current peak flows. Anticipated development along Santa Anita
Avenue is expected to generate additional sewer flows, further increasing demand
on the system and the potential for sewer backups and overflows.
To address these capacity deficiencies, the existing 8-inch and 10-inch sewer mains
along Santa Anita Avenue, between Christina Street and the alley north of El Dorado
Street, will be replaced with new 12-inch sewer mains. The larger-diameter sewer
mains will provide additional capacity to accommodate peak flows and reduce the
potential for sewer backups.
The project will utilize in-ground pipe bursting to replace the existing sewer mains.
This trenchless construction method will minimize the amount of excavation
required and reduce impacts to traffic along Santa Anita Avenue during construction.
Construction is anticipated to begin in December and is expected to take
approximately three months to complete. A Project Location Map is provided as
Exhibit “A”.
DISCUSSION
A Notice Inviting Bids was published on August 10, 2026, in accordance with City
Council Resolution No. 7483, and bid packages were provided to contractors that
perform this type of work. On September 1, 2026, the City Clerk received five bids
with the following results:
Bidder Location Bid Amount
GRBCON, Inc. Baldwin Park, CA $ 1,054,543
Torres Sanitation Systems Const. South Gate, CA $ 1,074,500
Ramona, Inc. Baldwin Park, CA $ 1,242,000
Award Sewer Main Replacement Program
October 6, 2026
Page 3 of 4
Bidder Location Bid Amount
We R Builders, Inc. Riverside, CA $ 1,379,000
T.E. Roberts, Inc. Irvine, CA $ 1,402,303
All bid documents were reviewed for content, and the contractor’s background was
investigated. Based on the review, it was determined that GRBCON, Inc. is the lowest
responsive bidder and is qualified to complete the project as defined in the bid
documents. GRBCON, Inc. has successfully completed similar projects on time and
within budget for Arcadia as well as the Cities of Alhambra and West Covina.
ENVIRONMENTAL ANALYSIS
This project involves the replacement and minor alteration of an existing utility
system with no expansion of the system, and therefore, qualifies as a Class 2
categorical exemption per Section 15302(2) of the California Environmental Quality
Act (“CEQA”).
FISCAL IMPACT
Funds in the amount of $1,350,000 have been budgeted in the FY 2025-26 Capital
Improvement Program for the Sewer Main Replacement Program. The total
construction cost for this project is $1,054,543. A 10% construction contingency
would bring the total cost to $1,159,997.30, which is within the adopted budget.
RECOMMENDATION
It is recommended the City Council determine that this project is exempt under the
California Environmental Quality Act (“CEQA”); and approve, authorize, and direct the
City Manager to execute a contract with GRBCON, Inc. for the Sewer Main
Replacement Program in the amount of $1,054,543, with a 10% contingency.
Award Sewer Main Replacement Program
October 6, 2026
Page 4 of 4
Attachments: Exhibit “A” - Project Location Map
Proposed Contract
CITY OF ARCADIA
SEWER MAIN REPLACEMENT PROGRAM
PROJECT NO.: 33861626
BETWEEN
CITY OF ARCADIA
AND
GRBCON, INC.
CONTRACT
Contract - 1
CONTRACT FOR THE
CITY OF ARCADIA
This CONTRACT, No. ________ is made and entered into this ____ day of _______, ______, by
and between City of Arcadia, sometimes hereinafter called “City,” and GRBCON, INC.,
sometimes hereinafter called “Contractor.”
WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these
presents do covenant and agree with each other as follows:
A. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated in the
Contract, and shall provide all labor, materials, equipment, tools, utility services, and
transportation to complete all of the Work required in strict compliance with the Contract
Documents as specified in Article 5, below, for the following Project:
Sewer Main Replacement Program / Project No.: 33861626
The Contractor and its surety shall be liable to the City for any damages arising as a result of
the Contractor’s failure to comply with this obligation.
B. TIME FOR COMPLETION. Time is of the essence in the performance of the Work. The Work
shall be commenced on the date stated in the City’s Notice to Proceed. The Contractor shall
complete all Work required by the Contract Documents within 90 calendar days from the
commencement date stated in the Notice to Proceed. By its signature hereunder, Contractor
agrees the time for completion set forth above is adequate and reasonable to complete the Work.
C. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for the
performance of the Contract, subject to any additions or deductions as provided in the Contract
Documents, and including all applicable taxes and costs, the sum of ONE MILLION, FIFTY-FOUR
THOUSAND, FIVE HUNDRED FORTY-THREE DOLLARS AND NO CENTS ($1,054,543.00).
Payment shall be made as set forth in the General Conditions.
D. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85, it is
agreed that the Contractor will pay the City the sum set forth in Special Conditions, Article 1.11
for each and every calendar day of delay beyond the time prescribed in the Contract Documents
for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this
is not paid, the Contractor agrees the City may deduct that amount from any money due or that
may become due the Contractor under the Contract. This Article does not exclude recovery of
other damages specified in the Contract Documents.
E. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the
following:
Notice Inviting Bids
Instructions to Bidders
Bid Form
Bid Bond
Designation of Subcontractors
Information Required of Bidders
Non-Collusion Declaration Form
Iran Contracting Act Certification
Public Works Contractor Registration Certification
Performance Bond
Contract - 2
Payment (Labor and Materials) Bond
General Conditions
Special Conditions
Technical Specifications
Addenda
Plans and Drawings
Standard Specifications for Public Works Construction “Greenbook”, latest edition, Except
Sections 1-9
Applicable Local Agency Standards and Specifications, as last revised
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract
The Contractor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the
Contract Documents and not by others shall be done as if required by all. This Contract shall
supersede any prior agreement of the parties.
F. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE. Each and every
provision of law required to be included in these Contract Documents shall be deemed to be
included in these Contract Documents. The Contractor shall comply with all requirements of
applicable federal, state and local laws, rules and regulations, including, but not limited to, the
provisions of the California Labor Code and California Public Contract Code which are applicable
to this Work.
G. INDEMNIFICATION. Contractor shall provide indemnification and defense as set forth in the
General Conditions.
H. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in
accordance with the Labor Code which such rates shall be made available at the City’s
Administrative Office or may be obtained online at dir.ca.gov and which must be posted at the job
site.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
Contract - 3
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on
the day and year above written.
CITY OF ARCADIA
By:
Dominic Lazzaretto
City Manager
GRBCCON, INC.
By:
Signature
Print Name and Title
Attest:
By:
City Clerk
By:
Signature
Print Name and Title
Approved as to Form:
Michael J. Maurer
City Attorney
(CONTRACTOR’S SIGNATURE MUST BE NOTARIZED AND CORPORATE SEAL AFFIXED)
Contract - 4
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally
appeared , who proved to me on the basis of satisfactory
evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me
that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s)
on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph
is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT
Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
Contract - 5
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally
appeared , who proved to me on the basis of satisfactory
evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me
that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s)
on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph
is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document
and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT
Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above