HomeMy WebLinkAboutItem 8b - Peck Well Motor Control Center Replacement STAFF REPORT PUBLIC WORKS SERVICES DEPARTMENT DATE: November 17, 2026 TO: Honorable Mayor and City Council FROM: Paul Cranmer, Assistant City Manager/Public Works Services Director By: Tiffany Lee, Principal Civil Engineer SUBJECT: RESOLUTION NO. 7716 AMENDING THE FISCAL YEAR 2024-25 CAPITAL IMPROVEMENT PROGRAM BUDGET, AUTHORIZING A SUPPLEMENTAL BUDGET APPROPRIATION FOR THE REPLACEMENT OF THE MOTOR CONTROL CENTER AND VOLTAGE CONVERSION AT PECK WELL IN THE AMOUNT OF $541,484, OFFSET BY A REDUCTION IN THE WATER FUND; AND APPROVE A CONTRACT WITH PACIFIC HYDROTECH CORPORATION FOR THE REPLACEMENT OF THE MOTOR CONTROL CENTER AND VOLTAGE CONVERSION PROJECT AT PECK WELL IN THE AMOUNT OF $892,900, WITH A 10% CONTINGENCY CEQA: Exempt Recommendation: Adopt and Approve SUMMARY The Public Works Services Department (“PWSD”) is responsible for the daily operation of City wells and the water distribution system. City wells are regularly inspected to ensure the wells are functioning properly and to identify any issues that require repair. The Fiscal Year 2024-25 Capital Improvement Program (“CIP”) Budget provided for well inspection and rehabilitation of Peck Well and included the replacement of the motor control center and voltage conversion of Peck Well. To date, the City Council has authorized agreements for the design of the Motor Control Center and Voltage Conversion at Peck Well and for the inspection and rehabilitation of Peck Well. Following these two expenditures, $440,706 remains available in the CIP budget for the Replacement of the Motor Control Center and Voltage Conversion Project, which is essential to complete the maintenance of this critical water well. Award Peck Well Motor Control Center Replacement and Voltage Conversion Project November 17, 2026 Page 2 of 5 To ensure the City is receiving the most competitive prices and quality service for this work, a formal bid process was conducted. Pacific Hydrotech Corporation submitted the lowest responsive bid. However, the total project cost exceeds the available project balance. Therefore, it is recommended that the City Council adopt Resolution No. 7716 amending the Fiscal Year 2024-25 CIP Budget, authorizing a supplemental budget appropriation for the replacement of the motor control center and the voltage conversion at Peck Well in the amount of $541,484, offset by a reduction in the Water Fund. It is further recommended that the City Council authorize and direct the City Manager to execute a contract with Pacific Hydrotech Corporation for the Replacement of the Motor Control Center and Voltage Conversion Project at Peck Well in the amount of $892,900, with a 10% contingency. BACKGROUND The City operates and maintains 10 groundwater wells that produce approximately 14,000 acre-feet of water annually. Regular inspection and maintenance are essential to preserve well efficiency, maximize production capacity, and reduce the risk of unexpected failures. City of Arcadia wells are inspected regularly to ensure they are functioning properly and to identify any issues requiring repair. Regular inspections and maintenance of Peck Well have revealed that the existing motor control center, installed in 1992, has reached the end of its useful life. Replacement parts for the existing equipment have become obsolete and are no longer readily available. Consequently, a failure of the motor control center could result in an extended shutdown of the well due to the unavailability of replacement parts. In addition, the motor at Peck Well currently operates at 2,400 volts, presenting significant electrical safety hazards, and requiring highly specialized and certified electrical personnel to perform work on the motor control center; a voltage conversion is also necessary. With the PFAS treatment system that is to be installed at the site, an extended shutdown of Peck Well resulting from a motor control center failure could adversely affect the treatment system operations and jeopardize the City’s ability to maintain continuous treatment. Peck Well plays a critical role in the City’s water system, supplying more than 40% of the groundwater to Zone 4, in the southern portion of the City. Replacing the existing motor control center and converting the power supply Award Peck Well Motor Control Center Replacement and Voltage Conversion Project November 17, 2026 Page 3 of 5 from 2,400 volts to 480 volts, three-phase power, is necessary to improve electrical safety, enhance system reliability, and