HomeMy WebLinkAboutItem 8g - Accept City Hall Lawn Fence Installation Project
STAFF REPORT
PUBLIC WORKS SERVICES DEPARTMENT
DATE: November 17, 2026
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Public Works Services Director
By: Leonel Martin, Public Works Project Manager
SUBJECT: ACCEPT ALL WORK PERFORMED BY MDJ MANAGEMENT, LLC FOR THE
CITY HALL LAWN FENCE INSTALLATION PROJECT AS COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On April 7, 2026, the City Council approved a contract with MDJ Management, LLC in
the amount of $125,236.16, with a 10% contingency for the City Hall Lawn Fence
Installation Project. The terms and conditions of this project have been complied
with, and the work has been performed to the satisfaction of the Project Manager for
a total project cost of $137,231.57. This amount reflects the approved contract of
$125,236.16, plus one change order totaling $11,995.41, or 9.6% more than the
approved contract amount.
It is recommended that the City Council accept all work performed by MDJ
Management, LLC, for the City Hall Lawn Fence Installation Project as complete and
authorize the final payment to be made in accordance with the contract documents,
subject to the retention of $6,261.81.
BACKGROUND
The City of Arcadia frequently hosts events at the City Hall Lawn, including the
Community Camp Out, Moon Festival, and Concerts and Movies in the Park. These
events attract hundreds, and sometimes, thousands of attendees, making the City
Hall Lawn a central gathering place for residents to connect, celebrate local culture,
and engage in civic life. These events also support local businesses and strengthen
Accept City Hall Lawn Fence Installation Project
November 17, 2026
Page 2 of 3
community identity by activating a prominent public space along Huntington Drive,
making the Civic Center more vibrant and welcoming.
The City Hall Lawn is located along Huntington Drive, a high-traffic roadway that
carries a significant volume of daily drivers. Community events held at the City Hall
Lawn regularly attract families, children, and large crowds. To provide a safe and
comfortable experience for event attendees and users of the City Hall Lawn, the
Public Works Services Department (“PWSD”) would install temporary K-rail barriers
along the roadway during events. The barriers created a protective buffer between
the lawn and passing vehicles, and helped define clear event boundaries. The
temporary installation of K-rail barriers for community events at City Hall Lawn from
May 2025 through October 2025 was approximately $35,000, which included the
installation, removal, and rental costs, but not the staff time required to coordinate
delivery, placement, and removal of the barriers. Installing a permanent fence along
the Huntington Drive side of the City Hall Lawn was necessary to provide a lasting
safety barrier for event attendees and reduce the ongoing costs of installing and
removing barriers each year.
DISCUSSION
On April 7, 2026, the City Council approved a contract with MDJ Management, LLC,
for the City Hall Lawn Fence Installation Project. As part of this project, approximately
660 linear feet of four-foot-tall wrought iron fencing was installed along the
Huntington Drive side of the lawn. The custom-designed wrought iron fence features
a bronze powder-coat finish to complement the appearance of the City Hall Lawn
area.
After the fence was installed, staff found that the new fence obstructed visibility for
vehicles exiting the northeast Police Department parking lot. To resolve this, the
contract scope was adjusted to reinstall the fence at an angle rather than along the
grass edge. A complete summary of the project change order is provided below.
CCO Description Amount
1. Reconfigure 70 linear feet of wrought iron fencing $11,995.41
Accept City Hall Lawn Fence Installation Project
November 17, 2026
Page 3 of 3
All terms and conditions of the contract have been complied with, and the work has
been performed to the satisfaction of the Project Manager. MDJ Management, LLC
completed the work as defined in the project plans and specifications, in an efficient
and timely manner.
ENVIRONMENTAL ANALYSIS
The Project is considered a Class 1 Exemption as defined in Section 15301(a) “Existing
Facilities” projects of the California Environmental Quality Act (“CEQA”), which
exempts projects consisting of the minor alteration of existing public structures.
FISCAL IMPACT
This project was not budgeted as part of the Capital Improvement Program Budget;
therefore, a budget appropriation from the Capital Outlay Fund in the amount of
$137,759.78 was requested and approved by the City Council on April 7, 2026. The
total cost for the City Hall Lawn Fence Installation Project is $137,231.57. This amount
reflects the approved contract of $125,236.16, plus a change order totaling
$11,995.41, or 9.6% more than the approved contract amount. The total cost is within
the budget appropriation provided for the project.
RECOMMENDATION
It is recommended that the City Council determine that this project is exempt under
the California Environmental Quality Act (“CEQA”); and accept all work performed by
MDJ Management, LLC, for the City Hall Lawn Fence Installation Project as complete
and authorize the final payment to be made in accordance with the contract
documents, subject to the retention of $6,261.81.