HomeMy WebLinkAboutItem 9g - Accept Stormdrain Repair Project
STAFF REPORT
PUBLIC WORKS SERVICES DEPARTMENT
DATE: December 1, 2026
TO: Honorable Mayor and City Council
FROM: Paul Cranmer, Assistant City Manager / Public Works Services Director
By: Michael Kwok, Associate Civil Engineer
SUBJECT: ACCEPT ALL WORK PERFORMED BY GRBCON, INC. FOR THE
STORMDRAIN REPAIR PROJECT AS COMPLETE
CEQA: Exempt
Recommendation: Approve
SUMMARY
On April 21, 2026, the City Council approved a contract with GRBCON, Inc. in the
amount of $144,325 for the Stormdrain Repair Project. The terms and conditions of
this project have been complied with and the work has been performed to the
satisfaction of the Project Manager for a total project cost of $143,000. This amount
reflects the original contract amount of $144,325, minus contract change orders
totaling $1,325, or 0.9% less than the original contract amount.
It is recommended that the City Council accept all work performed by GRBCON, Inc.
for the Stormdrain Repair Project as complete, and authorize the final payment to be
made in accordance with the contract documents, subject to the retention of $7,150.
BACKGROUND
The Public Works Services Department (“PWSD”) owns and maintains various catch
basins and stormdrain lines throughout the City. During previous storms, staff
observed that water was unable to properly drain from a curb opening catch basin
on Fallen Leaf Road. City crews located the pipe in this catch basin and attempted to
perform an inspection utilizing Closed Circuit Television (“CCTV”) equipment. The
CCTV camera could not get through the pipe, which indicated that the pipe was
damaged and likely collapsed. Replacement of the damaged pipe with a new
Accept Stormdrain Repair Project
December 1, 2026
Page 2 of 3
reinforced concrete pipe was necessary to restore proper stormwater flow in that
area and eliminate potential flooding.
DISCUSSION
On April 21, 2026, the City Council approved a contract with GRBCON, Inc. for the
Stormdrain Repair Project. The work performed included replacement of the existing
damaged 18-inch stormdrain pipe on Fallen Leaf Road. During the course of work,
the City received credits for reductions in quantities of material needed to complete
the project. Below is a breakdown of total contract change orders.
CCO Description Amount
1. Deleted (5 LF) – Remove Existing Stormdrain
Pipe and Replace with New 18” RCP Pipe ($1,325)
Total ($1,325)
The change orders listed reduced the overall contract amount by $1,325, or 0.9% less
than the original contract amount. All terms and conditions of this contract have
been complied with, and the work has been performed to the satisfaction of the
Project Manager. GRBCON, Inc. completed the work as defined in the project plans
and specifications in an efficient and timely manner.
ENVIRONMENTAL ANALYSIS
This project involves the replacement and minor alteration of an existing utility
system with no expansion of the system, and therefore, qualifies as a Class 2
categorical exemption per Section 15302(2) of the California Environmental Quality
Act (“CEQA”).
FISCAL IMPACT
Gas Tax (HUTA) Funds in the amount of $100,000 were budgeted for the Stormdrain
Repair Project, in the FY 2025-26 Capital Improvement Program. However, these
funds were insufficient to complete the project. Therefore, on April 21, 2026, the City
Council approved a supplemental budget appropriation of $58,757.50 from the
Capital Outlay Fund bringing the total funds available to $158,757,50.
Accept Stormdrain Repair Project
December 1, 2026
Page 3 of 3
The total construction cost for this project is $143,000. The total cost reflects the
original contract amount of $144,325, minus change orders totaling $1,325, or 0.9%
less than the original contract amount. Therefore, sufficient funds are available.
RECOMMENDATION
It is recommended the City Council determine that this project is exempt under the
California Environmental Quality Act (“CEQA”); and accept all work performed by
GRBCON, Inc. for the Stormdrain Repair Project as complete, and authorize a final
payment to be made in accordance with the contract documents, subject to the
retention of $7,150.