ensure the well’s long-term operability. These improvements will also help maintain the treatment system’s design capacity and efficiency. DISCUSSION A Notice Inviting Bids for the Replacement of the Motor Control Center and Voltage Conversion at Peck Well was published in accordance with City Council Resolution No. 7483, and bid packages were distributed to contractors that perform this type of work. On September 29, 2026, the City Clerk received two sealed bids with the following results: Bidder Location Bid Amount Pacific Hydrotech Corporation Murrieta, CA $ 892,900 Minako America Corporation Gardena, CA $ 1,688,700 Although the notice inviting bids was distributed to qualified contractors and published on the City’s website, only two bids were received. Staff contacted contractors that received the notice to inquire about their decision not to submit bids; two firms indicated that they had too many projects underway and did not have enough staff to perform the work, and other firms contacted did not respond despite multiple outreach attempts. The two bid documents received were reviewed for content and the contractor’s background was also investigated. Based on the review, it has been determined that Pacific Hydrotech Corporation is the lowest responsive bidder for this work and is qualified to complete the project as defined in the bid documents. Pacific Hydrotech Corporation has successfully completed similar projects for the Cities of Thousand Oaks and Tustin, Suburban Water System, Golden State Water District, and Irvine Ranch Water District. Award Peck Well Motor Control Center Replacement and Voltage Conversion Project November 17, 2026 Page 4 of 5 ENVIRONMENTAL ANALYSIS This project is categorically exempt from the California Environmental Quality Act (“CEQA”) pursuant to Class 2, Section 15302(c), which applies to the replacement or reconstruction of an existing utility system and/or facilities involving negligible or no expansion of capacity. The replacement of an existing motor control center and voltage conversion at an existing potable water supply well qualifies for this categorical exemption. FISCAL IMPACT Funds in the amount of $950,000 were budgeted in the Fiscal Year 2024-25 CIP for the Well Inspection and Rehabilitation Project and included the replacement of the motor control center and voltage conversion of Peck Well. The project funding consists of $600,000 in Water Funds and $350,000 in American Rescue Plan Act (“ARPA)” Funds. On September 16, 2025, the City Council approved a Professional Services Agreement with Linkture Corp. for the design of the motor control center and voltage conversion at Peck Well, in the amount of $50,000. On August 18, 2026, the City Council approved a contract with General Pump Company, Inc. for the well inspection and rehabilitation of Peck Well in the amount of $417,540, plus a 10% contingency, for a total project amount of $459,294. Following these two expenditures, $440,706 remains available in the CIP budget for the replacement of the Motor Control Center and Voltage Conversion Project. The total cost for the replacement of the Motor Control Center and Voltage Conversion Project is $892,900. With a 10% contingency, the total project cost is $982,190. After applying the remaining available CIP funding of $440,706, a supplemental budget appropriation of $541,484 is needed to provide sufficient funding to complete the replacement of the Motor Control Center and Voltage Conversion Project at Peck Well. Sufficient funds are available in the Water Fund to cover these additional costs. The high project cost is primarily attributable to the current market costs of the specified electrical equipment and installation, particularly the switchboard/motor control center and associated power distribution work. The switchboard and motor Award Peck Well Motor Control Center Replacement and Voltage Conversion Project November 17, 2026 Page 5 of 5 control center also have an estimated lead time of approximately 36–40 weeks, which reflects current supply-chain conditions and the specialized nature of the equipment. Additional factors contributing to the higher costs include specialized electrical equipment, prevailing-wage labor, installation and integration with the existing electrical system, and the complexity and coordination with SCE required to perform the work at an operating well facility. RECOMMENDATION It is recommended that the City Council determine this project is exempt under the California Environmental Quality Act (“CEQA”); and adopt Resolution No. 7716 amending the Fiscal Year 2024-25 Capital Improvement Program Budget, authorizing a supplemental budget appropriation for the replacement of the motor control center and the voltage conversion at Peck Well in the amount of $541,484, offset by a reduction in the Water Fund. It is further recommended that the City Council authorize and direct the City Manager to execute a contract with Pacific Hydrotech Corporation for the Replacement of the Motor Control Center and Voltage Conversion Project at Peck Well in the amount of $892,900, with a 10% contingency. Attachments: Resolution No. 7716 Exhibit “A”- Project Location Map Proposed Contract 1 RESOLUTION NO. 7716 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ARCADIA, CALIFORNIA, AMENDING THE FISCAL YEAR 2024-25 CAPITAL IMPROVEMENT PROGRAM BUDGET, AUTHORIZING A SUPPLEMENTAL BUDGET APPROPRIATION FOR THE REPLACEMENT OF THE MOTOR CONTROL CENTER AND VOLTAGE CONVERSION AT PECK WELL IN THE AMOUNT OF $541,484, OFFSET BY A REDUCTION IN THE WATER FUND WHEREAS, as part of the Fiscal Year 2024-25 Capital Improvement Program Budget, $950,000 was budgeted for the Peck Well Inspection and Rehabilitation Project; and WHEREAS, the replacement of the motor control center and voltage conversion of Peck Well was included as part of the Peck Well Inspection and Rehabilitation Project; and WHEREAS, inspections and maintenance of Peck Well revealed that the existing motor control center, has reached the end of its useful life; and WHEREAS, the well motor at Peck Well currently operates at 2,400 volts, presenting significant electrical safety hazards and requiring highly specialized, certified electrical personnel to perform work on the motor control center; and WHEREAS, replacing the existing motor control center and converting the power supply from 2,400 volts to 480 volts, three-phase power, is necessary to improve electrical safety, enhance system reliability, and ensure the well’s long-term operability; and 2 WHEREAS, the total cost of the Replacement of the Motor Control Center and Voltage Conversion at Peck Well is $892,900; and WHEREAS, including the requested 10% contingency of $89,290, the total project cost for the Replacement of Motor Control Center and Voltage Conversion at Peck Well is $982,190; and WHEREAS, funding in the amount of $440,706 is available in the Fiscal Year 2024-25 CIP budget for the Replacement of Motor Control Center and Voltage Conversion at Peck Well; and WHEREAS, an amendment to the Fiscal Year 2024-25 Capital Improvement Program Budget authorizing a supplemental appropriation in the amount of $541,484 is needed for the Replacement of Motor Control Center and Voltage Conversion at Peck Well; and WHEREAS, the supplemental budget appropriation will be offset by a reduction in the Water Fund; and WHEREAS, the City Manager has certified that there are sufficient reserves available in the Water Fund. NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF ARCADIA, CALIFORNIA, DOES FIND, DETERMINE AND RESOLVE AS FOLLOWS: SECTION 1. The sum of Five Hundred Forty-One Thousand, Four Hundred Eighty-Four Dollars ($541,484) is hereby appropriated in the Capital Improvement 3 Program Budget for the forgoing purposes, offset with an equal reduction in the Water Fund. SECTION 2. The City Clerk shall certify to the adoption of this Resolution. Passed, approved and adopted this 17th day of November, 2026. Mayor of the City of Arcadia ATTEST: City Clerk APPROVED AS TO FORM: Michael J. Maurer City Attorney CITY OF ARCADIA REPLACEMENT OF MOTOR CONTROL CENTER AND VOLTAGE CONVERSION AT PECK WELL PROJECT NO.: 72863625 BETWEEN CITY OF ARCADIA AND PACIFIC HYDROTECH CORPORATION CONTRACT Contract - 1 CONTRACT FOR THE CITY OF ARCADIA This CONTRACT, No. ________ is made and entered into this ____ day of _______, ______, by and between City of Arcadia, sometimes hereinafter called “City,” and PACIFIC HYDROTECH CORPORATION, sometimes hereinafter called “Contractor.” WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these presents do covenant and agree with each other as follows: A. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated in the Contract, and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all of the Work required in strict compliance with the Contract Documents as specified in Article 5, below, for the following Project: Replacement of Motor Control Center and Voltage Conversion at Peck Well / Project No. 72863625 The Contractor and its surety shall be liable to the City for any damages arising as a result of the Contractor’s failure to comply with this obligation. B. TIME FOR COMPLETION. Time is of the essence in the performance of the Work. The Work shall be commenced on the date stated in the City’s Notice to Proceed. The Contractor shall complete all Work required by the Contract Documents within Sixty (60) calendar days from the commencement date stated in the Notice to Proceed. By its signature hereunder, Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work. C. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs, the sum of EIGHT HUNDRED NINETY- TWO THOUSAND, NINE HUNDRED DOLLARS AND NO CENTS ($892,900.00). Payment shall be made as set forth in the General Conditions. D. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85, it is agreed that the Contractor will pay the City the sum set forth in Special Conditions, Article 1.11 for each and every calendar day of delay beyond the time prescribed in the Contract Documents for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this is not paid, the Contractor agrees the City may deduct that amount from any money due or that may become due the Contractor under the Contract. This Article does not exclude recovery of other damages specified in the Contract Documents. E. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the following: Notice Inviting Bids Instructions to Bidders Bid Form Bid Bond Designation of Subcontractors Information Required of Bidders Non-Collusion Declaration Form Iran Contracting Act Certification Public Works Contractor Registration Certification Contract - 2 Performance Bond Payment (Labor and Materials) Bond General Conditions Special Conditions Technical Specifications Addenda Plans and Drawings Standard Specifications for Public Works Construction “Greenbook”, latest edition, Except Sections 1-9 Applicable Local Agency Standards and Specifications, as last revised Approved and fully executed change orders Any other documents contained in or incorporated into the Contract The Contractor shall complete the Work in strict accordance with all of the Contract Documents. All of the Contract Documents are intended to be complementary. Work required by one of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties. F. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE. Each and every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, including, but not limited to, the provisions of the California Labor Code and California Public Contract Code which are applicable to this Work. G. INDEMNIFICATION. Contractor shall provide indemnification and defense as set forth in the General Conditions. H. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in accordance with the Labor Code which such rates shall be made available at the City’s Administrative Office or may be obtained online at dir.ca.gov and which must be posted at the job site. [REMAINDER OF PAGE LEFT INTENTIONALLY BLANK] Contract - 3 IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on the day and year above written. CITY OF ARCADIA By: Dominic Lazzaretto City Manager PACIFIC HYDROTECH CORPORATION By: Signature Print Name and Title Attest: By: City Clerk By: Signature Print Name and Title Approved as to Form: Michael J. Maurer City Attorney (CONTRACTOR’S SIGNATURE MUST BE NOTARIZED AND CORPORATE SEAL AFFIXED) Contract - 4 Notary Acknowledgment A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. STATE OF CALIFORNIA COUNTY OF ______________ On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal. Signature of Notary Public OPTIONAL Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document. CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT  Individual  Corporate Officer Title(s) Title or Type of Document  Partner(s)  Limited  General Number of Pages  Attorney-In-Fact  Trustee(s)  Guardian/Conservator Date of Document  Other: Signer is representing: Name Of Person(s) Or Entity(ies) Signer(s) Other Than Named Above Contract - 5 Notary Acknowledgment A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. STATE OF CALIFORNIA COUNTY OF ______________ On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal. Signature of Notary Public OPTIONAL Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document. CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT  Individual  Corporate Officer Title(s) Title or Type of Document  Partner(s)  Limited  General Number of Pages  Attorney-In-Fact  Trustee(s)  Guardian/Conservator Date of Document  Other: Signer is representing: Name Of Person(s) Or Entity(ies) Signer(s) Other Than Named Above